Question

Question 4 Orville Company’s standard and actual costs per unit are provided below for the most...

Question 4

Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced.

Standard

Actual

Materials:

     Standard: 2 metres at $1.50 per m.

$3.00

     Actual: 2.1 metres at $1.60 per m.

$3.36

Direct labour:

     Standard: 1.5 hrs. at $6.00 per hr.

9.00

     Actual: 1.4 hrs. at $6.50 per hr.

9.10

Variable overhead:

     Standard: 1.5 hrs. at $3.40 per hr.

5.10

     Actual: 1.4 hrs. at $3.10 per hr.

4.34

Total unit cost

$17.19

$16.80

For simplicity, assume there was no inventory of materials at the beginning or end of the period.

Required:

Given the information above, compute the following variances. Also indicate if the variances are favorable or unfavorable.

  1. Materials price variance
  2. Materials quantity variance
  3. Direct labour rate variance
  4. Direct labour efficiency variance
  5. Variable overhead spending variance
  6. Variable overhead efficiency variance
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Material Price Variance = (Actual Price - Standard Price) x Actual Quantity
= ($1.60 - $1.50) x 840 = $84 (U)
Actual Quantity = 400 x 2.1 = 840

Material Quantity Variance = (Actual Quantity - Standard Quantity) x Standard Price
= (840 - 800) x $1.50 = $60 (U)
Standard Quantity = 400 x 2 = 800

Direct Labor rate variance = (Actual rate - Standard rate) x actual hours
= ($6.50 - $6) x 560 = $380 (U)
Actual hours = 400 x 1.4 = 560 hours

Direct labor efficiency variance = (Actual hours - standard hours) x Standard rate
= (600 - 560) x $6 = $240 (F)
Standard hours = 1.5 x 400 = 600

Variable overhead spending variance = (Actual rate - Standard rate) x actual hours
= ($3.10 - $3.40) x 560 = $168 (F)
Actual hours = 400 x 1.4 = 560 hours

Direct labor efficiency variance = (Actual hours - standard hours) x Standard rate
= (600 - 560) x $3.40 = $136 (F)

Add a comment
Know the answer?
Add Answer to:
Question 4 Orville Company’s standard and actual costs per unit are provided below for the most...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 4 Orville Company’s standard and actual costs per unit are provided below for the most...

    Question 4 Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Standard Actual Materials:      Standard: 2 metres at $1.50 per m. $3.00      Actual: 2.1 metres at $1.60 per m. $3.36 Direct labour:      Standard: 1.5 hrs. at $6.00 per hr. 9.00      Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead:      Standard: 1.5 hrs. at $3.40 per hr. 5.10     ...

  • Q2. (25 marks) Granville Ltd's standard and actual costs per unit for the most recent period,...

    Q2. (25 marks) Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total...

  • Granville Ltd's standard and actual costs per unit for the most recent period, during which 400...

    Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total unit cost $17.12...

  • Lido Company's standard and actual costs per unit for the most recent period, during which 400...

    Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct Labour: Standard: 1.5 hours at $6.00 per hr. $9.00 Actual: 1.4 hours at $6.50 per hr. $9.10 Variable overhead: Standard: 1.5 hours at $3.40 per hr. $5.10 Actual: 1.4 hours at $3.10 per hr. $4.34 Total Unit...

  • Orville Company’s standard and actual costs per unit are provided below for the most recent period....

    Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 635 units were actually produced. Standard Actual Materials:      Standard: 2.4 metres at $2.40 per m. $5.76      Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour:      Standard: 1.4 hrs. at $8.20 per hr. 11.48      Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead:      Standard: 1.4 hrs. at $4.50 per hr. 6.30      Actual: 1.7...

  • Orville Company’s standard and actual costs per unit are provided below for the most recent period....

    Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials:      Standard: 2.5 metres at $2.7 per m. $6.75      Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour:      Standard: 1.6 hrs. at $8.40 per hr. 13.44      Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead:      Standard: 1.6 hrs. at $4.70 per hr. 7.52      Actual: 1.7...

  • Orville Company's standard and actual costs per unit are provided below for the most recent period....

    Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 635 units were actually produced. Standard Actual Materials: Standard: 2.4 mistres at $2.40 per m. $5.76 Actual: 2.1 metres at $2.60 per m. S5.46 Direct labour: Standard: 1.4 hrs at $8.20 per hr. 11.48 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.4 hrs. at $4.50 per hr. 6.30 Actual: 1.7 hrs. at $4.20 per hr. 7.14...

  • Question 3 Time: 20 minutes Total: 12 marks Orville Company’s standard and actual costs per unit...

    Question 3 Time: 20 minutes Total: 12 marks Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials:      Standard: 2.5 metres at $2.7 per m. $6.75      Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour:      Standard: 1.6 hrs. at $8.40 per hr. 13.44      Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead:      Standard: 1.6 hrs....

  • Orville Company's standard and actual costs per unit are provided below for the most recent period....

    Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 625 units were actually produced. Standard Actual Materials Standard: 23 metres a $2..perm 552 Actual: 2.1 metres a $2.00 55.45 Direct labour Sundard: 14 hrs $8.10 h 114 Actual: 17 les 58.5 perhe Variable overhead Standard: 1451.50 per hr 6.2 Actual: 1.7.54.20 per hr Total unit.com $22.88 $27,05 For simplicity, assume there was no inventory of materials at the beginning...

  • 3. Lido Company's standard and actual costs per unit for the most recent period, during which...

    3. Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Standard Actual Materials: Standard: 2 foot at $1.50 per foot $ 3.00 Actual: 2.1 foot at $1.60 per foot... $3.36 Direct labor: Standard: 1.5 hours at $6.00 per hour 9.00 Actual: 1.4 hours at $6.50 per hour... 9.10 Variable overhead: Standard: 1.5 hours at $3.40 per hour 5.10 Actual: 1.4 hours at $3.10 per hour... Total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT