Question

Orville Companys standard and actual costs per unit are provided below for the most recent period. During this time period 6
3. Direct labour rate variance (2 marks) 4. Direct labour efficiency variance (2 marks) 5. Variable overhead efficiency varia
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer :

(1) Material price variance = ( Standard price - Actual price ) * Actual Quantity

= ( $ 2.40 - $ 2.60 )*635 unit* 2.10 m

= $ 266.70 U

(2) Material Quanity Variance = ( standard quantity - Actual quantity ) * Standard rate

= ( 635*2.40 m - 635*2.10 m) *$ 2.40

= ( 1524 m - 1333.50 m) * $ 2.40

= $ 457.20 F

(3) Direct Labor rate variance = ( standard rate - actual rate ) * Actual hour

= ( $ 8.20- $ 8.50 ) * 635*1.70hr

= $ 323.85 U

(4) Direct Labor Efficiency variance = ( Standard hour - Actual Hour ) * Standard rate

= ( 635*1.40 hour - 635*1.70 hour ) *$ 8.20

= $ 1562.10 U

(5) Variable overhead efficiency variance = ( Standard hour - Actual Hour ) * Standard rate

   = ( 635*1.40 hour - 635*1.70 hour ) *$ 4.50

= $ 857.25 U

(6) Variable overhead spending variance = ( standard rate - actual rate ) * Actual hour

= ( $ 4.50- $ 4.20) *635*1.70 hour

= $ 323.85 F

Note -1

F = Favorable

U = Unfavorable

  

Add a comment
Know the answer?
Add Answer to:
Orville Company's standard and actual costs per unit are provided below for the most recent period....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Orville Company’s standard and actual costs per unit are provided below for the most recent period....

    Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 635 units were actually produced. Standard Actual Materials:      Standard: 2.4 metres at $2.40 per m. $5.76      Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour:      Standard: 1.4 hrs. at $8.20 per hr. 11.48      Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead:      Standard: 1.4 hrs. at $4.50 per hr. 6.30      Actual: 1.7...

  • Orville Company’s standard and actual costs per unit are provided below for the most recent period....

    Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials:      Standard: 2.5 metres at $2.7 per m. $6.75      Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour:      Standard: 1.6 hrs. at $8.40 per hr. 13.44      Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead:      Standard: 1.6 hrs. at $4.70 per hr. 7.52      Actual: 1.7...

  • Question 3 Time: 20 minutes Total: 12 marks Orville Company’s standard and actual costs per unit...

    Question 3 Time: 20 minutes Total: 12 marks Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials:      Standard: 2.5 metres at $2.7 per m. $6.75      Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour:      Standard: 1.6 hrs. at $8.40 per hr. 13.44      Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead:      Standard: 1.6 hrs....

  • Orville Company's standard and actual costs per unit are provided below for the most recent period....

    Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 625 units were actually produced. Standard Actual Materials Standard: 23 metres a $2..perm 552 Actual: 2.1 metres a $2.00 55.45 Direct labour Sundard: 14 hrs $8.10 h 114 Actual: 17 les 58.5 perhe Variable overhead Standard: 1451.50 per hr 6.2 Actual: 1.7.54.20 per hr Total unit.com $22.88 $27,05 For simplicity, assume there was no inventory of materials at the beginning...

  • Question 4 Orville Company’s standard and actual costs per unit are provided below for the most...

    Question 4 Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Standard Actual Materials:      Standard: 2 metres at $1.50 per m. $3.00      Actual: 2.1 metres at $1.60 per m. $3.36 Direct labour:      Standard: 1.5 hrs. at $6.00 per hr. 9.00      Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead:      Standard: 1.5 hrs. at $3.40 per hr. 5.10     ...

  • Question 4 Orville Company’s standard and actual costs per unit are provided below for the most...

    Question 4 Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Standard Actual Materials:      Standard: 2 metres at $1.50 per m. $3.00      Actual: 2.1 metres at $1.60 per m. $3.36 Direct labour:      Standard: 1.5 hrs. at $6.00 per hr. 9.00      Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead:      Standard: 1.5 hrs. at $3.40 per hr. 5.10     ...

  • Q2. (25 marks) Granville Ltd's standard and actual costs per unit for the most recent period,...

    Q2. (25 marks) Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total...

  • Granville Ltd's standard and actual costs per unit for the most recent period, during which 400...

    Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total unit cost $17.12...

  • Lido Company's standard and actual costs per unit for the most recent period, during which 400...

    Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct Labour: Standard: 1.5 hours at $6.00 per hr. $9.00 Actual: 1.4 hours at $6.50 per hr. $9.10 Variable overhead: Standard: 1.5 hours at $3.40 per hr. $5.10 Actual: 1.4 hours at $3.10 per hr. $4.34 Total Unit...

  • Triple Star Company's standard and actual costs per unit are provided below for the most recent...

    Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $21.00 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost I 3 $20.80 Hours Hourly Rate 2 2.2 $6.00 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT