I just need help with B&C I have the rest figured out.
Cost of Quality and Value-Added/Non-Value-Added Reports for a Service Company
Three Rivers Inc. provides cable TV and Internet service to the local community. The activities and activity costs of Three Rivers are identified as follows:
a. Identify the cost of quality classification for each activity and whether the activity is value-added or non-value-added.
Quality Control Activities | Activity Cost | Quality Cost Classification | Value-Added/ Non-Value-Added Classification |
|
Billing error correction | $40,900 | External failure | Non-value-added | |
Cable signal testing | 102,200 | Appraisal | Value-added | |
Reinstalling service (installed incorrectly the first time) | 87,900 | External failure | Non-value-added | |
Repairing satellite equipment | 43,800 | Internal failure | Non-value-added | |
Repairing underground cable connections to the customer | 26,600 | External failure | Non-value-added | |
Replacing old technology cable with higher quality cable | 159,400 | Prevention | Value-added | |
Replacing old technology signal switches with higher quality switches | 182,200 | Prevention | Value-added | |
Responding to customer home repair requests | 49,000 | External failure | Non-value-added | |
Training employees | 38,000 | Prevention | Value-added | |
Total activity cost | $730,000 |
Feedback
Correct
b. Prepare a cost of quality report. Assume that sales are $3,650,000. If required, round percentages to one decimal place.
Three Rivers Inc. | |||
Cost of Quality Report | |||
Quality Cost Classification | Quality Cost | Percent of Total Quality Cost | Percent of Total Sales |
Prevention | $ | % | % |
Appraisal | % | % | |
Internal failure | % | % | |
External failure | % | % | |
Total | $ | % | % |
Feedback
b. Classify each activity as either prevention, appraisal, internal failure or external failure. List the total costs of each of these four categories in a column called quality cost. In a separate column, determine the percent of each quality cost as compared to the total quality costs by dividing individual quality cost categories by the total quality cost. In another column, determine the percent of each quality cost classification as compared to total sales by dividing individual quality cost classes by the total sales amount. Total all columns. Remember that the Percent of total quality cost column should total to 100%.
Learning Objective 1 and Learning Objective 3.
c. Prepare a value-added/non-value-added analysis.
Three Rivers Inc. | ||
Value-Added/Non-Value-Added Activity Analysis | ||
Category | Amount | Percent |
Value-added | $ | % |
Non-value-added | % | |
Total | $ | % |
Part B
Three Rivers Inc. |
|||
Cost of Quality Report |
|||
Quality Cost Classification |
Quality Cost |
Percent of Total Quality Cost |
Percent of Total Sales |
Prevention |
$379600 |
52% |
10.40% |
Appraisal |
102200 |
14% |
2.80% |
Internal failure |
43800 |
6% |
1.20% |
External failure |
204400 |
28% |
5.60% |
Total |
$730000 |
100% |
20.0% |
Prevention =159400+182200+38000 = 379600
Appraisal = 102200
Internal failure =43800
External failure = 40900+87900+26600+49000 = 204400
Percent of Total Quality Cost = respective quality cost / total quality cost
Percent of Total Sales = respective quality cost / total sales
Part C
Three Rivers Inc. |
||
Value-Added/Non-Value-Added Activity Analysis |
||
Category |
Amount |
Percent |
Value-added |
$481800 |
66% |
Non-value-added |
248200 |
34% |
Total |
$730000 |
100% |
Value-added = 102200+159400+182200+38000
Non-value-added = 40900+87900+43800+26600+49000
Value-added % = 481800/730000 = 66%
Non-value-added% = 248200/730000 = 34%
I just need help with B&C I have the rest figured out. Cost of Quality and...
Cost of Quality and Value-Added/Non-Value Added Reports for a Service Company Three Rivers Inc. provides cable TV and Internet service to the local community. The activities and activity costs of Three Rivers are identified. a. Identify the cost of quality classification for each activity and whether the activity is value-added or non-value-added. Quality Control Activities Activity Cost Quality Cost Classification VA/NVA Classification Billing error correction $60,000 External failure 140,000 Appraisal Non-value-added Value-added Cable signal testing Reinstalling service (installed incorrectly the...
Cost of Quality and Value-Added/Non-Value-Added Reports for a Service Company Three Rivers Inc. provides cable TV and Internet service to the local community. The activities and activity costs of Three Rivers are identified as follows: a. Identify the cost of quality classification for each activity and whether the activity is value-added or non-value-added. Quality Control Activities Activity Cost Quality Cost Classification Value-Added/ Non-Value-Added Classification Billing error correction $28,600 External failure Non-value-added Cable signal testing 93,500 Appraisal Value-added Reinstalling service (installed...
Cost of Quality and Value-Added/Non-Value-Added Reports for a Service Company Three Rivers Inc. provides cable TV and Internet service to the local community. The activities and activity costs of Three Rivers are identified as follows: a. Identify the cost of quality classification for each activity and whether the activity is value-added or non-value-added. Quality Control Activities Activity Cost Quality Cost Classification Value-Added/ Non-Value-Added Classification Billing error correction $22,600 Cable signal testing 79,900 Reinstalling service (installed incorrectly the first time) 48,500...
Cost of Quality and Value-Added/Non-Value-Added Reports for a Service Company Three Rivers Inc. provides cable TV and Internet service to the local community. The activities and activity costs of Three Rivers are identified as follows: a. Identify the cost of quality classification for each activity and whether the activity is value-added or non-value-added. Quality Control Activities Activity Cost Quality Cost Classification Value-Added/ Non-Value-Added Classification Billing error correction $24,800 Cable signal testing 56,000 Reinstalling service (installed incorrectly the first time) 53,300...
Cost of Quality and Value-Added/Non -Value-Added Reports for a Service Company Three Rivers Inc. provides cable TV and Internet service to the local community. The activities and activity costs of Three Rivers are identified as follows: a. Identify the cost of quality classification for each activity and whether the activity is value-added or non-value-added. Value-Added / Activity Quality Cost Non-Value-Added Quality Control Activities Cost Classification Classification Billing error correction $24,500 Cable signal testing 91,800 Reinstalling service (installed incorrectly the first...
Three Rivers Inc. provides cable TV and Internet service to the local community. The activities and activity costs of Three Rivers are are identified. a. Identify the cost of quality classification for each activity and whether the activity is value-added or non value-added. Quality Activities Activity Cost Quality Cost Classification VA/NVA Billing error correction $60,000 Cable signal testing 140,000 Reinstalling service (installed incorrectly the first time) 40,000 Repairing satellite equipment 50,000 Repairing underground cable connections to the customer 25,000 Replacing...
Instructions Three Rivers Inc. provides cable TV and Internet service to the local community. The activities and activity costs of Three Rivers are identified as follows Activities Activity Cost 36,000.00 Biling error correction Cable signal testing 1,800.00 Reinstalling service (installed incorrectly the first time 8,00000 Repairing satellite equipment 7,800.00 Repairing underground cable connections to the customer 1700000 Replacing old technology cable with higher quality cable 169,000.00 ! Replacing old technology signal switches with higher quality switches 126,00000 9Responding to customer...
Pareto Chart and Cost of Quality Report for a Manufacturing Company The president of Mission Inc. has been concerned about the growth in costs over the last several years. The president asked the controller to perform an activity analysis to gain a better insight into these costs. The result of the activity analysis is summarized as follows: Required: 1. Classify the activities into prevention, appraisal, internal failure, external failure, and not costs of quality (producing product). Classify the activities into...
Pareto Chart and Cost of Quality Report for a Manufacturing Company The president of Mission Inc. has been concerned about the growth in costs over the last several years. The president asked the controller to perform an activity analysis to gain a better insight into these costs. The result of the activity analysis is summarized as follows: Activities Activity Cost Correcting invoice errors $15,960 Disposing of incoming materials with poor quality 13,300 Disposing of scrap 31,920 Expediting late production 26,600...
Pareto Chart and A report summarizing the costs, percent of total, and percent of sales by appraisal, prevention, internal failure, and external failure cost of quality categories.Cost of Quality Report for a Manufacturing Company The president of Mission Inc. has been concerned about the growth in costs over the last several years. The president asked the controller to perform an The study of employee effort and other business records to determine the cost of activities.activity analysis to gain a better...