On January 2, 2020, Vaughn Manufacturing began construction of a
new citrus processing plant. The automated plant was finished and
ready for use on September 30, 2021. Expenditures for the
construction were as follows:
January 2, 2020 | $ 599000 |
September 1, 2020 | 1801200 |
December 31, 2020 | 1801200 |
March 31, 2021 | 1801200 |
September 30, 2021 | 1220000 |
Vaughn Manufacturing borrowed $3230000 on a construction loan at
10% interest on January 2, 2020. This loan was outstanding during
the construction period. The company also had $13680000 in 7% bonds
outstanding in 2020 and 2021.
The interest capitalized for 2020 was:
$159600
$479060
$478800
$119940
Answer:
Option 4th is correct. i.e $119,940
Interest Capitalized for 2020 | |||
Date | Expenditure | Weight | Average |
02-Jan-20 | 5,99,000 | 12/12 | 5,99,000 |
01-Sep-20 | 18,01,200 | 4/12 | 6,00,400 |
31-Dec-20 | 18,01,200 | 0/12 | - |
Accumulated Expenditures | 42,01,400 | 11,99,400 | |
Interest Capitalized for 2020 = 11,99,400 x 10% = 1,19,940 | |||
On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated...
On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 609000 1812000 1812000 812000 198000 1 1 Bonita Industries borrowed $3290000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period....
On January 2, 2020, Marigold Corp. began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 592000 1806000 1806000 1806000 1219000 Marigold Corp. borrowed $3330000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...
On January 2, 2017, Sunland Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows: January 2, 2017 $ 597000 September 1, 2017 1812000 December 31, 2017 1812000 March 31, 2018 1812000 September 30, 2018 1215000 Sunland Company borrowed $3370000 on a construction loan at 10% interest on January 2, 2017. This loan was outstanding during the construction period. The company...
On January 2, 2017, Marigold Corp. began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows: January 2, 2017 September 1, 2017 December 31, 2017 March 31, 2018 September 30, 2018 592000 1812000 1812000 1812000 1201000 Ma gold Corp. borrowed $3280000 on a construction loan at 12% interest on an a y 2 2017. This loan was outstanding during bonds outstanding in...
On January 1, 2021, Jenner Inc. began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 235,000 September 1, 2021 $ 342,000 December 31, 2021 $ 342,000 March 31, 2022 $ 342,000 September 30, 2022 $ 235,000 Jenner borrowed $764,000 on a construction loan at 7% interest on January 1, 2021. This loan was outstanding throughout the construction period....
Please show how to get the answer as well! On January 2, 2017, Oriole Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows: January 2, 2017 September 1, 2017 December 31, 2017 March 31, 2018 September 30, 2018 603000 1810800 1810800 1810800 1218000 Oriole Company borrowed $3300000 on a construction loan at 10% nterest on January 2. 2017. This loan...
J pour Save Answer On January 1, 2021 Kendall Inc began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2022 Expenditures on the project were as follows: January 1, 2021 270.000 September 1, 2021 384 000 December 31, 2021 384 000 March 31 2022 334000 September 30, 2022 270.000 Kendall borrowed $778,000 on a construction loan at 8% Interest on January 1, 2021 This loan was outstanding throughout the construction...
On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The system was finished and ready for use on September 30, 2020. Expenditures on the project were as follows: January 2, 2019 $750,000 July 1, 2019 $600,000 December 31, 2019 $450,000 March 31, 2020 $450,000 September 30, 2020 $300,000 The company borrowed $900,000 on a construction loan at 10% interest on January 2, 2019. In addition, the company had $400,000 in 12% bonds and $800,000 in 7.5% bonds outstanding...
Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1. 2018. This loan was outstanding throughout the construction period. The...
Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1 2018. This loan was outstanding throughout the construction period. The...