a)
NPV
350,000 - [(100,000/1.20) + (100,000/(1.20)^2) + (100,000/(1.20) ^3) + (50,000/(1.20) ^4) + (50,000/(1.20) ^5)]
= - 95,145.31893
IRR
350,000 - [(100,000/1 + r) + (100,000/(1+r)^2) + (100,000/(1+r) ^3) + (50,000/(1+r) ^4) + (50,000/(1+r) ^5) = 0
= 350,000 = [(100,000/1 + r) + (100,000/(1+r)^2) + (100,000/(1+r) ^3) + (50,000/(1+r) ^4) + (50,000/(1+r) ^5)
on solving the above equation
we get
r = 5.31078 %
payback period
300,000 can be recovered in initial 3 years of cash flow
rest of 50,000 can be recovered in the 4th year
hence 350,000 can be recovered in 4 years
payback period is 4 years .
b) we should reject the project by NPV calculations because we have a negative NPV for this project - 95,145.31893
According to IRR method we should reject the project as the IRR is less than WACC i.e, 5.31078 % < 20 %
This means that the project is giving less rate of return than the cost of capital of the project .
Please show your steps! Question 1 a) What is the NPV, IRR, and payback period of a project with the following cash...
Please show your steps! Question 1 a) What is the NPV, IRR, and payback period of a project with the following cash flows if WACC is 20%? Time: 0 -$350,000 1 $100,000 2 $100,000 3 $100,000 $100,000 A $50,000 $50,000 NPV= IRR= Payback period b) Should you accept or reject the project according to NPV and IRR?!
Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR, and MIRR. The required rate of return is 8 percent. Year CF 0 $(50,000.00) 1 $15,000.00 2 $15,000.00 3 $15,000.00 4 $15,000.00 5 $5,000.00
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85.000 and expected free cash flows of $20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
(Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash outlay of 90,000 and expected free cash flows of 30,000 at the end of each year for 6 years. The required rate of return for this project is 8 percent. a. What is the project's payback period? b. What is the project's NPV ? c. What is the project's PI ? d. What is the project's IRR ?
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85 comma 000 and expected free cash flows of $30 comma 000 at the end of each year for 6 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR Cash Flow......($200).....$850....($700)......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Accept the project because the payback is short b. Accept the project because the NPV is greater than zero c. Reject the project because the IRR is less than the required rate of return d. Reject the project because...
This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows generated by mutually exclusive projects Formulate a recommendation using IRR, NPV and Payback Period as the criteria Background Suppose that your firm is considering the following two mutually exclusive projects. Both projects have the same initial cost of $312,500 and the resulting annual cash flows for the first five years are as shown in the table below: Year Alpha Beta 0 $ (312,500) $...
Calculate the Payback Period, IRR, NPV, and PI if cash flows are as follows: -$2M; $600K; $850K; $900K: and $700K. (WACC is 10%)
Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR Cash Flow.....($200).....$850.......($700).......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Reject the project because the NPV is less than zero b. Accept the project because the IRR is greater than zero c. Accept the project because the NPV is greater than zero d. Accept the project because the payback...
1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR A +42,176 2 years, +$10,500 16.4% B +39,090 2 years, +9,670 15.8% C +41,894 3 years, +16,620 13.2% D +43,778 3 years, +11,625 14.9% E +38,952 2 years, +15,475 15.9% B. What is the Payback Period of a project with an initial cost of $75,000, Year 1 cash flow of $20,000 which increases by 5% each year? If the Payback cutoff is 3 years,...