Question

The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2 Capacity: 30 units/hr Station 1 Machine A Station 2Station 3 Station 1 Machine Capacity: Capacity 4 units/hr12 units/h Capacity: 30 units/hr

1. The bottleneck time of the system is - ??? minutes per unit ​(enter your response as a whole​ number).

2. Which Station (1, 2, or 3) is the bottle neck station?

3. The throughput time is - ??????

4. If the firm operates 11 hours per? day, 5 days per? week, the weekly capacity of this work cell is?.......

units? (enter your response as a whole? number).

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
1. The bottleneck time of the system is - ??? minutes per unit ​(enter your response...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • What is the process time of the system? b) What is the bottleneck time of this...

    What is the process time of the system? b) What is the bottleneck time of this work cell? c)What is the process cycle time? d) If the firm operates 10 hours per day, 5 days per week, what is the weekly capacity of this work cell? The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. o Capacity:...

  • NEED ANSWER D. The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has...

    NEED ANSWER D. The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 2 Station 3 5 min/unit 12 min/unit Station 1 Machine B 12 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3....

  • The three stations work cell illustrated in the figure  below has a product that must go...

    The three stations work cell illustrated in the figure  below has a product that must go through one of the two machines at station 1 ( they are parallel) before proceeding  to station 2 Capacity:30 units/hrs Station 1 Machine A Station 1 Machine B Capacity:30 units / hrs Station 2 Capacity 12 units/hrs Station 3 Capacity 4 units/hrs A) The bottleneck time of the system is .......minutes per unit ( enter your response as  whole  number) B) Station 1 or...

  • The three-station work cell illustrated in the figure below has a product that must go through...

    The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. a) The bottleneck time of the system is 6 minutos per unit (onitor your response as a whole number). b) Station 3 is the bottleneck station c) The throughout time is 13 minutes (onter your response as a whole number). d) If the firm operates 8 hours per...

  • A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation...

    A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units.hr 1.8 units/hr Assembly a Sawing 0.8 units/hr Sanding Welding 5 units/hr Assembly 0.8 units/hr Driling 5 units.hr Assembly 0.8 units/hr a) Sanding is the bottleneck b) The bottleneck...

  • number. Umit the "> sign in your response.) Total processing time in minutes per machine: Number...

    number. Umit the "> sign in your response.) Total processing time in minutes per machine: Number of each machine needed and total cost A (Click to select) B (Click to select) ) C (Click to select) ) Buy (Click to select): (Click to select) machines. b. Consider this additional information: The machines differ in terms of hourly operating costs: The A machines have an hourly operating cost of $10 each, B machines have an hourly operating cost of $11 each,...

  • A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation...

    A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units/hr Sawing 2.1 units/he Sanding Assembly 0.8 unitsthe Welding 6 units.hr Assembly 0.8 units Drilling 5 unitshe Assembly 0.8 untui is the bottleneck 0.7 units/hr a) Drilling is the...

  • Can someone help me with bumber 3? i do not know if i did it right,...

    Can someone help me with bumber 3? i do not know if i did it right, i also dont know how to find 3. d. 3. A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 60/24-25min 60/2 = 30 min...

  • Macon Controls produces three different types of control units used to protect industrial equipment from overheating....

    Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two​ 8-hour shifts, 5 days per​ week, 52 weeks per year. The table below provides the time standards at the​ bottleneck, lot​ sizes, and demand forecasts for the three units. Because of demand​ uncertainties, the operations manager obtained three demand forecasts​ (pessimistic,...

  • a) The normal time for the "prepare daily reports" operation = _________ minutes (round your response...

    a) The normal time for the "prepare daily reports" operation = _________ minutes (round your response to two decimal places). The normal time for the "photocopy results" operation = __________ minutes (round your response to two decimal places). The normal time for the "label and package reports" operation = _________ minutes (round your response to two decimal places). The normal time for the "distribute reports" operation = _________ minutes (round your response to two decimal places). The normal time for...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT