Question

Required information [The following information applies to the questions displayed belowj In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows 2018 $2, 100, 000 4, 900, 000 2, 200, 000 1, 900, 000 2019 2020 2, 450, 000 $2, 695, 000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2, 450, 000 2, 350, 000 2, 300, 000 5, 450, 000 5, 800, 000 Westgate recognizes revenue over time according to percentage of completion Required . Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.) 2018 2019 2020 Revenue Gross profit (loss)

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed belowj In 2018, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.j In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.j In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows 2019 $2,490,000 $3,984,000 $2,008,600 1,826,000 2,030,000 4,444,000 3,526,000 3,900,000 2018 5,810,000 1,815,000 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,285,000...

  • Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction...

    Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2.000.000 4,000,000 3,600,000 4.000.000 4.600.000...

  • Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000...

  • ! Required information [The following information applies to the questions displayed below.] In 2018, the Westgate...

    ! Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,596,000 4,000,000 3,364,000...

  • Required information [The following information applies to the questions displayed below.) In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2, 259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2, 291, 000 5, 609,000 2, 110,000 1, 855,...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $2,072,000 $2,738,000 2,590, 000 2,650, 000 $2,849,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 5,328,000 2,160,000 1,880,000 0...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $2, 291, 000 $3, 555, 000 2, 054, 000 3, 736, 000 $2, 259, 400 Estimated costs to complete as of year-end Billings during the year Cash...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered intoo a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $4,032,000 1,764,000 4,596,000 4,000,000 $2,604,000 5,796,000 2,040,000 1,820,000 $1,940,400 3,364,000 4,180,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT