Question

Johnson & Johnson has been awarded a contract to build a 4-seat outhouse for a rich...

Johnson & Johnson has been awarded a contract to build a 4-seat outhouse for a rich man. The exterior dimensions will be 10 ft by 40 ft. The pit must be 10-ft deep so as not to fill up too quickly. The excavation has a bottom dimension of 20 ft by 50 ft and a top dimension of 60 ft by 90 ft with the cast-in-place concrete pit walls also being 10 ft by 40 ft. The borrow material has a dry unit weight of 97.0 pcf and a water content of 5%. The specifications call for the backfill to have a dry unit weight of 118 pcf at a water content of 7%. How may cubic yards of borrow material are required? How many gallons of water are required? The specific gravity of the soil solids is 2.67.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Hi,

Solution as follows:

  1. Excavation Quantity:

Excavation dimensions provided in the question are as follows:

Bottom Size of pit = 20 ft x 50 ft

Top Size of pit = 60 ft x 90 ft

Depth of pit = 10 ft

Pit is in the shape of a Prismoid. Hence the volume of excavation shall be calculated by below formula:

Where,

h = height

A1 and A2 = Bottom and top areas

Hence volume of excavation,

Since 1 cubic yard = 27 cubic feet,

  1. Borrow Quantity (CCY):

Earth shall be filled outside the walls. Hence the volume of fill can be calculated by excavation quantity less volume of walls (out-to-out)

Volume of Walls = 10 x 40 x 10 =4,000 cubic feet

Since 1 cubic yard = 27 cubic feet,

Volume of fill = 1077.01 – 148.15 = 928.86 cubic yards

Since the fill need to be compacted after fill; the quantity calculated above will be compacted cubic yards (CCY).

  1. Swell factor:

Dry unit weight of soil required (Compacted Density) = 118 pcf

Dry unit weight of borrow soil (Bank density) = 97 pcf

  1. Required Volume of earth:

Bank volume of Earth required (BCY) = CCY x Swell factor = 928.86 x 1.216 = 1129.49 bank cubic yards

  1. Required Volume of Water:

Water content in borrow soil = 5%

Water content required in compacted soil = 7%

Additional water content required = 7% – 5% = 2%

Weight of solids = Dry density x Volume

Weight of solids in borrowed earth = 118 x 928.86 = 109,605.48 lbs

Unit weight of water = 8.34 lbs per gallon

Hence they will required 1129.49 BCY of borrow earth and 262.84 gallons of water for the job.

Hope the same is clear.

Keep Chegging

Best Regards

Chegg Expert Team

Add a comment
Know the answer?
Add Answer to:
Johnson & Johnson has been awarded a contract to build a 4-seat outhouse for a rich...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A soil borrow material in its natural state in the ground has a unit weight of...

    A soil borrow material in its natural state in the ground has a unit weight of 123 pcf. When a sample of this soil is dried in the laboratory, its dry unit weight is 103 pcf. What is the water content of this borrow material?

  • the only question to answer are 2-5 2-7 2-10 2-17 2-19 thank you CHAPTER Two 2-3....

    the only question to answer are 2-5 2-7 2-10 2-17 2-19 thank you CHAPTER Two 2-3. An undisturbed chunk of soil has a wet weight of 62 lb and a volume of o.s6 ft. When dried out in an oven, the soil weighs S0 Ib. If the specific gravity o solids is found to be 2.64, determine the water con- tent, wet unit weight of soil, dry unit soil. 2-13. The wet unit weight of a soil sample is 18.55...

  • 1. A soil sample is taken from a small test hole in a soil borrow pit....

    1. A soil sample is taken from a small test hole in a soil borrow pit. The volume of the test hole is 5 ft. The wet mass of the soil is 18 kg and the dry mass is 21 kg. The specific gravity of the soil solids is 2.65. ( m 35. 3147ft)(1 kge 2.205 lb) ( 1 lb= 0.2248 N) Determine: a. Wet and dry density (Mg/m) b. Wet and dry unit weight (pcf) C. Water content (%)...

  • on and Volume Change: 10 points An earthwork project has the following conditions: Borrow Site -soil...

    on and Volume Change: 10 points An earthwork project has the following conditions: Borrow Site -soil density is 120 PCF with water content w = 15% Fill Site soil density is 135 PCF with water content w 17 % - Unit weight of water: 8.34 lb per gallon a. How many gallons of water must be added to the borrow per cubic yard and 20 Points ph 4. Dozer Production material pped per hour (9CHd atteched Cat Estinated Ripper Prd...

  • Assignment 2 Question 1 Your company was awarded a culvert contract. The contract manager has appointed...

    Assignment 2 Question 1 Your company was awarded a culvert contract. The contract manager has appointed you to manage the project and has requested you to provide a schedule for the client. The contract manager handed you the table below, showing a breakdown of activities involved, together with their duration. The Start date is the 01/02/2021 (1st February 2021) Working week of 5 days, 40 hours must be use. Task Name 1 Setting out Excavation 2 Earthworks/Site Clearing 3 Bulk...

  • reply ma as soon as possible 120 points total Due: October 23, 2019 Budget your time...

    reply ma as soon as possible 120 points total Due: October 23, 2019 Budget your time carefully TRUE OR FALSE (45 points - 3 points cach): Mark whether the statements as written are "true" or "false". If the statement is false, make minor changes to the statement so that the statement is true. The primary adverse health effect resulting from the disposal of mercury wastes into Minamata Bay was dysentery The flow regime in horizontal velocity grit chambers approaches continuous...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT