Weston Industries is considering the following independent
projects for the coming year:
|
Required |
Expected |
|
|
|
|
|
Y |
3 million |
9.5% |
Average |
Z |
7 million |
6.5% |
Low |
Weston’s WACC is 9 percent, but it adjusts for risk by adding 2
percent to the WACC for high-risk projects and subtracting 2
percent for low-risk projects. Which project(s) should Weston
accept assuming it faces no capital constraints?
a. |
Project Z only |
|
b. |
Projects Y and Z |
|
c. |
Projects X and Y |
|
d. |
Projects X and Z |
|
e. |
Project Y only |
|
Required |
Expected |
|
Required rate of return = WACC+Risk Premium |
|
|
|
|
11% |
Y |
3 million |
9.5% |
Average |
9% |
Z |
7 million |
6.5% |
Low |
7% |
Hence, acceptable project is only Y since expected return is greater than required return
Hence, the answer is e.
Weston Industries is considering the following independent projects for the coming year: Project Required Investment Expected...
Please show steps. Ziege Systems is considering the following independent projects for the coming year: Required Investment Rate of Return Project Risk $4 million 15.00% > High 5 million 12.50 0 High 0 3 million 10.50 Low 2 million 9.50 0 Average 6 million 13.50 m High 5 million 13.50 Average I Low 6 million 7.50 Low 3 million 12.25 Ziege's WACC is 11.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 12.25% High B 5 million 14.75 High C 3 million 10.25 Low D 2 million 10.25 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 8.25 Low H 3 million 12.75 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Required Investment Rate of Return Project Risk A $4 million 13.00% High 5 million 10.50 High 3 million 8.50 Low 8.00 Average 2 million 6 million 11.50 High 5 million 11.50 Average 6 million 6.00 Low 3 million 11.00 LOW Ziege's WACC is 9.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2% for low-risk projects. a. Which projects should Ziege accept if it faces no capital constraints? Project A Reject Project...
Ch 10: End-of-Chapter Problems-LPK - The Cost Who wins LSU-Bama Sett eBook Ziege Systems is considering the following independent projects for the coming year: Required Investment Rate of Return Project Risk "$4 million 13.00% 10.50 High High 0 2 5 million 1 3 million 8.50 Low 2 million 8.00 Average 6 million 11.50 High 2 5 million 11.50 Average 6 million 6.00 Low 3 million 11.00 Ziege's WACC is 9.00%, but it adjusts for risk by adding 2% to the...
QUESTION 1 Star Industries is considering three alternative projects for the company's investment. The cash flows for three independent projects are as follows: Year 1 Project A ($50,000) $10,000 $15,000 $20,000 $25,000 $30,000 Project B ($100,000) $25,000 $25,000 $25,000 $25,000 $25,000 Project C ($450,000) $200,000 $200,000 $200,000 a) If the discount rate for all three projects is 9.5 percent, calculate the profitability index (PI) of these three projects. Which project will be accepted if the projects are mutually exclusive? b)...
A firm is considering the following four independent projects: Project Beta of project TRR Α. 0.9 11% B 2.0 19% 1.0 14% 0. 4 10% The risk-free rate is 5%, the expected market return is 10%. The firm's WACC is 13%. Which of the following statements is correct (true)? Reject project A Accept projects B and C only Accept project D only Accept project B only Accept all projects
Lane Industries is considering three independent projects, each of which requires a $3.4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 13% IRR = 15% Project M (medium risk): Cost of capital = 11% IRR = 9% Project L (low risk): Cost of capital = 10% IRR = 11% Note that the projects' costs of capital vary because the projects have...
An all-equity firm is considering the following projects: Project Beta IRR W .65 10.0 % X .90 10.5 Y 1.20 14.0 Z 1.80 17.0 The T-bill rate is 5 percent, and the expected return on the market is 12 percent. Required: (a) Which projects have a higher expected return than the firm’s 12 percent cost of capital? Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project...
Robben Manufacturing has the following two possible projects. The required return is 11 percent. Year Project Y Project Z 0 27,200 52.000 21,000 23,000 19,000 21,000 13,200 11,600 14.000 9.600 a. What is the profitability index for each project? (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Profitability index Project Y Project Z b. What is the NPV for each project? (Do not round intermediate calculations and round your answers to 2 decimal...
Dahlia Manufacturing has the following two possible projects. The required return is 12 percent. Year Project Y Project Z 0 –$31,000 –$60,000 1 14,000 24,000 2 12,400 23,000 3 14,800 22,000 4 10,400 21,000 Required: (a) What is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 3 decimal places (e.g., 32.161).) Profitability index Project Y Project Z (b) What is the NPV for each project? (Do not round intermediate calculations. Round your answers...