Question

GG finds that the demand is really uncertain. The typical leadtime for supply is 9 weeks....

GG finds that the demand is really uncertain. The typical leadtime for supply is 9 weeks. The standard deviation of demand during the leadtime is 120. If GG wants to provide 95% cycle service level, what should be the safety stock and reorder level? Show calculations to get credit.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

For 95% service level, z=1.645

LT=9

=120

safety stock = (z**LT)0.5

safety stock = (1.645*120*9)0.5

Safety Stock =42.15

Add a comment
Know the answer?
Add Answer to:
GG finds that the demand is really uncertain. The typical leadtime for supply is 9 weeks....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT