Compute the IRR statistic for Project E. The appropriate cost of
capital is 7 percent. (Do not round intermediate
calculations and round your final answer to 2 decimal
places.)
Project E | ||||||
Time: | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow | −$2,800 | $870 | $870 | $780 | $560 | $360 |
Project E | ||||||
IRR is the rate at which NPV =0 | ||||||
IRR | 0.084223276 | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -2800 | 870 | 870 | 780 | 560 | 360 |
Discounting factor | 1 | 1.084223 | 1.17554 | 1.274548 | 1.3818946 | 1.498282 |
Discounted cash flows project | -2800 | 802.4177 | 740.0853 | 611.9817 | 405.24076 | 240.2752 |
NPV = Sum of discounted cash flows | ||||||
NPV Project E = | 0.000682761 | |||||
Where | ||||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
IRR= | 8.42% | |||||
Compute the IRR statistic for Project E. The appropriate cost of capital is 7 percent. (Do...
Compute the IRR statistic for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow −$1,800 $670 $720 $680 $460 $260 IRR? Should the project be accepted or rejected?
Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: 0 -$2,300 1 $870 2 $870 3 $780 4 $560 5 $360 Payback years Should the project be accepted or rejected? accepted O rejected
Compute the payback statistic for Project A if the appropriate cost of capital is 7 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: Cash flow: 0 -$2,300 1 $870 2 $870 3 $780 4 $560 5 $360 Payback years Should the project be accepted or rejected? accepted O rejected
Compute the PI statistic for Project Z if the appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow: −$2,300 $610 $740 $910 $560 $360 Should the project be accepted or rejected? accepted rejected
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,100 $390 $510 $540 $320 $120 IRR= _____% Should the project be accepted or rejected?
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 2 4 Cash flow: -$9,900 $3,7s0 $4,580 $1,920 $2,550 IRR Should the project be accepted or rejected? ассepted Orejected Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project...
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,300 $470 $570 $580 $360 $160
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$3,600 $1,110 $1,050 $900 $680 $480
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: Cash flow 0 $1,300 1 $470 2 $570 3 $580 4 $360 5 $160 IRR IRR C % Should the project be accepted or rejected? O accepted O rejected
Compute the IRR for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: Cash flow:-$10,100 $3,850 $4,680 $2,020 $2,650 IRR % Should the project be accepted or rejected? rejected O accepted Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E...