Question

Problems – Find the Net Present Value and Benefit Cost Ratio for the following: 1.An investment...

ProblemsFind the Net Present Value and Benefit Cost Ratio for the following:

1.An investment in new software is expected to have the following cash flows over a three-year period. The discount rate is 12 percent?

Year Cash Flow

0 -$28,900

1   $12,450

2   $19,630

3   $ 2,750

  1. A layoff is expected to have an immediate restructuring charge of $7,500 and save money for the firm according to the schedule below.   The firm’s weighted average cost of capital is 11 percent (which may be used as the discount rate for average-risk investments).

Year Cash Inflows

1   $4,375

2   $ 0

3   $8,750

4   $4,100

  1. Productivity training for a firm’s employees should produce cost savings from productivity increases of $1,750 a year for four years. The training initially costs $10,600. The firm’s weighted average cost of capital is 13 percent (which may be used as the discount rate for average-risk investments).
  2. You are considering the following two mutually exclusive projects. The required rate of return is 11 percent (which is the same as the discount rate) for project A and 10 percent for project B. Which project should you accept and why?

Year    Project A        Project B

0          -$48,000       -$126,900

1             $18,400         $ 69,700

2             $31,300         $ 80,900

3             $11,700         $ 0

  1. You are considering two mutually exclusive projects with the following after-tax cash flows. Will your choice between the two projects differ if the required rate of return (which is the same as the discount rate) is 8 percent rather than 11 percent? If so, what should you do?

Year    Project A        Project B

0          -$240,000     -$198,000

1             $ 0                 $110,800

2             $ 0                 $ 82,500

3          $325,000      $ 45,000

PS: I need to show the work of how I arrived to the answer. Thanks. I need this today, if possible, please.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV = PV of Cash Inflows - PV of Cash Outflows

Part A:

Year CF PVF@ 12% Disc CF
0 $ -28,900.00       1.0000 $ -28,900.00
1 $ 12,450.00       0.8929 $    11,116.07
2 $ 19,630.00       0.7972 $    15,648.92
3 $    2,750.00       0.7118 $      1,957.40
NPV $        -177.62

Part B:

Year CF PVF @11% Disc CF
0 $ -7,500.00     1.0000 $ -7,500.00
1 $ 4,375.00     0.9009 $ 3,941.44
2 $              -       0.8116 $              -  
3 $ 8,750.00     0.7312 $ 6,397.92
4 $ 4,100.00     0.6587 $ 2,700.80
NPV $ 5,540.16

Part C:

Year CF PVF @13% Disc CF
0 $ -10,600.00     1.0000 $ -10,600.00
1 $    1,750.00     0.8850 $    1,548.67
2 $    1,750.00     0.7831 $    1,370.51
3 $    1,750.00     0.6931 $    1,212.84
4 $    1,750.00     0.6133 $    1,073.31
NPV $   -5,394.68

Part D:

Project A:

Year CF PVF @11% Disc CF
0 $ -48,000.00     1.0000 $ -48,000.00
1 $ 18,400.00     0.9009 $    16,576.58
2 $ 31,300.00     0.8116 $    25,403.78
3 $ 11,700.00     0.7312 $      8,554.94
NPV $      2,535.30

Project B:

Year CF PVF @10% Disc CF
0 $ -1,26,900.00     1.0000 $ -1,26,900.00
1 $      69,700.00     0.9091 $      63,363.64
2 $      80,900.00     0.8264 $      66,859.50
3 $                    -       0.7513 $                    -  
NPV $        3,323.14

Project B is considered as Project B has higher NPV.

Part E:

Project A:

Year CF PVF @8% Disc CF
0 $ -2,40,000.00     1.0000 $ -2,40,000.00
1 $                    -       0.9259 $                    -  
2 $                    -       0.8573 $                    -  
3 $ 3,25,000.00     0.7938 $ 2,57,995.48
NPV $     17,995.48

Project B:

Year CF PVF @8% Disc CF
0 $ -1,98,000.00     1.0000 $ -1,98,000.00
1 $ 1,10,800.00     0.9259 $ 1,02,592.59
2 $      82,500.00     0.8573 $      70,730.45
3 $      45,000.00     0.7938 $      35,722.45
NPV $     11,045.50

Project A is selected as it has Higher NPV.

Add a comment
Know the answer?
Add Answer to:
Problems – Find the Net Present Value and Benefit Cost Ratio for the following: 1.An investment...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...

    If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 Year Project Y Project Z 0 -$1,500 -$1,500 1 $200 $900 2 $400 $600 $600 $300 4 $1,000 $200 Project Y Project 2 If the weighted average cost of capital (WACC) for each project is...

  • If an independent project with conventional, or normal, cash flows is being analyzed, the net present...

    If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars Year Project Y Project Z 800 -$1,500 -$1,500 0 $200 $900 1 600 Project Y $400 $600 2 $600 $300 400 $1,000 $200 4 Project Z 200 If the weighted average cost of capital...

  • If an independent project with conventional, or normal, cash flows is being analyzed, the net present...

    If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 0 -$1,00 Year Project W -$1,000 1 $200 2 $350 $400 $600 Project x -$1,500 $350 $500 $600 $750 Project X Project W If the weighted average cost of capital (WACC) for each...

  • Q. What is the net present value of a project with the following cash flows and...

    Q. What is the net present value of a project with the following cash flows and a required return of 12%? What is the internal rate of return? What is the payback period for this project? How about PI? Year 1 Cash Flow -$28,900 $12,450 $19,630 $ 2,750

  • 1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value...

    1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Cute Camel Woodcraft Company is evaluating a proposed capital budgeting project (project Alpha) that will require an initial investment of $550,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $375,000 Year 2 $450,000...

  • Help and verified and be clear. The net present value (NPV) and internal rate of return...

    Help and verified and be clear. The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company's CFO remembers that the internal rate of return (IRR) of Project Lambda is...

  • 1. Calculate the net present value (NPV) for both projects, and determine which project should be...

    1. Calculate the net present value (NPV) for both projects, and determine which project should be accepted based on NPV. Round both NPVs to the nearest dollar. 2. Calculate the internal rate of return (IRR) for both projects, and determine which project should be accepted based on IRR. 3. Calculate the net present value (NPV) for both projects using the crossover rate as your discount rate. Round both NPVs to the nearest dollar. Please show all work. Thank you. Use...

  • 1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value...

    1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Lumbering Ox Truckmakers is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $3,000,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $375,000 Year 2 $400,000 Year...

  • 1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value...

    1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions Consider this case: Suppose Pheasant Pharmaceuticals is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $2,225,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 Year 2 Year 3 Year 4...

  • 1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value...

    1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Fuzzy Button Clothing Company is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $3,000,000. The project is expected to generate the following net cash flows: Year Year 1 Year 2 Year 3 Year 4...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT