The Botosan Factory has determined that its budgeted factory overhead budget for the year is $696,864...

The Botosan Factory has determined that its budgeted factory overhead budget for the year is $696,864 and budgeted direct labor hours are 292,800. If the actual direct labor hours for the period are 266,400, how much overhead would be allocated to the period?

a.$634,032

b.$538,927

c.$653,053

d.$767,179

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Overhead rate =Overhead budget/direct labor hours =696864/292800 =2.38

Overhead allocated to the period =266400*2.38 =634032

Add a comment
Know the answer?
Add Answer to:
The Botosan Factory has determined that its budgeted factory overhead budget for the year is $696,864...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Botosan Factory has determined that its budgeted factory overhead budget for the year is $735,904...

    The Botosan Factory has determined that its budgeted factory overhead budget for the year is $735,904 and budgeted direct labor hours are 317,200. If the actual direct labor hours for the period are 288,700, how much overhead would be allocated to the period? a. $569,316 b. $669,784 c. $689,878 d. $810,439

  • The Botosan Factory has determined that its budgeted factory overhead budget for the year is $586,245...

    The Botosan Factory has determined that its budgeted factory overhead budget for the year is $586,245 and budgeted direct labor hours are 313,500. If the actual direct labor hours for the period are 285,300, how much overhead would be allocated to the period? a.$549,516 b.$533,511 c.$453,484 d.$645,548

  • 1) 2) 3) 4) 5) The Botosan Factory has determined that its budgeted factory overhead budget...

    1) 2) 3) 4) 5) The Botosan Factory has determined that its budgeted factory overhead budget for the year is $615,420 and budgeted direct labor hours are 473,400. If the actual direct labor hours for the period are 430,800, how much overhead would be allocated to the period? Oa, $576,841 Ob. $560,040 Oc. $476,034 Od. $677,648 Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to...

  • The Roget Factory has determined that its budgeted factory overhead budget for the year is $4,588,000....

    The Roget Factory has determined that its budgeted factory overhead budget for the year is $4,588,000. They plan to produce 1,000,000 units. Budgeted direct labor hours are 310,000 and budgeted machine hours are 375,000. Using the single plantwide factory overhead rate based on direct labor hours, calculate the factory overhead rate for the year. a. $7.40 b. $19.24 c. $14.80 d. $71.04

  • Overhead using a normal costing approach based upon machine-hours. Budgeted factory overhead was $266,400, budgeted machine-hours...

    Overhead using a normal costing approach based upon machine-hours. Budgeted factory overhead was $266,400, budgeted machine-hours were 18,500. Actual factory overhead was $287,920, actual machine-hours were 19,050. How much is the over- or underapplied overhead?

  • The total factory overhead for Big Light Company is budgeted for the year at $894,880. Big...

    The total factory overhead for Big Light Company is budgeted for the year at $894,880. Big Light manufactures two different products: night lights and desk lamps. Night lights are budgeted for 10,700 units. Each night light requires 2 hours of direct labor. Desk Lamps are budgeted for 24,600 units. Each desk lamp requires 3 hours of direct labor. a Determine the total number of budgeted direct labor hours for the year. direct labor hours b Determine the single plantwide factory...

  • The total factory overhead for Big Light Company is budgeted for the year at $1,701,700. Big...

    The total factory overhead for Big Light Company is budgeted for the year at $1,701,700. Big Light manufactures two different products: night lights and desk lamps. Night lights are budgeted for 13,100 units. Each night light requires 3 hours of direct labor. Desk lamps are budgeted for 16,100 units. Each desk lamp requires 2 hours of direct labor a Determine the total number of budgeted direct labor hours for the year. direct labor hours b Determine the single plantwide factory...

  • Flexible Overhead Budget Wiki Wiki Company has determined that the variable overhead rate is $4 per...

    Flexible Overhead Budget Wiki Wiki Company has determined that the variable overhead rate is $4 per direct labor hour in the Fabrication Department. The normal production capacity for the Fabrication Department is 17,000 hours for the month. Fixed costs are budgeted at $108,800 for the month. a. Prepare a monthly factory overhead flexible budget for 16,000, 17,000, and 18,000 hours of production. Enter all amounts as positive numbers. S Wiki Wikl Company Monthly Factory Overhead Cost Budget-Fabrication Department 16,000 17,000...

  • Flexible Overhead Budget Wiki Wiki Company has determined that the variable overhead rate is $2.9 per...

    Flexible Overhead Budget Wiki Wiki Company has determined that the variable overhead rate is $2.9 per direct labor hour in the Fabrication Department. The normal production capacity for the Fabrication Department is 16,000 hours for the month. Fixed costs are budgeted at $68,800 for the month. a. Prepare a monthly factory overhead flexible budget for 14,800, 16,000, and 17,200 hours of production. Enter all amounts as positive numbers. Wiki Wiki Company Monthly Factory Overhead Cost Budget-Fabrication Department Direct labor hours...

  • The total factory overhead for Big Light Company is budgeted for the year at $1,146,000. Big...

    The total factory overhead for Big Light Company is budgeted for the year at $1,146,000. Big Light manufactures two different products: night lights and desk lamps. Night lights are budgeted for 9,900 units. Each night light requires 3 hours of direct labor. Desk lamps are budgeted for 13,800 units. Each desk lamp requires 2 hours of direct labor. a Determine the total number of budgeted direct labor hours for the year. direct labor hours b Determine the single plantwide factory...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT