Question

1.) Based on a predicted level of production and sales of 29,000 units, a company anticipates...

1.)

Based on a predicted level of production and sales of 29,000 units, a company anticipates total variable costs of $113,100, fixed costs of $29,000, and operating income of $203,580. Based on this information, the budgeted amount of fixed costs for 26,000 units would be:

Multiple Choice

  • $159,400.

  • $232,580.

  • $29,000.

  • $113,100

  • $101,400

2.)

Product A has a sales price of $21 per unit. Based on a 12,000-unit production level, the variable costs are $9 per unit and the fixed costs are $8 per unit. Using a flexible budget for 14,500 units, what is the budgeted operating income from Product A?

Multiple Choice

  • $14,500.

  • $78,000.

  • $96,000.

  • $22,500.

  • $52,500.

3.)

Parallel Enterprises has collected the following data on one of its products. During the period the company produced 25,000 units. The direct materials quantity variance is:

Direct materials standard (7 kg. @ $2.50/kg) $17.50 per finished unit
Actual cost of materials purchased $423,500
Actual direct materials purchased and used 160,000 kg

Multiple Choice

  • $14,000 unfavorable.

  • $37,500 unfavorable.

  • $37,500 favorable.

  • $23,500 unfavorable.

  • $23,500 favorable.

4.)

Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance is:

Direct materials standard (3 lbs @ $1/lb) $3 per finished unit
Total direct materials cost variance—unfavorable $19,250
Actual direct materials used 140,000 lbs.
Actual finished units produced 35,000 units

Multiple Choice

  • $15,750 favorable.

  • $35,000 unfavorable.

  • $35,000 favorable.

  • $19,250 unfavorable.

  • $19,250 favorable.

5.)

Grant Co. uses the following standard to produce a single unit of its product: Variable overhead (1.40 hrs. per unit @ $3.90/hr.) Actual data for the month show total variable overhead costs of $150,260, and 26,000 units produced. The total variable overhead variance is:

Multiple Choice

  • $8,300F.

  • $8,300U.

  • $76,900U.

  • $76,900F.

  • $0.

6.)

The standard materials cost to produce 1 unit of Product R is 6 pounds of material at a standard price of $44 per pound. In manufacturing 6,600 units, 37,500 pounds of material were used at a cost of $46 per pound. What is the direct materials quantity variance?

Multiple Choice

  • $75,000 unfavorable.

  • $75,000 favorable.

  • $92,400 unfavorable.

  • $92,400 favorable.

  • $17,400 favorable.

7.)

laymore Corp. has the following information about its standards and production activity for September. The volume variance is:

Actual total factory overhead incurred $ 29,620
Standard factory overhead:
Variable overhead $ 5.90 per unit produced
Fixed overhead
($7,740 / 4,300 estimated units to be produced) $ 1.80 per unit
Actual units produced 3,200 units

Multiple Choice

  • $3,000U.

  • $3,000F.

  • $1,980U.

  • $1,980F.

  • $4,980U.

8.)

Milltown Company specializes in selling used cars. During the month, the dealership sold 24 cars at an average price of $15,200 each. The budget for the month was to sell 22 cars at an average price of $16,200. Compute the dealership's sales volume variance for the month.

Multiple Choice

  • $24,000 unfavorable.

  • $10,200 favorable.

  • $24,000 favorable.

  • $32,400 unfavorable.

  • $32,400 favorable.

9.)

Brownley Company has two service departments and two operating (production) departments. The Payroll Department services all three of the other departments in proportion to the number of employees in each. The Maintenance Department costs are allocated to the two operating departments in proportion to the floor space used by each. Listed below are the operating data for the current period:

Service Depts. Production Depts.
Payroll Maintenance Cutting Assembly
Direct costs $ 40,400 $ 45,500 $ 96,500 $ 125,400
No. of personnel 35 35 105
Sq. ft. of space 12,000 17,000


The total cost of operating the Maintenance Department for the current period is:

Multiple Choice

  • $26,280.

  • $30,251.

  • $45,500.

  • $53,580.

  • $46,751.

10.)

The Menswear Department of Major's Department Store had sales of $203,000, cost of goods sold of $140,000, indirect expenses of $14,750, and direct expenses of $29,000 for the current period. The Menswear Department's contribution to overhead as a percent of sales is:

Multiple Choice

  • 85.71%.

  • 31.03%.

  • 16.75%.

  • 68.75%.

  • 9.48%.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1)

Fixed costs of producing 29,000 units = $29,000

Budgeted amount of fixed costs for 26,000 units would be = $29,000

Total fixed costs are not affected by the change in the volume of output. Hence, fixed costs of producing 26,000 units would be same as fixed costs of producing 29,000 units.

Correct option is (c)

2)

Budgeted fixed costs = Budgeted output x Fixed cost per unit

= 12,000 x 8

= $96,000

Sales (14,500 x 21) 304,500
Less: Variable costs (14,500 x 9) - 130,500
Less: Fixed costs - 96,000
Operating income $78,000

Budgeted operating income from Product A = $78,000

Correct option is (b)

3)

Standard quantity = 7 kg. per unit

Actual output = 25,000 units

Hence, standard quantity for actual output = 25,000 x 7

= 175,000 kg

Direct material quantity variance = Standard price x (Standard quantity - Actual quantity)

= 2.5 x (175,000 - 160,000)     

= $37,500 (Favorable)

Correct option is (c)

4)

Standard quantity = 3 lb per unit

Actual output = 35,000 units

Hence, standard quantity for actual output = 35,000 x 3

= 105,000 lb

Direct material quantity variance = Standard price x (Standard quantity - Actual quantity)

= 1 x (105,000 - 140,000)

= $35,000 (Unfavorable)

Correct option is (b)

Only 4 MCQs could be answered as per Chegg policy. You please post your other questions separately.

Kindly comment if you need further assistance. Thanks

Add a comment
Know the answer?
Add Answer to:
1.) Based on a predicted level of production and sales of 29,000 units, a company anticipates...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Based on predicted production of 12,000 units, a company anticipates $150,000 of fixed costs and $123,000...

    Based on predicted production of 12,000 units, a company anticipates $150,000 of fixed costs and $123,000 of variable costs. The flexible budget amounts of foed and variable costs for 10,000 units are: О $125,000 fixed and $102,500 variable. О $125,000 fixed and $123,000 variable. О $102.500 fixed and $150,000 variable. О $150,000 fixed and $123,000 variable. О S150,000 fixed and $102,500 variable. Preu A company provided the following direct materials cost information. Compute the total direct materials cost variance. $810,000...

  • Based on a predicted level of production and sales of 29,000 units, a company anticipates total...

    Based on a predicted level of production and sales of 29,000 units, a company anticipates total variable costs of $113,100, fixed costs of $29,000, and operating income of $203,580. Based on this information, the budgeted amount of operating income for 26,000 units would be: I know the correct answer is $179,520, but I don't know how they got that. Multiple Choice a. $179,520. b. $208,520. c. $66,420. d. $101,400. e. $309,920.

  • A company's flexible budget for the range of 30,000 units to 36,000 units of production showed...

    A company's flexible budget for the range of 30,000 units to 36,000 units of production showed variable overhead costs of $3.60 per unit and fixed overhead costs of $70,000. The company incurred total overhead costs of $180,100 while operating at a volume of 40,000 units. The total controllable cost variance is Multiple Choice $2,100 unfavorable. $2100 favorable. 33.900 favorable. $6,000 favorable $33.900 unfavorable Hassock Corp. produces woven wall hangings. It takes 4 hours of direct labor to produce a single...

  • PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on...

    PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is: Direct materials standard (3 lbs @ $2/lb) $6 per finished unit Total direct materials cost variance—unfavorable $14,250 Actual direct materials used 100,000 lbs. Actual finished units produced 25,000 units Multiple Choice $135,750. $164,250. $150,000. $182,000. $100,000. 2. Use the following data to find the total direct labor cost variance if the...

  • The standard materials cost to produce 1 unit of Product R is 6 pounds of material at a standard price of $50...

    The standard materials cost to produce 1 unit of Product R is 6 pounds of material at a standard price of $50 per pound. In manufacturing 8,000 units, 47,000 pounds of material were used at a cost of $51 per pound. What is the direct materials quantity variance? Multiple Choice $47,000 unfevorable $47000 favorable $50,000 unfavcracle Multiple Choice $47,000 unfavorable. $47,000 favorable. $50,000 unfavorable $50,000 favorable. Prex 1 of 20 Next Fletcher Company collected the following data regarding production of...

  • Fletcher Company collected the following data regarding production of one of its products. Compute the variable...

    Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead efficiency variance. Direct labor standard (2 hrs. @ $12.40/hr.) $ 24.80 per finished unit Actual direct labor hours 96,500 hrs. Budgeted units 56,000 units Actual finished units produced 47,500 units Standard variable OH rate (2 hrs. @ $15.00/hr.) $ 30.00 per finished unit Standard fixed OH rate ($526,400/56,000 units) $ 9.40 per unit Actual cost of variable overhead costs incurred $ 1,417,000 Actual...

  • The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units...

    The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units Materials:     Standard price per ounce $1.82     Standard ounces per completed unit 12     Actual ounces purchased and used in production 12,805     Actual price paid for materials $26,250 Labor:     Standard hourly labor rate $14.95 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,335.4     Actual total labor costs $81,365 Overhead:     Actual and budgeted fixed overhead $1,110,000     Standard variable overhead rate $28.00 per...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows:   Direct materials: 5 kg at $10.00 per kg $ 50.00     Direct labour: 3 hours at $14 per hour 42.00     Variable overhead: 3 hours at $4 per hour 12.00     Total standard cost per unit $ 104.00   The company planned to produce and sell 29,000 units in March. However, during March the company actually produced and...

  • The following company information is available. The direct materials quantity variance is: Direct materials used for...

    The following company information is available. The direct materials quantity variance is: Direct materials used for prodution Standard quantity for units produced Standard cost per gallon of direct material Actual cost per gallon of direct material 35,000 gallons 33,400 gallons $11.00 $11.20 Multiple Choice $17600 unfavorable. $17200 favorable $24,600 unfavorable Multiple Choice $17,600 unfavorable. $17.200 favorable. $24,600 unfavorable. $24,600 favorable. $17,200 unfavorable Use the following data to find the direct labor rate variance if the company produced 3,500 units during...

  • Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance IS. Dir...

    Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance IS. Direct materials standard (3 lbs $1/1b) Total direct materials cost variance-unfavorable $24,250 $3 per finished unit Actual direct materials used 108,000 lbs. 27,000 units Actual finished units produced Multiple Choice $24,250 unfavorable. $27,000 favorable. $2,750 favorable. $24,250 favorable. $27,000 unfavorable. A company has an overhead application rate of 128% of direct labor costs. How much overhead would be allocated to a job...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT