Question

Determine the maximum output of a manufacturing system that operations 60 minutes per hour, has a...

Determine the maximum output of a manufacturing system that operations 60 minutes per hour, has a calculated total task time of all operations equal 220 seconds, and a bottleneck cycle time of 30 seconds per unit. The maximum output rate of this system is: __________ units per hour.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Total Available Time = 60 minutes per hour = 3600 seconds per hour

Cycle Time of Bottleneck = 30 seconds per unit

Maximum Output Rate = Total Available time / Cycle time of Bottleneck

Maximum Output Rate = 3600/30 = 120 units per hour

Add a comment
Know the answer?
Add Answer to:
Determine the maximum output of a manufacturing system that operations 60 minutes per hour, has a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Prakesh Company has the following data for one of its manufacturing cells: Maximum units produced in...

    Prakesh Company has the following data for one of its manufacturing cells: Maximum units produced in a month: 50,000 units Actual units produced in a month: 40,000 units Hours of production labor in one month: 10,000 hours 1. Compute the theoretical cycle time (in minutes per unit). 2. Compute the actual cycle time (in minutes per unit). 3. Compute the theoretical velocity (in units per hour). 4. Compute the actual velocity (in units per hour).

  • An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes,...

    An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)    Minimum cycle time minutes Maximum cycle time minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter...

  • An assembly line with 17 tasks is to be balanced. The longest task is 2.3 minutes,...

    An assembly line with 17 tasks is to be balanced. The longest task is 2.3 minutes, and the total time for all tasks is 18 minutes. The line will operate for 490 minutes per day. a. What is the minimum number of workstations needed if the output rate is to be 170 units per day? (Round the final answer to the next whole number.) Number of workstation             b. What cycle time will provide an output rate of 126 units per...

  • An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 1...

    An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)    Minimum cycle time minutes Maximum cycle time minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the...

  • An assembly line with 17 tas ks is to be balanced. The longest task is 2.4...

    An assembly line with 17 tas ks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 17 minutes. The line will operate for 474 minutes per day. a. What is the OT? minutes minutes b. What is the minimum cycle time? c. What is the maximum cycle time? minutes d. What is the range of output that is theoretically possible for the line? to units e. What is the minimum number...

  • Cycle Time and Velocity Norton Company has the following data for one of its production departments: Theoretical velocity: 180 units per hour Productive minutes available per year: 62,000,000 A...

    Cycle Time and Velocity Norton Company has the following data for one of its production departments: Theoretical velocity: 180 units per hour Productive minutes available per year: 62,000,000 Annual conversion costs: $372,000,000 Actual velocity: 72 units per hour Required: 1. Calculate the actual conversion cost per unit using actual cycle time and the standard cost per minute. Round your actual cycle time answer to three decimal places and your cost per unit answer to the nearest cent. Actual cycle time...

  • A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation...

    A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units.hr 1.8 units/hr Assembly a Sawing 0.8 units/hr Sanding Welding 5 units/hr Assembly 0.8 units/hr Driling 5 units.hr Assembly 0.8 units/hr a) Sanding is the bottleneck b) The bottleneck...

  • In the first quarter of operations, a manufacturing cell produced 150,000 stereo speakers, using 17,000 production...

    In the first quarter of operations, a manufacturing cell produced 150,000 stereo speakers, using 17,000 production hours. In the second quarter, the cycle time was 10 minutes per unit with the same number of production hours as were used in the first quarter. Required: 1. Compute the velocity (per hour) for the first quarter. If required, round your answer to two decimal places. units per hour 2. Compute the cycle time for the first quarter (minutes per unit produced). If...

  • 1 . Product A has a unit profit of $40 and takes 10 minutes on the...

    1 . Product A has a unit profit of $40 and takes 10 minutes on the bottleneck; Product B has unit profit of $60 and takes 30 minutes on the bottleneck. Non-bottleneck operations have infinite capacity because capacity can be added at no cost. The bottleneck has a capacity of 24 hours in a day. Should I maximize feasible production of: a. Product A b. Product B   2In terms of setting up a safety program, Heinrich’s Safety Triangle states the...

  • Compute the takt time for a system where the total time per shift is 480 minutes,...

    Compute the takt time for a system where the total time per shift is 480 minutes, there are two shifts, and workers on each shift are given two 15-minute breaks and 45 minutes for lunch. Daily demand is 650 units. What cycle time would match capacity and demand if demand is 120 units a day, there are two shifts of 480 minutes each, and workers are given two half-hour breaks during each shift, one of which is for lunch or...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT