Explain what payback period, NPV and IRR are in layman’s terms.
Payback period is the period in which initial investment is recovered.
If the Actual Payback period < desired Payback period, then accept the project.
NPV = PV of Cash Inflows @WACC - PV of Cash Outflows @WACC.
IF the NPV of Project is >/= 0, then accept the project else reject the same.
IRR is the Rate of Ret that Project gives or IRR is the Rat which PV of Cash Inflows are equal to PV of Cash Outflows.
If IRR of Project is >/= WACC, accept the Project else reject the same.
Pls comment, if any further asssistane is required.
Based on the (NPV / IRR / Discounted Payback Period / modified IRR), an investment is acceptable if its (NPV / IRR / Discounted Payback Period / modified IRR) is less than some prescribed number of years. ( ... ) is the choices
Please show your steps! Question 1 a) What is the NPV, IRR, and payback period of a project with the following cash flows if WACC is 20%? Time: 0 -$350,000 1 $100,000 2 $100,000 3 $100,000 $100,000 A $50,000 $50,000 NPV= IRR= Payback period b) Should you accept or reject the project according to NPV and IRR?!
Please show your steps! Question 1 a) What is the NPV, IRR, and payback period of a project with the following cash flows if WACC is 20%? Time: 0 -$350,000 1 $100,000 2 $100,000 3 $100,000 5 $50,000 $50,000 NPV= IRRE Payback period= b) Should you accept or reject the project according to NPV and IRR?
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85.000 and expected free cash flows of $20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
(Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash outlay of 90,000 and expected free cash flows of 30,000 at the end of each year for 6 years. The required rate of return for this project is 8 percent. a. What is the project's payback period? b. What is the project's NPV ? c. What is the project's PI ? d. What is the project's IRR ?
difference between payback period and accounting rate of return and NPV and IRR
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85 comma 000 and expected free cash flows of $30 comma 000 at the end of each year for 6 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
5. ULJI,123 dl the end of the next 3 years (Payback period, IRR, & NPV) You are considering a project with an initial cash outlay of $5,213, and expect to receive free cash flows $2,125 at the end of each year for the next 7 years. If required rate of return is 10%, what is the firm's a. Payback period? b. NPV? c. IRR? d. Should this project be accepted? (use answers to parts b and c)
Explain how payback period, NPV, and IRR criteria are used in decision making and provide example in which each is most appropriate as an appraisal tool. Table 1: Bank of Ghana Bill rates Issue Date 20 April 2020 27 Apr 2020 27 Apr 2020 Security type 91 day 182 day 91 day Discount rate 13.39 13.11 13.55 Interest rate 13.86 14.03 14.03
Calculate the Payback Period, IRR, NPV, and PI if cash flows are as follows: -$2M; $600K; $850K; $900K: and $700K. (WACC is 10%)