An all-equity firm is considering the following projects: |
Project | Beta | IRR | |||
W | .65 | 10.0 | % | ||
X | .90 | 10.5 | |||
Y | 1.20 | 14.0 | |||
Z | 1.80 | 17.0 | |||
The T-bill rate is 5 percent, and the expected return on the market is 12 percent. |
Required: | |
(a) | Which projects have a higher expected return than the firm’s 12 percent cost of capital? |
Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project Y has a (Click to select)lowerhigher expected return, and Project Z has a (Click to select)higherlower expected return. |
(b) | Which projects should be accepted? |
Project W should be (Click to select)acceptedrejected, Project X should be (Click to select)acceptedrejected, Project Y should be (Click to select)acceptedrejected, and Project Z should be (Click to select)acceptedrejected. |
(c) |
Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were used as a hurdle rate? |
Project W would be (Click to select)correctly acceptedcorrectly rejectedincorrectly acceptedincorrectly rejected, Project X would be (Click to select)correctly rejectedincorrectly acceptedincorrectly rejectedcorrectly accepted, Project Y would be (Click to select)incorrectly acceptedcorrectly rejectedincorrectly rejectedcorrectly accepted, and Project Z would be (Click to select)incorrectly rejectedincorrectly acceptedcorrectly rejectedcorrectly accepted. "show steps please" |
Expected Return of W =Risk free rate+Beta*(Market Return-Risk
free Rate)=5%+0.0.65*(12%-5%) =9.55%
Expected Return of X =Risk free rate+Beta*(Market Return-Risk free
Rate)=5%+0.0.90*(12%-5%) =11.30%
Expected Return of Y =Risk free rate+Beta*(Market Return-Risk free
Rate)=5%+1.20*(12%-5%) =13.40%
Expected Return of Z =Risk free rate+Beta*(Market Return-Risk free
Rate)=5%+1.80*(12%-5%) =17.60%
a. If cost of capital is 12%. When Expected rate is higher than
cost of capital it is higher or else lower
Project W has lower expected return
,Project X has lower expected return
.Project Y has higher expected
return .
Project Z has higher expected return
.
b.If IRR is less than expected return it should be accepted or it
else it should be rejected.
Project W would be rejected
,Project X would be
accepted .Project Y would
be rejected. .
Project Z would be accepted.
c. If IRR would be used as hurdle rate
Project W Correctly rejected.
Project X incorrectly accepted
Project Y incorrectly rejected.
Project Z correctly accepted
An all-equity firm is considering the following projects: Project Beta IRR W .65 10.0 %...
An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X .76 10.8 Y 1.41 14.3 Z 1.52 17.3 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm’s 12.3 percent cost of capital? Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)higherlower expected return, Project Y has a (Click...
An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87 9.7% Y 1.13 12.1% Z 1.47 15.2% The T-bill rate is 4.2 percent, and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a _____(answer 1) (lower or Higher)____ expected return, Project X has a _____(answer 2) (lower or Higher)____ expected return, Project Y has a _____(answer 3) (lower or Higher)____ expected...
n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90 11.4 Y 1.10 12.1 Z 1.35 15.1 he T-bill rate is 4 percent, and the expected return on the market is 12 percent. . Which projects have a higher expected return than the firm's 12 percent cost of capital? expected return, Project X has a Project W has a expected return, Project Y has a expected return expected return, and Project Z has a...
An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108 143 173 1.52 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm's 12.3 percent cost of capital? expected return, Project X has a expected return, Project Y has a Project W has a expected return, and Project Z has a expected return b. Which projects should...
An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...
An all-equity firm is considering the following projects: Project Beta IRR W .64 9.5 % X .75 10.6 Y 1.31 14.1 Z 1.42 17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...
17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35 10.8 12.8 < 13.3 N The T-bill rate is 4 percent, and the expected return on the market is 11 percent. a. Which projects have a higher expected return than the firm's 11 percent cost of capital? b. Which projects should be accepted? c. Which projects would be incorrectly accepted or rejected if the firm's overall cost...
Project Beta IRR W .57 10.0 % X .93 10.5 Y 1.13 14.0 Z 1.70 17.0 The T-bill rate is 4.5 percent, and the expected return on the market is 13 percent. a. Compared with the firm's 12 percent cost of capital, Project W has a __________ expected return, Project X has a __________ expected return, Project Y has a __________ expected return, and Project Z has a __________ expected return. b. Project W should be __________, Project X should...
In section (a) the options for each drop down are higher or lower In section (b) the options for each drop down section are accepted or rejected In section (c) the options for each drop down section are correctly accepted, incorrectly accepted, correctly rejected or incorrectly rejected Thank you! An all-equity firm is considering the following projects: Project W Х Beta .80 .90 1.10 1.35 IRR 10.2% 11.4 12.6 15.1 Ž The T-bill rate is 4 percent, and the expected...
An all-equity firm is considering the following projects: Project Beta W 58 IRR 9.0 % X 87 9.7 Y 1.13 12.1 Z 1.47 15.2 The T-bill rate is 4.2 percent and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a expected return, Project Y has a expected return expected return, Project X has a. expected return, and Project Z has a b. Project W should be Project...