Question

Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...

Problem 12-18 (Algorithmic)

A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions:

Contractor Probability Distribution of Bid
A Uniform probability distribution between $590,000 and $790,000
B Normal probability distribution with a mean bid of $690,000 and a standard deviation of $49,000

If required, round your answers to three decimal places.

  1. If the building contractor submits a bid of $730,000, what is the probability that the building contractor will obtain the bid? Use an Excel worksheet to simulate 1,000 trials of the contract bidding process.

    The probability of winning the bid of $730,000 =

  2. The building contractor is also considering bids of 755,000 and $765,000. If the building contractor would like to bid such that the probability of winning the bid is about 0.6, what bid would you recommend? Repeat the simulation process with bids of $755,000 and $765,000 to justify your recommendation.

    The probability of winning the bid of $755,000 =  
    The probability of winning the bid of $765,000 =  

    The reccomendation would be to choose the bid of $
0 0
Add a comment Improve this question Transcribed image text
Answer #1

As Contractor A bid follows a uniform distribution, the probability that the bid is more than contractor A is:

P(A) = (730000 - 590000)/(790000 - 590000)

P(A) = 0.7

As Contractor B bid follows a normal distribution, the probability that the bid is more than contractor B is:

P(z<=x) where z = (730000 - 690000)/49000

z = 0.816

Hence, P(z<=x) = P(B) = 0.792

Therefore, probability of winning the bid of $730,000 = P(A). P(B) =0.7*0.792 = 0.555

B) Doing the same procedure for the bid of 755000,

P(A) = 0.825

P(B) = 0.907

P(winning the bid of $755,000)= 0.749

The probability of winning the bid of $765000 = P(A). P(B) = 0.875 * 0.937 = 0.820

The recommendation would be to choose the bid of $755000.

Add a comment
Know the answer?
Add Answer to:
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A building contractor is preparing a bid an new construction project. Two other contractors will be...

    A building contractor is preparing a bid an new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributlons: Contractor Probability Distribution Bid A Uniform probability distribution between $600,000 and $800,000 mean bid of $700,000 and a Normal probablity distributlon with standard deviation of $50,000 If required, round your answers to three decimal places. simulate 1,000 trials of the...

  • A building contractor is preparing a bid on a new construction project. Two other contractors will...

    A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for this project. In this case, the lowest bid wins the contract. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions (PLEASE SHOW IN EXCEL WITH FORMULAS FOR FULL RATING) A. Suppose the building contractor submits a bid of $650,000, what is the probability that the contractor submits the lowest bid and...

  • A contractor is to bid on one of two construction projects, Project A or Project B....

    A contractor is to bid on one of two construction projects, Project A or Project B. If the firm wins project A, its estimated profit is $2,000,000; if the firm wins project B, the estimated profit is $3,000,000. The cost of putting the bid together for the projects is $200,000 for A and $250,000 for B. Due to a difference in the number of qualified competitors, the firm estimates its probability of getting Project A as 0.7 and its probability...

  • TORENTO CONSTRUCTION: ETHICAL CONTRACTING On December 27, 2010, Cary Holmes, manager of the Supply Chain Management...

    TORENTO CONSTRUCTION: ETHICAL CONTRACTING On December 27, 2010, Cary Holmes, manager of the Supply Chain Management (SCM) group at Torento Construction Inc. (NCG), was in his office in Torento, Ontario, trying to organize the thoughts running through his head as a result of a recent bidding to save operating costs at NCG. There was no problem in terms of the final outcome; in fact, the bid was going to result in cost savings of 25 per cent, which was exactly...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT