Answer - 5
Material Price Variance = (Actual price - Standard price) x Actual quantity used
Actual Price = $2.60
Standard Price = $2.40
Actual quantity used = Quantity Produced x Actual Material used per unit
Actual quantity used = 625 units x 2.1 meter
Actual quantity used = 1312.50 meter
Material Price Variance = ($2.60 - $2.40) x 1312.50
Material Price Variance = $262.50 (U)
Answer - 6
Material Quantity Variance = (Actual quantity used - Standard
quantity used) x Standard Price
Standard quantity used = Quantity Produced x Standard Material used per unit
Standard quantity used = 625 units x 2.3 meter
Standard quantity used = 1437.50 meter
Material Quantity Variance = (1312.50 - 1437.50) x $2.40
Material Quantity Variance = $300.00 (F)
Answer -7
Direct Labour Rate Variance = (Actual rate - Standard rate) x Actual hours
Actual rate = $8.50 per hour
Standard rate = $8.10 per hour
Actual hours = Quantity Produced x Actual hrs per unit
Actual hours = 625 x 1.7 hrs
Actual hours = 1062.50 hrs
Direct Labour Rate Variance = ( $8.50 - $8.10 ) x 1062.50
Direct Labour Rate Variance = $425 (U)
Orville Company's standard and actual costs per unit are provided below for the most recent period....
Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 635 units were actually produced. Standard Actual Materials: Standard: 2.4 mistres at $2.40 per m. $5.76 Actual: 2.1 metres at $2.60 per m. S5.46 Direct labour: Standard: 1.4 hrs at $8.20 per hr. 11.48 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.4 hrs. at $4.50 per hr. 6.30 Actual: 1.7 hrs. at $4.20 per hr. 7.14...
Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials: Standard: 2.5 metres at $2.7 per m. $6.75 Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour: Standard: 1.6 hrs. at $8.40 per hr. 13.44 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.6 hrs. at $4.70 per hr. 7.52 Actual: 1.7...
Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 635 units were actually produced. Standard Actual Materials: Standard: 2.4 metres at $2.40 per m. $5.76 Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour: Standard: 1.4 hrs. at $8.20 per hr. 11.48 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.4 hrs. at $4.50 per hr. 6.30 Actual: 1.7...
Question 4 Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 ...
Question 4 Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 ...
Question 3 Time: 20 minutes Total: 12 marks Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials: Standard: 2.5 metres at $2.7 per m. $6.75 Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour: Standard: 1.6 hrs. at $8.40 per hr. 13.44 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.6 hrs....
Q2. (25 marks) Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total...
Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct Labour: Standard: 1.5 hours at $6.00 per hr. $9.00 Actual: 1.4 hours at $6.50 per hr. $9.10 Variable overhead: Standard: 1.5 hours at $3.40 per hr. $5.10 Actual: 1.4 hours at $3.10 per hr. $4.34 Total Unit...
Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total unit cost $17.12...
Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $21.00 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost I 3 $20.80 Hours Hourly Rate 2 2.2 $6.00 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given...