Question

An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 %...

An all-equity firm is considering the following projects:
Project Beta IRR
W .65       10.0 %
X .90       10.5
Y 1.20       14.0
Z 1.80       17.0
The T-bill rate is 5 percent, and the expected return on the market is 12 percent.
Required:
(a) Which projects have a higher expected return than the firm’s 12 percent cost of capital?

Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project Y has a (Click to select)lowerhigher expected return, and Project Z has a (Click to select)higherlower expected return.

(b) Which projects should be accepted?

Project W should be (Click to select)acceptedrejected, Project X should be (Click to select)acceptedrejected, Project Y should be (Click to select)acceptedrejected, and Project Z should be (Click to select)acceptedrejected.

(c)

Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were used as a hurdle rate?

Project W would be (Click to select)correctly acceptedcorrectly rejectedincorrectly acceptedincorrectly rejected, Project X would be (Click to select)correctly rejectedincorrectly acceptedincorrectly rejectedcorrectly accepted, Project Y would be (Click to select)incorrectly acceptedcorrectly rejectedincorrectly rejectedcorrectly accepted, and Project Z would be (Click to select)incorrectly rejectedincorrectly acceptedcorrectly rejectedcorrectly accepted.

"show steps please"

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Expected Return of W =Risk free rate+Beta*(Market Return-Risk free Rate)=5%+0.0.65*(12%-5%) =9.55%
Expected Return of X =Risk free rate+Beta*(Market Return-Risk free Rate)=5%+0.0.90*(12%-5%) =11.30%
Expected Return of Y =Risk free rate+Beta*(Market Return-Risk free Rate)=5%+1.20*(12%-5%) =13.40%
Expected Return of Z =Risk free rate+Beta*(Market Return-Risk free Rate)=5%+1.80*(12%-5%) =17.60%

a. If cost of capital is 12%. When Expected rate is higher than cost of capital it is higher or else lower
Project W has lower expected return ,​​​​​​​​​​​​​​Project X has lower expected return .​​​​​​​​​​​​​​Project Y has higher expected return .
​​​​​​​​​​​​​​Project Z has higher expected return .

b.If IRR is less than expected return it should be accepted or it else it should be rejected.
​​​​​​​Project W would be  rejected ,​​​​​​​​​​​​​​​​​​​​​Project X would be accepted  .​​​​​​​​​​​​​​Project Y would be rejected. .
​​​​​​​​​​​​​​Project Z would be accepted.

c. If IRR would be used as hurdle rate
Project W Correctly rejected.
Project X incorrectly accepted​​​​​​​
Project Y incorrectly rejected. ​​​​​​​
Project Z correctly accepted

Add a comment
Know the answer?
Add Answer to:
An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 %...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X .76 10.8 Y 1.41 14.3 Z 1.52 17.3 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm’s 12.3 percent cost of capital?    Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)higherlower expected return, Project Y has a (Click...

  • An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87...

    An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87 9.7% Y 1.13 12.1% Z 1.47 15.2% The T-bill rate is 4.2 percent, and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a _____(answer 1) (lower or Higher)____ expected return, Project X has a _____(answer 2) (lower or Higher)____ expected return, Project Y has a _____(answer 3) (lower or Higher)____ expected...

  • n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90...

    n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90 11.4 Y 1.10 12.1 Z 1.35 15.1 he T-bill rate is 4 percent, and the expected return on the market is 12 percent. . Which projects have a higher expected return than the firm's 12 percent cost of capital? expected return, Project X has a Project W has a expected return, Project Y has a expected return expected return, and Project Z has a...

  • An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108...

    An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108 143 173 1.52 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm's 12.3 percent cost of capital? expected return, Project X has a expected return, Project Y has a Project W has a expected return, and Project Z has a expected return b. Which projects should...

  • An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3%...

    An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...

  • An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X .75     10.6 Y 1.31     14.1 Z 1.42     17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...

  • 17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR...

    17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35 10.8 12.8 < 13.3 N The T-bill rate is 4 percent, and the expected return on the market is 11 percent. a. Which projects have a higher expected return than the firm's 11 percent cost of capital? b. Which projects should be accepted? c. Which projects would be incorrectly accepted or rejected if the firm's overall cost...

  • Project Beta IRR W .57 10.0 % X .93 10.5 Y 1.13 14.0 Z 1.70 17.0...

    Project Beta IRR W .57 10.0 % X .93 10.5 Y 1.13 14.0 Z 1.70 17.0 The T-bill rate is 4.5 percent, and the expected return on the market is 13 percent. a. Compared with the firm's 12 percent cost of capital, Project W has a __________ expected return, Project X has a __________ expected return, Project Y has a __________ expected return, and Project Z has a __________ expected return. b. Project W should be __________, Project X should...

  • In section (a) the options for each drop down are higher or lower In section (b)...

    In section (a) the options for each drop down are higher or lower In section (b) the options for each drop down section are accepted or rejected In section (c) the options for each drop down section are correctly accepted, incorrectly accepted, correctly rejected or incorrectly rejected Thank you! An all-equity firm is considering the following projects: Project W Х Beta .80 .90 1.10 1.35 IRR 10.2% 11.4 12.6 15.1 Ž The T-bill rate is 4 percent, and the expected...

  • An all-equity firm is considering the following projects: Project Beta W 58 IRR 9.0 % X 87 9.7 Y 1.13 12.1 Z 1.47 15.2...

    An all-equity firm is considering the following projects: Project Beta W 58 IRR 9.0 % X 87 9.7 Y 1.13 12.1 Z 1.47 15.2 The T-bill rate is 4.2 percent and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a expected return, Project Y has a expected return expected return, Project X has a. expected return, and Project Z has a b. Project W should be Project...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT