Question

On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The...

On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The system was finished and ready for use on September 30, 2020. Expenditures on the project were as follows:

January 2, 2019                       $750,000         

July 1, 2019                            $600,000         

December 31, 2019                 $450,000         

March 31, 2020                       $450,000         

September 30, 2020                $300,000

            

The company borrowed $900,000 on a construction loan at 10% interest on January 2, 2019. In addition, the company had $400,000 in 12% bonds and $800,000 in 7.5% bonds outstanding during 2019 and 2020.

Required:

1.         Calculate the following items for 2019 and 2020:

  1. Average accumulated expenditures
  2. Amount of interest capitalized and expensed.
  3. Balance of the Cattle Feeder System account.

2.         Prepare the journal entry to capitalize the interest at December 31, 2019

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • On January 1, 2021, Jenner Inc. began construction of an automated cattle feeder system. The system...

    On January 1, 2021, Jenner Inc. began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 235,000 September 1, 2021 $ 342,000 December 31, 2021 $ 342,000 March 31, 2022 $ 342,000 September 30, 2022 $ 235,000 Jenner borrowed $764,000 on a construction loan at 7% interest on January 1, 2021. This loan was outstanding throughout the construction period....

  • Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1. 2018. This loan was outstanding throughout the construction period. The...

  • Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1 2018. This loan was outstanding throughout the construction period. The...

  • On January 3, 20X5, Brighton, Inc. began construction of an automated cattle feeder system.   Expenditures on...

    On January 3, 20X5, Brighton, Inc. began construction of an automated cattle feeder system.   Expenditures on the project during 20X5 were as follows:                     January 2, 20X5         $800,000                             September 1, 20X5         $300,000                            December 31, 20X5         $300,000         The company borrowed $750,000 on a construction loan at 12% interest on January 2, 20X5. The company also had two other loans outstanding at the beginning of 20X5 of $600,000 at 7% and $200,000 at 10%. Both loans were outstanding all year long....

  • J pour Save Answer On January 1, 2021 Kendall Inc began construction of an automated cattle...

    J pour Save Answer On January 1, 2021 Kendall Inc began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2022 Expenditures on the project were as follows: January 1, 2021 270.000 September 1, 2021 384 000 December 31, 2021 384 000 March 31 2022 334000 September 30, 2022 270.000 Kendall borrowed $778,000 on a construction loan at 8% Interest on January 1, 2021 This loan was outstanding throughout the construction...

  • On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 599000 September 1, 2020 1801200 December 31, 2020 1801200 March 31, 2021 1801200 September 30, 2021 1220000 Vaughn Manufacturing borrowed $3230000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...

  • On January 1, 2017, UAE Inc. began construction of an automated car system. The system was...

    On January 1, 2017, UAE Inc. began construction of an automated car system. The system was finished and ready for use on 12-31 2017. Expenditures on the project were as follows January 1, 2017 April 1, 2017 July 1, 2017 December 31, 2017 $100,000 200,000 200,000 500,000 On January 1, 2017, UAE borrowed $225,000 on a construction loan at 12 % interest. These loans were outstanding throughout the construction period. The company had $750,000 in 9% bonds outstanding in 2017....

  • On January 2, 2017, Sunland Company began construction of a new citrus processing plant. The automated...

    On January 2, 2017, Sunland Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows: January 2, 2017 $ 597000 September 1, 2017 1812000 December 31, 2017 1812000 March 31, 2018 1812000 September 30, 2018 1215000 Sunland Company borrowed $3370000 on a construction loan at 10% interest on January 2, 2017. This loan was outstanding during the construction period. The company...

  • On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 609000 1812000 1812000 812000 198000 1 1 Bonita Industries borrowed $3290000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period....

  • On January 2, 2020, Marigold Corp. began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Marigold Corp. began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 592000 1806000 1806000 1806000 1219000 Marigold Corp. borrowed $3330000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT