A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from
0.7 units/hr a) Drilling is the bottleneck b) The bottleneck time is 33.33 minutes per unit (round your response to two decim


0.7 units/hr a) Drilling is the bottleneck b) The bottleneck time is 33.33 minutes per unit (round your response to two decim
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a.

For the bottleneck we need to figure out the process giving least units per hour

Since assembly has three parts running in parallel, total capacity of assembly is 0.8*3 = 2.4 units per hour

Hence out of all processes, sanding has the least units/hr i.e 1.8 and hence is the bottleneck process

b. 1.8 units per hour implies 60 mins for 1.8 units i.e. 60/1.8 = 33.33 mins per unit

c.

For sawing it is 60/2.5 24 mins per unit
For drilling it is 60/5 12 mins per unit
For welding it is 60/5 12 mins per unit
For assembly it is 60/0.8 75 mins per unit

Hence throughput time will be total time taken for sawing + sanding + welding + assembly (since drilling takes less time compared to sawing + sanding) = 24 + 33.33 + 12 + 75 = 144.33 mins

d. 8 hrs per day 20 days a month i.e. 160 hrs i.e. 160X60 = 9600 mins

Monthly capacity of the manufacturing process = =9600/144.33 = 67

Add a comment
Know the answer?
Add Answer to:
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation...

    A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units/hr Sawing 2.1 units/he Sanding Assembly 0.8 unitsthe Welding 6 units.hr Assembly 0.8 units Drilling 5 unitshe Assembly 0.8 untui is the bottleneck 0.7 units/hr a) Drilling is the...

  • Can someone help me with bumber 3? i do not know if i did it right,...

    Can someone help me with bumber 3? i do not know if i did it right, i also dont know how to find 3. d. 3. A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 60/24-25min 60/2 = 30 min...

  • The three-station work cell illustrated in the figure below has a product that must go through...

    The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. a) The bottleneck time of the system is 6 minutos per unit (onitor your response as a whole number). b) Station 3 is the bottleneck station c) The throughout time is 13 minutes (onter your response as a whole number). d) If the firm operates 8 hours per...

  • A production process Kenneth Day Manufacturing is shown in the rebelow. Thengertion go through only one...

    A production process Kenneth Day Manufacturing is shown in the rebelow. Thengertion go through only one of the three assembly operations (the operations are in parte tod a y the wing and wegende Aroute to round your The botenecke mi t The Proughout time of the overall system a n d you to be

  • What is the process time of the system? b) What is the bottleneck time of this...

    What is the process time of the system? b) What is the bottleneck time of this work cell? c)What is the process cycle time? d) If the firm operates 10 hours per day, 5 days per week, what is the weekly capacity of this work cell? The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. o Capacity:...

  • The following diagram describes a process that consists of eight separate operations, with sequential relationships and...

    The following diagram describes a process that consists of eight separate operations, with sequential relationships and capacities (units per hour) as shown below. Operation A:13/hr > Operation B:11/hr > Operation C:19/hr > Operation G:28/hr > Operation H:19/hr Operation D:3/hr > Operation E:6/hr > Operation F: 10/hr > What is the throughput time (in minutes)? *Keep at least 4 decimal places in your calculation.

  • 1. The bottleneck time of the system is - ??? minutes per unit ​(enter your response...

    1. The bottleneck time of the system is - ??? minutes per unit ​(enter your response as a whole​ number). 2. Which Station (1, 2, or 3) is the bottle neck station? 3. The throughput time is - ?????? 4. If the firm operates 11 hours per? day, 5 days per? week, the weekly capacity of this work cell is?....... units? (enter your response as a whole? number). The three-station work cell illustrated in the figure below has a product...

  • In the first quarter of operations, a manufacturing cell produced 150,000 stereo speakers, using 17,000 production...

    In the first quarter of operations, a manufacturing cell produced 150,000 stereo speakers, using 17,000 production hours. In the second quarter, the cycle time was 10 minutes per unit with the same number of production hours as were used in the first quarter. Required: 1. Compute the velocity (per hour) for the first quarter. If required, round your answer to two decimal places. units per hour 2. Compute the cycle time for the first quarter (minutes per unit produced). If...

  • Problem 5-15 The following diagram describes a process that consists of eight separate operations with sequential...

    Problem 5-15 The following diagram describes a process that consists of eight separate operations with sequential relationships and capacities (units per hour) as shown. 20/hr 3 15/hr 10/hr 34/hr 30/hr 8 5/hr 4 8/hr 5 12/hr 6 a. What is the current capacity of the entire process? units b-1. If you could increase the capacity of only two operations through process Apps forquck arom place yor booinks here on 9w bookman barbsport bookmarks now- Help Problem 6-1 3 An assembly...

  • In the figure below, two lines (1, 2) produce in parallel. The final process combines production...

    In the figure below, two lines (1, 2) produce in parallel. The final process combines production in one way or another as described below. Hourly capacity of each process is shown in the table. А D E 17 Process Units/Hr A B 10 с 12 D 15 9 14 ESG Consider two scenarios: Scenario 1 Lines 1 and 2 produce different products, which are individually packaged in process G. a System capacity is units. b. Is process Ga bottleneck? (Click...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT