Date for Variance | |||||||
Standard (400 units) | Actual (400 units) | ||||||
Qty/ Hours | Price/ Rate | Amount | Qty/ Hours | Price/ Rate | Amount | ||
Materials | 800 | $ 1.50 | $ 1,200.00 | 840 | $ 1.60 | $ 1,344.00 | |
Labor | 600 | $ 6.00 | $ 3,600.00 | 560 | $ 6.50 | $ 3,640.00 | |
Variable OH | 600 | $ 3.40 | $ 2,040.00 | 560 | $ 3.10 | $ 1,736.00 |
Variances | |||||||
Material Price Variance | = | (Standard Price - Actual Price) x Actual Quantity | |||||
= | ($ 1.5 - $ 1.6) x 840 | ||||||
= | $ 84.00 | (U) | |||||
Material Quan. Variance | = | (Standard Qty - Actual Qty) x Standard Price | |||||
= | (800 - 840) x $ 1.5 | ||||||
= | $ 60.00 | (U) | |||||
Direct Labor Rate Variance | = | (Standard Rate - Actual Rate) x Actual Hours | |||||
= | ($ 6 - $ 6.5) x 560 | ||||||
= | $ 280.00 | (U) | |||||
Direct Labor Effi. Variance | = | (Standard Hours - Actual Hours) x Standard Rate | |||||
= | (600 - 560) x $ 6 | ||||||
= | $ 240.00 | (F) | |||||
Variable OH Spending Variance | = | (Standard Rate - Actual Rate) x Actual Hours | |||||
= | ($ 3.4 - $ 3.1) x 560 | ||||||
= | $ 168.00 | (F) |
Granville Ltd's standard and actual costs per unit for the most recent period, during which 400...
Q2. (25 marks) Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total...
Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct Labour: Standard: 1.5 hours at $6.00 per hr. $9.00 Actual: 1.4 hours at $6.50 per hr. $9.10 Variable overhead: Standard: 1.5 hours at $3.40 per hr. $5.10 Actual: 1.4 hours at $3.10 per hr. $4.34 Total Unit...
Question 4 Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 ...
Question 4 Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 ...
3. Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Standard Actual Materials: Standard: 2 foot at $1.50 per foot $ 3.00 Actual: 2.1 foot at $1.60 per foot... $3.36 Direct labor: Standard: 1.5 hours at $6.00 per hour 9.00 Actual: 1.4 hours at $6.50 per hour... 9.10 Variable overhead: Standard: 1.5 hours at $3.40 per hour 5.10 Actual: 1.4 hours at $3.10 per hour... Total...
Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 635 units were actually produced. Standard Actual Materials: Standard: 2.4 metres at $2.40 per m. $5.76 Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour: Standard: 1.4 hrs. at $8.20 per hr. 11.48 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.4 hrs. at $4.50 per hr. 6.30 Actual: 1.7...
Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 635 units were actually produced. Standard Actual Materials: Standard: 2.4 mistres at $2.40 per m. $5.76 Actual: 2.1 metres at $2.60 per m. S5.46 Direct labour: Standard: 1.4 hrs at $8.20 per hr. 11.48 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.4 hrs. at $4.50 per hr. 6.30 Actual: 1.7 hrs. at $4.20 per hr. 7.14...
Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials: Standard: 2.5 metres at $2.7 per m. $6.75 Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour: Standard: 1.6 hrs. at $8.40 per hr. 13.44 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.6 hrs. at $4.70 per hr. 7.52 Actual: 1.7...
Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 625 units were actually produced. Standard Actual Materials Standard: 23 metres a $2..perm 552 Actual: 2.1 metres a $2.00 55.45 Direct labour Sundard: 14 hrs $8.10 h 114 Actual: 17 les 58.5 perhe Variable overhead Standard: 1451.50 per hr 6.2 Actual: 1.7.54.20 per hr Total unit.com $22.88 $27,05 For simplicity, assume there was no inventory of materials at the beginning...
Question 3 Time: 20 minutes Total: 12 marks Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials: Standard: 2.5 metres at $2.7 per m. $6.75 Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour: Standard: 1.6 hrs. at $8.40 per hr. 13.44 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.6 hrs....