Question

#2. Short Answer You are a project manager of a construction contractor. You have a supplier...

#2. Short Answer

You are a project manager of a construction contractor. You have a supplier who manufactures and delivers curtain walls to your site. Your supplier and you are working on a solution to reduce total supply chain costs. You found that the PPC (Planned Percent Complete) and PCR (Percent Constraint Removed), of the contractor in charge of structure work are 60% and 43% respectively for the last three months. How do you think such PPC and PCR make an impact on the curtain-wall supply chain costs?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

PPC is Planned Percent Complete. The PPC of the current project is 60% in 3 months. This means the project is being implemented at a decent pace. Every project has certain constraints, which may act as roadblock to its execution. PCR is percent constraint removed. With time, the project implementation also tries to remove the constraints which may be hampering its performance. The PCR of current project is 43%. The project needs to have more interventions to remove the constraints as this may be affecting the performance of the project. A PCR of 43% will increase more supply costs as more interventions will be required to remove the constraints. A PPC of 60% is quite nominal and will lead to decrease the supply cost in the long run.

Add a comment
Know the answer?
Add Answer to:
#2. Short Answer You are a project manager of a construction contractor. You have a supplier...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are the project manager's assistant on a construction site. The project manager is off site...

    You are the project manager's assistant on a construction site. The project manager is off site for the day and you are responsible for the ongoing progress of the site in her absence. Two similar beams are delivered to a construction site. Each beam is a hollow box beam, constructed of A36 structural steel, (E=29.0 x 10ʻpsi, density of 490 1bm/ft), each beam having outside dimensions of 16" base and 18" height, 18 feet long. Beam A has top and...

  • You are the project manager's assistant on a construction site. The project manager is off site...

    You are the project manager's assistant on a construction site. The project manager is off site for the day and you are responsible for the ongoing progress of the site in her absence. Two similar beams are delivered to a construction site. Each beam is a hollow box beam, constructed of A36 structural steel, (E=29.0 x 106 psi, density of 490 lbm/ft?), each beam having outside dimensions of 16" base and 18" height, 18 feet long. Beam A has top...

  • You are the project manager's assistant on a construction site. The project manager is off site...

    You are the project manager's assistant on a construction site. The project manager is off site for the day and you are responsible for the ongoing progress of the site in her absence. Two similar beams are delivered to a construction site. Each beam is a hollow box beam, constructed of A36 structural steel, (E=29.0 x 106 psi, density of 490 lbm/ft?), each beam having outside dimensions of 16" base and 18" height, 18 feet long. Beam A has top...

  • Assume the following: You are a contractor and have just been awarded a Greenfield Project. A...

    Assume the following: You are a contractor and have just been awarded a Greenfield Project. A budget has been established to install 20,000ft of pipe at an estimated 15,000 man hours and an estimated billable cost of $700,000. The original schedule planned for 4,000ft of pipe to be installed per day by a 300-man crew working a 10-hour shift (anticipated). The job was scheduled to start in Monday and finish on Friday. On Monday 2,000 ft of pipe was installed....

  • You have been selected as the project manager for the Global Treps project. You helped to...

    You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths are your organizational and leadership skills....

  • Dear Sir/Madam, could you answer all the question below. I appreciate if u can answer all....

    Dear Sir/Madam, could you answer all the question below. I appreciate if u can answer all. Thank You :) A (Bad?) Day in the Life of a Project Manager Frank Mills is a Site Agent for McMurray Concrete Ltd which specialises in building concrete structures on industrial sites. His present site is a large chemical plant, Agrochem Ltd that manufactures farm fertilisers. The project he is currently working on is part of a large contract being managed by Design Solutions...

  • TORENTO CONSTRUCTION: ETHICAL CONTRACTING On December 27, 2010, Cary Holmes, manager of the Supply Chain Management...

    TORENTO CONSTRUCTION: ETHICAL CONTRACTING On December 27, 2010, Cary Holmes, manager of the Supply Chain Management (SCM) group at Torento Construction Inc. (NCG), was in his office in Torento, Ontario, trying to organize the thoughts running through his head as a result of a recent bidding to save operating costs at NCG. There was no problem in terms of the final outcome; in fact, the bid was going to result in cost savings of 25 per cent, which was exactly...

  • please answer #2 The Stratton Township Park The Stratton Township Park is located on a piece...

    please answer #2 The Stratton Township Park The Stratton Township Park is located on a piece of property that contains two golf courses, a swimming pool, and 800 acres of woods and open spaces. Three years ago, the Stratton Parks Department (Stratton) carved out miles of trails to allow visitors to hike the property and enjoy nature. To make that experience more enjoyable for visitors and available to school groups, Stratton decided to offer guided tours that have proven popular....

  • QUESTION 1: Why must project manager should have good technical skills but also good management skills?...

    QUESTION 1: Why must project manager should have good technical skills but also good management skills? QUESTION 2: **Communication and Communicator are related" This quote from the text suppose that the communication process is lead by the spokeperson. Do you think is it a gift" to be a good communicator or a skill to improve ( use example of your knowledge to answer)? QUESTION 3: Look at the text paragraph yellow highlighted, and do you think that in today's world...

  • please answer #5 The Stratton Township Park The Stratton Township Park is located on a piece...

    please answer #5 The Stratton Township Park The Stratton Township Park is located on a piece of property that contains two golf courses, a swimming pool, and 800 acres of woods and open spaces. Three years ago, the Stratton Parks Department (Stratton) carved out miles of trails to allow visitors to hike the property and enjoy nature. To make that experience more enjoyable for visitors and available to school groups, Stratton decided to offer guided tours that have proven popular....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT