Note: the interpretation may not make sense, but do it regardless, for the sake of practice.
Hours | Feet |
24.00 | 545 |
13.50 | 400 |
26.25 | 562 |
25.00 | 540 |
9.00 | 220 |
20.00 | 344 |
22.00 | 569 |
11.25 | 340 |
50.00 | 900 |
12.00 | 285 |
38.75 | 865 |
40.00 | 831 |
19.50 | 344 |
18.00 | 360 |
28.00 | 750 |
27.00 | 650 |
21.00 | 415 |
15.00 | 275 |
25.00 | 557 |
45.00 | 1028 |
29.00 | 793 |
21.00 | 523 |
22.00 | 564 |
16.50 | 312 |
37.00 | 757 |
32.00 | 600 |
34.00 | 796 |
25.00 | 577 |
31.00 | 500 |
24.00 | 695 |
40.00 | 1054 |
27.00 | 486 |
18.00 | 442 |
62.50 | 1249 |
53.75 | 995 |
79.50 | 1397 |
Project Work Conditions
Job-site labor productivity can be estimated either for each craft (carpenter, bricklayer, etc.) or each type of construction (residential housing, processing plant, etc.) under a specific set of work conditions. A base labor productivity may be defined for a set of work conditions specified by the owner or contractor who wishes to observe and measure the labor performance over a period of time under such conditions. A labor productivity index may then be defined as the ratio of the job-site labor productivity under a different set of work conditions to the base labor productivity, and is a measure of the relative labor efficiency of a project under this new set of work conditions.
The effects of various factors related to work conditions on a new project can be estimated in advance, some more accurately than others. For example, for very large construction projects, the labor productivity index tends to decrease as the project size and/or complexity increase because of logistic problems and the "learning" that the work force must undergo before adjusting to the new environment. Job-site accessibility often may reduce the labor productivity index if the workers must perform their jobs in round about ways, such as avoiding traffic in repaving the highway surface or maintaining the operation of a plant during renovation. Labor availability in the local market is another factor. Shortage of local labor will force the contractor to bring in non-local labor or schedule overtime work or both. In either case, the labor efficiency will be reduced in addition to incurring additional expenses. The degree of equipment utilization and mechanization of a construction project clearly will have direct bearing on job-site labor productivity. The contractual agreements play an important role in the utilization of union or non-union labor, the use of subcontractors and the degree of field supervision, all of which will impact job-site labor productivity. Since on-site construction essentially involves outdoor activities, the local climate will influence the efficiency of workers directly. In foreign operations, the cultural characteristics of the host country should be observed in assessing the labor efficiency.
Non-Productive Activities
The non-productive activities associated with a project should also be examined in order to examine the productive labor yield, which is defined as the ratio of direct labor hours devoted to the completion of a project to the potential labor hours. The direct labor hours are estimated on the basis of the best possible conditions at a job site by excluding all factors which may reduce the productive labor yield. For example, in the repaving of highway surface, the flagmen required to divert traffic represent indirect labor which does not contribute to the labor efficiency of the paving crew if the highway is closed to the traffic. Similarly, for large projects in remote areas, indirect labor may be used to provide housing and infrastructure for the workers hired to supply the direct labor for a project. The labor hours spent on rework to correct unsatisfactory original work represent extra time taken away from potential labor hours. The labor hours related to such activities must be deducted from the potential labor hours in order to obtain the actual productive labor yield.
Example 4-1: Effects of job size on productivity
A contractor has established that under a set of "standard" work conditions for building construction, a job requiring 500,000 labor hours is considered standard in determining the base labor productivity. All other factors being the same, the labor productivity index will increase to 1.1 or 110% for a job requiring only 400,000 labor-hours. Assuming that a linear relation exists for the range between jobs requiring 300,000 to 700,000 labor hours as shown in Figure 4-1, determine the labor productivity index for a new job requiring 650,000 labor hours under otherwise the same set of work conditions.
The labor productivity index I for the new job can be obtained by linear interpolation of the available data as follows:
This implies that labor is 15% less productive on the large job than on the standard project.
In the construction of an off-shore oil drilling platform, the potential labor hours were found to be L = 7.5 million hours. Of this total, the non-productive activities expressed in thousand labor hours were as follows:
Determine the productive labor yield after the above factors are taken into consideration.
The percentages of time allocated to various non-productive activities, A, B, C and D are:
The total percentage of time X for all non-productive activities is:
The productive labor yield, Y, when the given factors for A, B, C and D are considered, is as follows:
As a result, only 41% of the budgeted labor time was devoted directly to work on the facility.
Example 4-3: Utilization of on-site worker's time
An example illustrating the effects of indirect labor requirements which limit productive labor by a typical craftsman on the job site was given by R. Tucker with the following percentages of time allocation: [4]
Productive time |
40% |
In this estimate, as much time is spent on productive work as on delays due to management and inefficiencies due to antiquated work methods.
Trying to avoid over- or under-allocating labour hours in a particular moving job, the owner of...
The owner of a moving company typically has his most experienced manager predict the total number of labor hours that will be required to complete an upcoming move. This approach has proved useful in the past, but the owner has the business objective of developing a more accurate method of predicting labor hours. In a preliminary effort to provide a more accurate method, the owner has decided to use the number of cubic feet moved and the number of pieces...
13.50 The owner of a moving company typically has his most experienced manager predict the total number of labor hours that will be required to complete an upcoming move. This approach has proved useful in the past, but the owner has the business ob-jective of developing a more accurate method of predicting labor hours. In a preliminary effort to provide a more accurate method, the owner has decided to use the number of cubic feet moved and the number of...
The owner of a moving company typically has his most experienced manager predict the total number of labor hours that will be required to complete an upcoming move. This approach has proved useful in the past, but the owner has the business objective of developing a more accurate method of predicting labor hours. In a preliminary effort to provide a more accurate method, the owner has decided to use the number of cubic feet moved as the independent variable and...
PLEASE SHOW ALL EXCEL FORMULAS USED FOR EACH CALCULATIONS. A STEP BY STEP WALKTHROUGH OF HOW TO DO THE PROBLEM. Thank you so much for your help! Hours Feet Elevator Elevator code 24.00 545 Yes 1 13.50 400 Yes 1 26.25 562 No 0 25.00 540 No 0 9.00 220 Yes 1 20.00 344 Yes 1 22.00 569 Yes 1 11.25 340 Yes 1 50.00 900 Yes 1 12.00 285 Yes 1 38.75 865 Yes 1 40.00 831 Yes 1...