Question

J pour Save Answer On January 1, 2021 Kendall Inc began construction of an automated cattle feeder system. The system was fin
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Date Amount Period Weighted average amount
January 1 2021 270000 12/12 270000
September 1 2021 384000 4/12 128000
December 31 2021 384000 0 0
Total 398000
Weighted average amount 398000
X Interest rate 8%
Interest capitalized for 2021 31840
Option A $31,840 is correct
Add a comment
Know the answer?
Add Answer to:
J pour Save Answer On January 1, 2021 Kendall Inc began construction of an automated cattle...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2021, Jenner Inc. began construction of an automated cattle feeder system. The system...

    On January 1, 2021, Jenner Inc. began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 235,000 September 1, 2021 $ 342,000 December 31, 2021 $ 342,000 March 31, 2022 $ 342,000 September 30, 2022 $ 235,000 Jenner borrowed $764,000 on a construction loan at 7% interest on January 1, 2021. This loan was outstanding throughout the construction period....

  • Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1. 2018. This loan was outstanding throughout the construction period. The...

  • Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1 2018. This loan was outstanding throughout the construction period. The...

  • On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The...

    On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The system was finished and ready for use on September 30, 2020. Expenditures on the project were as follows: January 2, 2019                       $750,000          July 1, 2019                            $600,000          December 31, 2019                 $450,000          March 31, 2020                       $450,000          September 30, 2020                $300,000              The company borrowed $900,000 on a construction loan at 10% interest on January 2, 2019. In addition, the company had $400,000 in 12% bonds and $800,000 in 7.5% bonds outstanding...

  • On January 3, 20X5, Brighton, Inc. began construction of an automated cattle feeder system.   Expenditures on...

    On January 3, 20X5, Brighton, Inc. began construction of an automated cattle feeder system.   Expenditures on the project during 20X5 were as follows:                     January 2, 20X5         $800,000                             September 1, 20X5         $300,000                            December 31, 20X5         $300,000         The company borrowed $750,000 on a construction loan at 12% interest on January 2, 20X5. The company also had two other loans outstanding at the beginning of 20X5 of $600,000 at 7% and $200,000 at 10%. Both loans were outstanding all year long....

  • On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 599000 September 1, 2020 1801200 December 31, 2020 1801200 March 31, 2021 1801200 September 30, 2021 1220000 Vaughn Manufacturing borrowed $3230000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,740,000 1,380,000 1, 580,000 1, 380,000 387,000 720,000 1, 017, 000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a...

  • On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $1,850,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $4,000,000, 14% bonds $1,000,000, 10% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 800,000 March 31 1,400,000 June 30 1,040,000 September 30 800,000...

  • On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,000,000 at 13% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: points $5.829.oe. 17% bonds $3.880.880.13% long-term note Construction expenditures incurred during 2021 were as follows: $ January 1 March 31 June 30 September 30 December 31 820,000 1,420.000...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,420,000 1,140,000 1,340,000 1,140,000 351,000 684,000 981,000 On January 1, 2021, the company obtained a $3,900,000 construction loan with a 12% interest rate. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT