Question

On January 1, 2017, UAE Inc. began construction of an automated car system. The system was finished and ready for use on 12-3
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution 1:

Construction of Building - UAE Inc.
Schedule of Weighted-Average accumulated expenditure
Date Amount Current year capitalization period Weighted Average Accumulated Expenditures
1-Jan-17 $100,000.00 12/12 $100,000
1-Apr-17 $200,000.00 9/12 $150,000
1-Jul-17 $200,000.00 6/12 $100,000
31-Dec-17 $500,000.00 0/12 $0
$1,000,000.00 $350,000

Solution 2:

Total avoidable interest for 2017 = ($225,000 * 12%) + ($125,000*9%) = $38,250

Solution 3:

Actual interest = ($225,000*12%) + ($750,000*9%) = $94,500

Solution 4:

Total cost of project = Total cost + avoidable interest = $1,000,000 + $38,250 = $1,038,250

Add a comment
Know the answer?
Add Answer to:
On January 1, 2017, UAE Inc. began construction of an automated car system. The system was...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1. 2018. This loan was outstanding throughout the construction period. The...

  • Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1 2018. This loan was outstanding throughout the construction period. The...

  • On January 3, 20X5, Brighton, Inc. began construction of an automated cattle feeder system.   Expenditures on...

    On January 3, 20X5, Brighton, Inc. began construction of an automated cattle feeder system.   Expenditures on the project during 20X5 were as follows:                     January 2, 20X5         $800,000                             September 1, 20X5         $300,000                            December 31, 20X5         $300,000         The company borrowed $750,000 on a construction loan at 12% interest on January 2, 20X5. The company also had two other loans outstanding at the beginning of 20X5 of $600,000 at 7% and $200,000 at 10%. Both loans were outstanding all year long....

  • On January 1, 2021, Jenner Inc. began construction of an automated cattle feeder system. The system...

    On January 1, 2021, Jenner Inc. began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 235,000 September 1, 2021 $ 342,000 December 31, 2021 $ 342,000 March 31, 2022 $ 342,000 September 30, 2022 $ 235,000 Jenner borrowed $764,000 on a construction loan at 7% interest on January 1, 2021. This loan was outstanding throughout the construction period....

  • On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The...

    On January 2, 2019, Siloam Farms Inc. began construction of an automated Cattle Feeder System. The system was finished and ready for use on September 30, 2020. Expenditures on the project were as follows: January 2, 2019                       $750,000          July 1, 2019                            $600,000          December 31, 2019                 $450,000          March 31, 2020                       $450,000          September 30, 2020                $300,000              The company borrowed $900,000 on a construction loan at 10% interest on January 2, 2019. In addition, the company had $400,000 in 12% bonds and $800,000 in 7.5% bonds outstanding...

  • J pour Save Answer On January 1, 2021 Kendall Inc began construction of an automated cattle...

    J pour Save Answer On January 1, 2021 Kendall Inc began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2022 Expenditures on the project were as follows: January 1, 2021 270.000 September 1, 2021 384 000 December 31, 2021 384 000 March 31 2022 334000 September 30, 2022 270.000 Kendall borrowed $778,000 on a construction loan at 8% Interest on January 1, 2021 This loan was outstanding throughout the construction...

  • On January 2, 2017, Marigold Corp. began construction of a new citrus processing plant. The automated...

    On January 2, 2017, Marigold Corp. began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows: January 2, 2017 September 1, 2017 December 31, 2017 March 31, 2018 September 30, 2018 592000 1812000 1812000 1812000 1201000 Ma gold Corp. borrowed $3280000 on a construction loan at 12% interest on an a y 2 2017. This loan was outstanding during bonds outstanding in...

  • On January 2, 2017, Sunland Company began construction of a new citrus processing plant. The automated...

    On January 2, 2017, Sunland Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows: January 2, 2017 $ 597000 September 1, 2017 1812000 December 31, 2017 1812000 March 31, 2018 1812000 September 30, 2018 1215000 Sunland Company borrowed $3370000 on a construction loan at 10% interest on January 2, 2017. This loan was outstanding during the construction period. The company...

  • On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 609000 1812000 1812000 812000 198000 1 1 Bonita Industries borrowed $3290000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period....

  • On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 599000 September 1, 2020 1801200 December 31, 2020 1801200 March 31, 2021 1801200 September 30, 2021 1220000 Vaughn Manufacturing borrowed $3230000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT