Griffin Industries is evaluating whether to invest in solar panels to provide some of the electrical needs of its main office building in Ann Arbor, Michigan. The solar panel project would cost $700,000 and would provide cost savings in its utility bills of $65,000 per year. It is anticipated that the solar panels would have a life of 15 years and would have no residual value.
1. |
Calculate the payback period in years of the solar panel project. |
2. |
If the company uses a discount rate of 10%, what is the net present value of this project? |
3. |
If the company has a rule that no projects will be undertaken that have a payback period of more than five years, would this investment be accepted? If not, what arguments could the energy manager make to try to obtain approval for the solar panel project? |
4. |
What would you do if you were in charge of approving capital investment proposals? |
Solution 1: Calculation of Payback Period:
Year |
Annual Cost Savings $ |
Cumulative Annual Cost Savings $ |
1 |
65,000 |
65,000 |
2 |
65,000 |
130,000 |
3 |
65,000 |
195,000 |
4 |
65,000 |
260,000 |
5 |
65,000 |
325,000 |
6 |
65,000 |
390,000 |
7 |
65,000 |
455,000 |
8 |
65,000 |
520,000 |
9 |
65,000 |
585,000 |
10 |
65,000 |
650,000 |
11 |
65,000 |
715,000 |
12 |
65,000 |
780,000 |
13 |
65,000 |
845,000 |
14 |
65,000 |
910,000 |
15 |
65,000 |
975,000 |
The Initial Investment is $700,000
We see that project recovers $700000 from the savings in between 10th year and 11th year
Payback period
= Completed number of years + (Amount to be recovered / Cost savings for the next year)
= 10 + (50,000/65,000)
= 10.77 Years
Solution 2: Calculation of Net Present Value
Year |
Annual Cost Savings $ |
Present value factor @ 10% |
Present Value of the Cost Savings |
1 |
65,000 |
0.909091 |
59,090.91 |
2 |
65,000 |
0.826446 |
53,719.01 |
3 |
65,000 |
0.751315 |
48,835.46 |
4 |
65,000 |
0.683013 |
44,395.87 |
5 |
65,000 |
0.620921 |
40,359.89 |
6 |
65,000 |
0.564474 |
36,690.81 |
7 |
65,000 |
0.513158 |
33,355.28 |
8 |
65,000 |
0.466507 |
30,322.98 |
9 |
65,000 |
0.424098 |
27,566.35 |
10 |
65,000 |
0.385543 |
25,060.31 |
11 |
65,000 |
0.350494 |
22,782.10 |
12 |
65,000 |
0.318631 |
20,711.00 |
13 |
65,000 |
0.289664 |
18,828.18 |
14 |
65,000 |
0.263331 |
17,116.53 |
15 |
65,000 |
0.239392 |
15,560.48 |
Total Present Value of the Cost Savings $ |
494,395.17 |
Net Present Value = Total Present Value of the Cost Savings $ - Initial Investment $
= 494,395.17 - $700,000
= -$205,604.83
As the Net Present Value of the project is negative, it is not recommended to invest in the solar panels
Solution 3: If the company has a rule that no projects will be undertaken that have payback period of more than 5 years, then investment in solar panels is not recommended as it has a payback period of 10.77 years and also the Net Present Value of the project is negative.
Solution 4: Being incharge of the project I would have rejected the proposal looking at a long payback period of 10.77 years and a negative NPV of $205,604.83.
Griffin Industries is evaluating whether to invest in solar panels to provide some of the electrical...
Griffin Industries is evaluating whether to invest in solar panels to provide some of the electrical needs of its main office building in Ann Arbor, Michigan. The solar panel project would cost $700,000 and would provide cost savings in its utility bills of $65,000 per year. It is anticipated that the solar panels would have a life of 15 years and would have no residual value. 1. Calculate the payback period in years of the solar panel project. 2. If...
please complete the 4 requirements for E12-23 Wouw A Calculate the payback and NPV for a sustainable energy project E12-23A Calci Grant Industries is electrical needs of (Learning Objectives 1 & 3) ant Industries is evaluating whether to invest in solar panels to provide some of the SUSTAINABILITY ctrical needs of its main office building in Buffalo, New York. The solar panel project ould cost $600,000 and would provide cost savings in its utility bills of $50,000 per year. It...
In this problem, we consider replacing an existing electrical water heater with an array of solar panels... Answer all parts of question if there is multiple parts not just what's below the line please ;) In this problem, we consider replacing an existing electrical water heater with an array of solar panels. The net installed investment cost of the panels is $1,080 ($1,800 less a 40% tax credit from the government). Based on an energy audit, the existing water heater...
In this problem, we consider replacing an existing electrical water heater with an array of solar panels. The net installed investment cost of the panels is $1,365 ($2,100 less a 35% tax credit from the government). Based on an energy audit, the existing water heater uses 180 kilowatt hours (kWh) of electricity per month, so at $0.13 per kWh, the cost of operating the water heater is $23.4 per month. Assuming the solar panels can save the entire cost of...
In this problem, we consider replacing an existing electrical water heater with an array of solar panels. The net installed investment cost of the panels is $1,235 ($1,900 less a 35% tax credit from the government). Based on an energy audit, the existing water heater uses 210 kilowatt hours (kWh) of electricity per month, so at $0.14 per kWh, the cost of operating the water heater is $29.4 per month. Assuming the solar panels can save the entire cost of...
1. Suppose MSU has an opportunity to build a solar facility just outside of Ann Arbor that would generate about 120,000 MWh per year (1 MWh = 1000 KWh), and cost $25 million to install. To determine if this is a good deal for the university, you need to analyze the economics. Assume the market price for electricity over the next five years is $48 per MWh and there is a 5-year project horizon. Evaluate this decision using a 3%...
I really need help with number 5 1. Suppose MSU has an opportunity to build a solar facility just outside of Ann Arbor that would generate about 120,000 MWh per year (1 MWh = 1000 KWh), and cost $25 million to install. To determine if this is a good deal for the university, you need to analyze the economics. Assume the market price for electricity over the next five years is $48 per MWh and there is a 5-year project...
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...
Mr. Reynolds has asked each member of the committee to carefully review the data related to Mr. Meek's proposal, and then send him an email message letting him know your initial thoughts. In your message, you might want to take into consideration the following information: The current and projected patient volumes and payer mix. The present and projected financial position of the system. The effectiveness of similar approaches to improving patient service revenue, lowering costs, and achieving economies of scale....