Chicago's Hard Rock Hotel distributes a mean of 800 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with a standard deviation of 105 towels per day, based on occupancy. The laundry firm that has the linen contract requires a 2-day lead time. The hotel expects a 98% service level to satisfy high guest expectations. Refer to the standard normal tableLOADING... for z-values. a) What is the reorder point? nothing towels (round your response to the nearest whole number).
reorder point = Daily demand* lead time + z*Standard deviation of demand*sqrt(lead time)
=800*2+normsinv(0.98)*105*sqrt(2) = 1904.966154 = 1905 (Rounded to nearest whole number)
Chicago's Hard Rock Hotel distributes a mean of 800 bath towels per day to guests at...
Chicago's Hard Rock Hotel distributes a mean of 1,200 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with a standard deviation of 95 towels per day, based on occupancy. The laundry firm that has the linen contract requires a 4-day lead time. The hotel expects a 99% service level to satisfy high guest expectations. Refer to the standard normal table for z-values. a) What is the reorder point? ___towels (round...
Problem 12.46 Question Help o Chicago's Hard Rock Hotel distributes a mean of 1,200 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with a standard deviation of 95 towels per day, based on occupancy. The laundry firm that has the linen contract requires a 3-day lead time. The hotel expects a 99% service level to satisfy high guest expectations. Refer to the standard normal table for z-values. a) What is...
Rich Hotel distributes a mean of 1,000 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with a standard deviation of 100 towels per day, based on occupancy. The laundry firm that has the linens contract requires a 2-day lead time. The hotel expects a 98% service level to satisfy high guest expectations. a. What is the safety stock needed to meet this service level? b. What is the ROP? c....
Z-Table Z Pr(Z) 0.38 65 0.50 69 0.67 75 0.84 80 1.04 85 1.28 90 92 1.41 1.56 94 1.65 95 1.75 96 98 2.06 2.33 99 Chicago's Hard Rock Hotel distributes a mean of 800 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with deviation of 105 towels per day, based on occupancy. The laundry firm that has the linen contract requires a 4-day lead time. The hotel expects...