Planned production per month:

Units (one table) = 100

Piece of Woods = 20

Estimate M price = $30

Actual production

Quantity purchased (QP) = 18

Actual Price (AP) = $34

The calculated material quantity (volume) variance is:

a. 72 Favorable

b. 72 Unfavorable

c. 60 Favorable

d. 60 Unfavorable

e. 12 Favorable

f. 12 Unfavorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Materials Quantity Variance

= (SQ-AQ) * SP

= (20 - 18)* 30

= 2 * 30

= 60 Favourable

Option C

Comment if you face any issues

Add a comment
Know the answer?
Add Answer to:
Table Manufacturing Company produce one style of tables. The following data pertain to producing one table....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • estion 15 Table Manufacturing Company produce one style of tables. the following data pertain to producing...

    estion 15 Table Manufacturing Company produce one style of tables. the following data pertain to producing one table Planned production per month Units (one table) 100 Piece of woods (M) 20 Estimated M price $30 Actual production Quantity purchased (QP) 18 $34 Actual price (AP) The calculated total material variance is 1.72 Favorable 2.72 Unfavorable 3.60 Favorable 4.60 Unfavorable 5.12 Favorable 6.12 Unfavorable A Moving to another question will save this me

  • 6. Table Manufacturing Company produces one style of tables. The following data pertain to producing one...

    6. Table Manufacturing Company produces one style of tables. The following data pertain to producing one table Planned production per month Units (one table) 100 Place of woods (M) 20 Estimated M price $30 Actual production   Quality purchased (QP) 18 Actual Price (AP) $34 The calculated material quality (volume) variance is 72 fav 72 unfav 60 fav 60 unfav 12 fav 12 u

  • Table Manufacturing Company produces one style of tables. the following data pertain to producing one table...

    Table Manufacturing Company produces one style of tables. the following data pertain to producing one table Planned production/month ? units (one table) 50 Piece of woods (M) 20 Estimated M price $20 Actual production ? Quantity purchased (QP) from M 19 Actual price (AP) $21 Material?volume (efficiency)?variance? ? $19, Favorable $19, Unfavorable $20, Favorable $20, Unfavorable Given: Total direct material variance $200 favorable (F), Direct material price variance $900 unfavorable (UF), Standard price $10 Standard quantities 750 Find actual price...

  • Table Manufacturing Company produces one style of tables. the following data pertain to producing one table...

    Table Manufacturing Company produces one style of tables. the following data pertain to producing one table Planned production/month ? units (one table) 50 Piece of woods (M) 20 Estimated M price $20 Actual production ? Quantity purchased (QP) from M 19 Actual price (AP) $21 Material price variance? ? $19, Favorable $19, Unfavorable $20, Favorable $20, Unfavorable Given for XM Company the following data for January 20X1. Direct material purchased and used in production accounted for $100,000 Units purchased 10,000...

  • Q5: Table Manufacturing Company produces one style of tables. The following data pertain to producing one...

    Q5: Table Manufacturing Company produces one style of tables. The following data pertain to producing one table Planned production/month units (one unit = one table) 20 A piece of woods (M) 20 Estimated M price $10 Actual production Quantity purchased (QP) from M 22 Actual price (AP) $9.5 Material variances? Q6: Given the following data to calculate variable overhead variances Actual inputs Actual hours 200 Actual rate $12.00 Standards Standards hours 190 Standard rate $10.00 Find the budget variance and...

  • > as Moving to another question will save this response. Question 7 Table Manufacturing Company produces...

    > as Moving to another question will save this response. Question 7 Table Manufacturing Company produces one style of tables. The following data pertain to producing one table Planned production/month units (one table) Piece of woods (M) Estimated M price Actual production Quantity purchased (QP) Find actual price (AP) 90 20 540 Assuming that the manager wants the total material variance Less than $30 Between $30 and $33 Between $34 and $35 More than $36 à Moving to another question...

  • Variance means a. difference between standard or applied amount and actual amount b. actual costs less...

    Variance means a. difference between standard or applied amount and actual amount b. actual costs less actual rates c. standard costs less standard rates d. square root of standard deviation 2. Table Manufacturing Company produces one style of tables. The following data pertain to producing one table Planned production/month units (one table) 90 Piece of woods (M) 20 Estimated M price $40 Actual production Quantity purchased (QP) 22 Find actual price (AP) x Assuming that the manager wants the total...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $180 per ton Standard labor rate $14.50 per hour Standard materials price $182 per ton Quantities Actual hours incurred and used 4,700 hours Actual quantity of materials purchased and used 1,900 tons Standard hours used 4,760 hours Standard quantity of materials used 1,890 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $140 per ton Standard labor rate $14.50 per hour Standard materials price $142 per ton Quantities Actual hours incurred and used 3,800 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 3,850 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $140 per ton Standard labor rate $14.50 per hour Standard materials price $142 per ton Quantities Actual hours incurred and used 3,800 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 3,850 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT