Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced.
Standard |
Actual |
|
Materials: |
||
Standard: 2.5 metres at $2.7 per m. |
$6.75 |
|
Actual: 2.1 metres at $2.60 per m. |
$5.46 |
|
Direct labour: |
||
Standard: 1.6 hrs. at $8.40 per hr. |
13.44 |
|
Actual: 1.7 hrs. at $8.50 per hr. |
14.45 |
|
Variable overhead: |
||
Standard: 1.6 hrs. at $4.70 per hr. |
7.52 |
|
Actual: 1.7 hrs. at $4.20 per hr. |
7.14 |
|
Total unit cost |
$27.71 |
$27,05 |
For simplicity, assume there was no inventory of materials at the beginning or end of the period.
Required:
Given the information above, compute the following variances. Also indicate if the variances are favorable or unfavorable.
6. Variable overhead spending variance
Solution-
1) Material Price Variance =(Actual Price - Standard Price) * Actual Quantity
= ($2.60-$2.70) * 1365
= $136.5(F)
Actual Quantity = 650*2.1 = 1365
2) Material Quantity Variance = (Actual Quantity - Standard Quantity ) * Standard Price
= (1365 - 1625 ) * $2.7
= $702(F)
Standard Quantity = 650* 2.5 = 1625
3) Direct Labor rate variance = (Actual rate - Standard rate ) * Actual hours
= ($8.50-$8.40) * 1105
= $110.5 (U)
Actual hours = 650 *1.7 =1105
4) Direct labor efficiency variance = (Actual hours - Standard hours) * Standard rate
= (1105 - 1040 ) * $8.40
= $546(U)
Standard hours = 650*1.6 = 1040
5) Variable overhead efficiency variance = (Actual hours - Standard hours ) * Standard rate
= (1105 - 1040) * $4.70
=$305.5(U)
Actual hours = 650 *1.7 =1105
Standard hours = 650 *1.6 =1040
6) Variable overhead spending variance = (Actual rate - Standard rate ) * Actual hours
=( $4.20 - $4.70) * 1105
= $552.5(F)
Orville Company’s standard and actual costs per unit are provided below for the most recent period....
Question 3 Time: 20 minutes Total: 12 marks Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials: Standard: 2.5 metres at $2.7 per m. $6.75 Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour: Standard: 1.6 hrs. at $8.40 per hr. 13.44 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.6 hrs....
Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 635 units were actually produced. Standard Actual Materials: Standard: 2.4 metres at $2.40 per m. $5.76 Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour: Standard: 1.4 hrs. at $8.20 per hr. 11.48 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.4 hrs. at $4.50 per hr. 6.30 Actual: 1.7...
Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 635 units were actually produced. Standard Actual Materials: Standard: 2.4 mistres at $2.40 per m. $5.76 Actual: 2.1 metres at $2.60 per m. S5.46 Direct labour: Standard: 1.4 hrs at $8.20 per hr. 11.48 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.4 hrs. at $4.50 per hr. 6.30 Actual: 1.7 hrs. at $4.20 per hr. 7.14...
Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 625 units were actually produced. Standard Actual Materials Standard: 23 metres a $2..perm 552 Actual: 2.1 metres a $2.00 55.45 Direct labour Sundard: 14 hrs $8.10 h 114 Actual: 17 les 58.5 perhe Variable overhead Standard: 1451.50 per hr 6.2 Actual: 1.7.54.20 per hr Total unit.com $22.88 $27,05 For simplicity, assume there was no inventory of materials at the beginning...
Question 4 Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 ...
Question 4 Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 ...
Q2. (25 marks) Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total...
Granville Ltd's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Actual $3.36 Standard Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. Total unit cost $17.12...
Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Standard Actual Materials: Standard: 2 metres at $1.50 per m. $3.00 Actual: 2.1 metres at $1.60 per m. $3.36 Direct Labour: Standard: 1.5 hours at $6.00 per hr. $9.00 Actual: 1.4 hours at $6.50 per hr. $9.10 Variable overhead: Standard: 1.5 hours at $3.40 per hr. $5.10 Actual: 1.4 hours at $3.10 per hr. $4.34 Total Unit...
yandard and actual costs per unit are provided below for the most recent period Brod 500 units were acully produced Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $7.79 $21.00 3 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 $6.82 $35.41 $35.00 Required: Given the information above, compute the following variances....