Required return as per CAPM = Risk free rate + beta*(market return - risk free rate) | |||
Project | Beta | Expected Return | |
W | 0.89 | 11.53 | lower |
X | 0.76 | 10.62 | lower |
Y | 1.41 | 15.17 | Higher |
Z | 1.52 | 15.94 | Higher |
Projects whose IRR is higher than the Expected Return should be accepted | |||
W | Reject | ||
X | Accept | ||
Y | Reject | ||
Z | Accept | ||
c | |||
W | Reject | ||
X | Reject | Incorrectly Rejected | |
Y | Accept | Incorrectly Accepted | |
Z | Accept |
An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108...
An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X .76 10.8 Y 1.41 14.3 Z 1.52 17.3 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm’s 12.3 percent cost of capital? Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)higherlower expected return, Project Y has a (Click...
n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90 11.4 Y 1.10 12.1 Z 1.35 15.1 he T-bill rate is 4 percent, and the expected return on the market is 12 percent. . Which projects have a higher expected return than the firm's 12 percent cost of capital? expected return, Project X has a Project W has a expected return, Project Y has a expected return expected return, and Project Z has a...
An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...
An all-equity firm is considering the following projects: Project Beta IRR W .65 10.0 % X .90 10.5 Y 1.20 14.0 Z 1.80 17.0 The T-bill rate is 5 percent, and the expected return on the market is 12 percent. Required: (a) Which projects have a higher expected return than the firm’s 12 percent cost of capital? Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project...
An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87 9.7% Y 1.13 12.1% Z 1.47 15.2% The T-bill rate is 4.2 percent, and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a _____(answer 1) (lower or Higher)____ expected return, Project X has a _____(answer 2) (lower or Higher)____ expected return, Project Y has a _____(answer 3) (lower or Higher)____ expected...
An all-equity firm is considering the following projects: Project Beta IRR W .64 9.5 % X .75 10.6 Y 1.31 14.1 Z 1.42 17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...
17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35 10.8 12.8 < 13.3 N The T-bill rate is 4 percent, and the expected return on the market is 11 percent. a. Which projects have a higher expected return than the firm's 11 percent cost of capital? b. Which projects should be accepted? c. Which projects would be incorrectly accepted or rejected if the firm's overall cost...
An all-equity firm is considering the following projects: Project Beta W 58 IRR 9.0 % X 87 9.7 Y 1.13 12.1 Z 1.47 15.2 The T-bill rate is 4.2 percent and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a expected return, Project Y has a expected return expected return, Project X has a. expected return, and Project Z has a b. Project W should be Project...
An all-equity firm is considering the following projects: Project Beta IRR W .56 9.2 % X .89 9.9 Y 1.11 12.3 Z 1.49 15.4 The T-bill rate is 4.4 percent, and the expected return on the market is 11.4 percent. Compared with the firm's 11.4 percent cost of capital, Project W has a expected return, Project X has a expected return, Project Y has a expected return, and Project Z has a expected return.
(5 points) An all equity firm is considering the following projects: 2. Project Beta 0.8 1.2 IRR 10% 12% The risk-free rate is 3% and the expected market rate premium is 8%. The firm has a beta equal to 1 (1 point) What is the firm's cost of capital? a. b. (2 points) Which projects should be accepted? Explain (2 point) Which projects will be incorrectly accepted or rejected if the firm's overall cost of capital were used to as...