Question

Two products are considered for evaluation, the data of which is as given per week. Historical...

Two products are considered for evaluation, the data of which is as given per week.

Historical Data for Product A

Week

1

2

3

4

5

6

7

8

Massachusetts

33

45

37

38

55

30

18

58

New Jersey

46

35

41

40

26

48

18

55

Total

79

80

78

78

81

78

36

113

Historical Data for Product B

Week

1

2

3

4

5

6

7

8

Massachusetts

0

3

3

0

0

1

3

0

New Jersey

2

4

0

0

3

1

0

0

Total

2

7

3

0

3

2

3

0

The lead time is 1.5 weeks and the standard deviation of lead time is 1.25 weeks. Refer the attached King Safety Stock analysis for conceptual clarity and answer the following questions,

i) If the lead time is considered to be constant, what would be the safety stock for product A & B?

ii) If the lead time is not constant and is as given in the data above but independent of the demand, what would be the safety stock for product A & B?

iii) If the lead time is not constant and is as given in the data above but dependent on the demand fluctuations, what would be the safety stock for Product A & B?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Available Data:

Historical Demand data for Product A (Pa) and Product B (Pb)

Lead Time (L) for Pa and Pb = 1.5 weeks

Standard Deviation of Lead time (SDL) = 1.25 weeks

Assumption: Cycle Service Level (CSL) of Product A and B is 95%

i) Case 1: Lead time is considered to be constant. This means SDL = 0

Safety Stock of Product A = NORMSINV (CSL) * (Lead Time)0.5*Standard Deviation of Product A (SDa)

  = NORMSINV (0.95) * (1.5)0.5*19.4

= 1.645*1.225*19.4

Safety Stock of Product A = 39.02 units ~ 39 units

Safety Stock of Product B = NORMSINV (CSL) * (Lead Time)0.5*Standard Deviation of Product B (SDb)

  = NORMSINV (0.95) * (1.5)0.5*2.1

= 1.645*1.225*2.1

Safety Stock of Product A = 4.15 units ~ 4 units

ii) Lead time is not constant and is as given in the data above but independent of the demand, This means SDL = 1.25 weeks

Safety Stock of Product A = NORMSINV (CSL) * (L*SDa2 + SDL2Davg2)0.5

  = NORMSINV (0.95) * (1.5*19.42 + 1.252*77.92)0.5

= 1.645 * 100.224

Safety Stock of Product A = 164.85 units ~ 165 units

Safety Stock of Product B = NORMSINV (CSL) * (L*SDb2 + SDL2Davg2)0.5

  = NORMSINV (0.95) * (1.5*2.12 + 1.252*2.52)0.5

= 1.645 * 4.017

Safety Stock of Product A = 6.6 units ~ 7 units

iii) Lead time is not constant and is as given in the data above but dependent of the demand, This means SDL = 1.25 weeks

Safety Stock of Product A = NORMSINV (CSL) * (L)0.5*SDa2 + NORMSINV (CSL) *SDL*Davg

  = NORMSINV (0.95) * (1.5)0.5*19.4 + NORMSINV (0.95) *1.25*77.9

= 1.645*1.225*19.4 + 1.645*1.25*77.9

= 39.02 + 160.11

Safety Stock of Product A = 199.14 units ~ 199 units

Safety Stock of Product A = NORMSINV (CSL) * (L)0.5*SDb2 + NORMSINV (CSL) *SDL*Davg

  = NORMSINV (0.95) * (1.5)0.5*2.1 + NORMSINV (0.95) *1.25*2.5

= 1.645*1.225*2.1 + 1.645*1.25*2.5

= 4.15 + 5.14

Safety Stock of Product A = 9.29 units ~ 9 units

Add a comment
Know the answer?
Add Answer to:
Two products are considered for evaluation, the data of which is as given per week. Historical...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2.) A survey ELAC Student and the time they spend studying per week is given in...

    2.) A survey ELAC Student and the time they spend studying per week is given in the table below If a student studies 14 hours per week, would that student be considered unusual? Hours per Week Frequency 0-3 100 4-7 87 8-11 50 12-15 35 16-19 20 20-23 18 2.) A survey ELAC Student and the time they spend studying per week is given in the table below If a student studies 14 hours per week, would that student be...

  • 7. Calculate the number of Kanbans needed at this company for the following two products, produced...

    7. Calculate the number of Kanbans needed at this company for the following two products, produced in a factory that works eight hours per day, five days per week Usage Lead time Container size Safety stock Product 1 300/week 1 week 20 units 15 percent Product 2 150/day 2 weeks 30 units

  • i Data Table Table 2. INVENTORY RECORD DATA F G C Data Category Lot-sizing rule Lead...

    i Data Table Table 2. INVENTORY RECORD DATA F G C Data Category Lot-sizing rule Lead time Safety stock Scheduled receipts Beginning inventory L4L 3 weeks 0 150 (week 2) 125 D FOQ = 800 3 weeks 0 300 (week 2) 0 Item E FOQ = 600 4 weeks 0 600 (week 1) 255 L4L 2 weeks 70 None 670 L4L 1 week 0 1,200 (week 1) 0 Print Done Done nd then click Check Answer. Clear All The BOM...

  • Simulate the following inventory replenishment problem for 20 weeks. You will have to use the Excel...

    Simulate the following inventory replenishment problem for 20 weeks. You will have to use the Excel program to simulate. Demand is uniformly distributed between 20 and 30 units. Additional Data are given below. Inventory Cost/Week = $ 1.00 Shortage Cost/Week = $ 2.00 Lead Time = 2 weeks Beginning Stock on Hand (SOH) = 0 Supply in Week 1 = 21 units Supply in Week 2 = 22 units What is the total shortage cost at the end of 20...

  • Assume that a manufacturing company works five days per week, a supplier for a part has...

    Assume that a manufacturing company works five days per week, a supplier for a part has a lead-time of 3 days and the daily demand for the part is 120 items with standard deviation of 23.5 items. If the company wants to use a 97% service level (3% stock-out situation allowed), what would be the required safety stock and ROP

  • Southern Office Supplies Inc.

    Southern Office Supplies Inc. distributes office supplies to customers in the Southeast. One popular SKU is laser printer paper. Ordering costs are $51.00 per order. One ream of paper costs $3.80, and Southern uses a 25 percent annual inventory-holding cost rate. The average annual demand is 15,500 reams and historical data shows that the standard deviation of weekly demand is about 72. The lead time from the manufacturer is 3 weeks. The data has been collected in the Microsoft Excel...

  • Question 3B CWD Electronics sells Televisions (TV), which it orders from the USA. Because of ship...

    Question 3B CWD Electronics sells Televisions (TV), which it orders from the USA. Because of shipping and handling costs, each order must be for 10 TVs. Because of the time it takes to receive an order, the company places an order every time the present stock drops to 5 TVs. It costs $50 to place an order. It costs the company $200 in lost sales when a customer asks for a TV and the warehouse is out of stock. It...

  • (8 points total) 5. The following questions involve inventory management using the demand data in the...

    (8 points total) 5. The following questions involve inventory management using the demand data in the table below for 14 weeks (weeks 12-25 for the year) for one product. demand 12 13 14 15 16 17 18 19 20 21 35 40 20 30 35 45 30 23 24 25 30 25 35 Suppose inventory is managed with a continuous review system where the order size Q-200 and the reorder point R-160. The lead time is a constant 4 weeks....

  • Consider the end item whose bill of material file is as given in Figure 8-7 of...

    Consider the end item whose bill of material file is as given in Figure 8-7 of your textbook. Suppose that the planning horizon is 8 weeks. Week Forecas 145 Order 168 13 325 279 4 196 213 127 312 273 167 123 b) Suppose that the initial inventory level of B is 1200 and the safety stock level is 20 and a lot-for-lot (LFL) policy is appropriate. There are scheduled receipts of 279, 486 and 523 in weeks 2, 5...

  • Week 1 2 3 4 5 6 7 8 9 10 Demand 41 44 84 42...

    Week 1 2 3 4 5 6 7 8 9 10 Demand 41 44 84 42 84 86 7 18 49 30 End item A has a planned lead time of two weeks. There are currently 120 units on hand and no scheduled receipts. a. Compute the planned order releases using lot-for-lot b. Compute the planned order releases using part-period balancing where the ratio of the setup cost to the holding cost is 200 c. Compute the planned order releases...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT