Subatomic Shirts' standard cost included 0.70 metres of direct material per t-shirt at $3.80 per metre. Subatomic actually used 32,500 metres of direct material at a cost of $3.75 per metre to produce 50,000 t-shirts.
a) Calculate the direct materials price variance: $
b) Is the direct materials price variance favourable or unfavourable?
c) Calculate the direct materials quantity variance: $
d) Is the direct materials quantity variance favourable or unfavourable?
e) Calculate the total direct materials variance: $
f) Is the total direct materials variance favourable or unfavourable?
Materials Price Variance = (SP-AP) * AQ = (3.80-3.75)*32500 = 1625 |
|
FAVOURABLE | |
Materials Quantity Variance = (SQ-AQ) * SP = (0.70*50,000 - 32,500)* 3.80 = 2500 |
|
FAVOURABLE | |
Total direct materials variance = 1625 F + 2500 F = 4125 |
|
FAVOURABLE |
.
.
Comment if you face any issues
Subatomic Shirts' standard cost included 0.70 metres of direct material per t-shirt at $3.80 per metre....
ABC Limited uses a standard costing system for all its products. ABC Limited produces shirts. Each shirt uses a standard 3 metres of material at a standard cost of £5.50 per metre. Budgeted production is 5,000 shirts per annum. During the financial year ended 30 April 2019, ABC produced 5,500 shirts. The cost of each metre of material was £5.30 and 2.8 metres of material were used in each shirt produced. Based on the above information, what is the direct...
ks 1& 2 pending * FNSACC613 05-6.pdf Als/FNSACC613%20Q5-6.pdf Direct Materials: Direct Labour: Factory Overhead: 2 metres @$1.80 per metre 40 minutes $12 per hour 40 minutes $6 per hour $3.60 $8.00 $4.00 The factory overhead rate was arrived at using the following annual budgets: Variable factory overhead Fixed factory overhead $80,000 160,000 240,000 Estimated production for the year is 60,000 shirts (spread evenly over 12 months). Management keeps cost records and calculates material, labour and overhead variances. Details of actual...
Pagley Company's standard labour cost of producing one unit of Product DD is 4 hours at the rate of $12 per hour During August, 40,800 hours of labour are incurred at a cost of $12.10 per hour to produce 10,000 units of Product Calculate the total direct labour variance: Is it favourable or unfavourable? Calculate the direct labour price variance: Is it favourable or unfavourable? Calculate the direct labour quantity variance: Is it favourable or unfavourable?
Jay Levitt Company budgeted the following cost standards for
the current year:
Direct materials (2 kg of
plastic at $6 per kilogram)
$12.00
Direct labour (2 hours at $12
per hour)
24.00
Variable manufacturing
overhead
11.90
Fixed manufacturing
overhead
6.25
Total standard cost per
unit
$54.15
Actual costs for producing 2,740 units were as follows:
Direct materials used
5,560
kg
Direct materials purchased
(6,780 kg)
$40,002
Direct labour (6,880 hours)
$67,424
Variable manufacturing
costs
$32,600
Fixed manufacturing costs
$17,600
Your...
Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total unit cost $17.12...
Q2. (25 marks) Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total...
Granger Tees is a manufacturer of T-shirts. The standard amount
of 100% cotton jersey fabric used to make each T-shirt is 3.00
yards. The standard price per yard of the fabric is $2.31. During
last month, Granger purchased 6,300 yards of the jersey fabric for
$13,860. The production department used 4,900 yards to produce
1,800 T-shirts during the month.
Compute the material price and quantity variances.
(Round answers to 0 decimal places, e.g. 125. Enter all
variances as a positive...
The Jacksonville Shirt Company makes two types of T-shirts: basic and custom. Basic shirts are plain shirts without any screen using the basic shirts and then adding a custom screen printing design The company buys cloth in various colors and then makes the basic shirts in two departments, Cutting and Sewing. The company uses a process costing system (weighted-average method) to determine the production cost of the basic shirts. In the Cutting Department, direct materials (cloth) are added at the...
The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 5.0 millilitres $ 0.30 per millilitre $ 1.50 Direct labour 0.4 hours $ 12.00 per hour $ 4.80 During the most recent month, the following activity was recorded: 28,000 millilitres of material was purchased at a cost of $0.25 per millilitre. All of the material was used to produce 3,000 bottles...
The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 7.0 millilitres $ 0.26 per millilitre $ 1.82 Direct labour 0.4 hours $ 12.00 per hour $ 4.80 During the most recent month, the following activity was recorded: 26,000 millilitres of material was purchased at a cost of $0.21 per millilitre. All of the material was used to produce 3,000 bottles...