Question

On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated...

On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows:

January 2, 2020 $ 599000
September 1, 2020 1801200
December 31, 2020 1801200
March 31, 2021 1801200
September 30, 2021 1220000


Vaughn Manufacturing borrowed $3230000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company also had $13680000 in 7% bonds outstanding in 2020 and 2021.

The interest capitalized for 2020 was:

$159600

$479060

$478800

$119940

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Option 4th is correct. i.e $119,940

Interest Capitalized for 2020
Date Expenditure Weight Average
02-Jan-20               5,99,000 12/12                   5,99,000
01-Sep-20             18,01,200 4/12                   6,00,400
31-Dec-20             18,01,200 0/12                              -  
Accumulated   Expenditures             42,01,400                 11,99,400
Interest Capitalized for 2020 = 11,99,400 x 10% = 1,19,940
Add a comment
Know the answer?
Add Answer to:
On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 609000 1812000 1812000 812000 198000 1 1 Bonita Industries borrowed $3290000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period....

  • On January 2, 2020, Marigold Corp. began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Marigold Corp. began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 592000 1806000 1806000 1806000 1219000 Marigold Corp. borrowed $3330000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...

  • On January 2, 2017, Sunland Company began construction of a new citrus processing plant. The automated...

    On January 2, 2017, Sunland Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows: January 2, 2017 $ 597000 September 1, 2017 1812000 December 31, 2017 1812000 March 31, 2018 1812000 September 30, 2018 1215000 Sunland Company borrowed $3370000 on a construction loan at 10% interest on January 2, 2017. This loan was outstanding during the construction period. The company...

  • On January 2, 2017, Marigold Corp. began construction of a new citrus processing plant. The automated...

    On January 2, 2017, Marigold Corp. began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows: January 2, 2017 September 1, 2017 December 31, 2017 March 31, 2018 September 30, 2018 592000 1812000 1812000 1812000 1201000 Ma gold Corp. borrowed $3280000 on a construction loan at 12% interest on an a y 2 2017. This loan was outstanding during bonds outstanding in...

  • On January 1, 2021, Jenner Inc. began construction of an automated cattle feeder system. The system...

    On January 1, 2021, Jenner Inc. began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 235,000 September 1, 2021 $ 342,000 December 31, 2021 $ 342,000 March 31, 2022 $ 342,000 September 30, 2022 $ 235,000 Jenner borrowed $764,000 on a construction loan at 7% interest on January 1, 2021. This loan was outstanding throughout the construction period....

  • Please show how to get the answer as well! On January 2, 2017, Oriole Company began...

    Please show how to get the answer as well! On January 2, 2017, Oriole Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows: January 2, 2017 September 1, 2017 December 31, 2017 March 31, 2018 September 30, 2018 603000 1810800 1810800 1810800 1218000 Oriole Company borrowed $3300000 on a construction loan at 10% nterest on January 2. 2017. This loan...

  • J pour Save Answer On January 1, 2021 Kendall Inc began construction of an automated cattle...

    J pour Save Answer On January 1, 2021 Kendall Inc began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2022 Expenditures on the project were as follows: January 1, 2021 270.000 September 1, 2021 384 000 December 31, 2021 384 000 March 31 2022 334000 September 30, 2022 270.000 Kendall borrowed $778,000 on a construction loan at 8% Interest on January 1, 2021 This loan was outstanding throughout the construction...

  • On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The...

    On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The system was finished and ready for use on September 30, 2020. Expenditures on the project were as follows: January 2, 2019                       $750,000          July 1, 2019                            $600,000          December 31, 2019                 $450,000          March 31, 2020                       $450,000          September 30, 2020                $300,000              The company borrowed $900,000 on a construction loan at 10% interest on January 2, 2019. In addition, the company had $400,000 in 12% bonds and $800,000 in 7.5% bonds outstanding...

  • Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1. 2018. This loan was outstanding throughout the construction period. The...

  • Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1 2018. This loan was outstanding throughout the construction period. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT