Expected Return from the project = Risk free rate + beta*(Market Return - Risk Free Rate) | ||||
Project | Risk free rate | Beta | Market Return | Expected Return |
W | 4% | 0.8 | 12% | 10.40% |
X | 4% | 0.9 | 12% | 11.20% |
Y | 4% | 1.1 | 12% | 12.80% |
Z | 4% | 1.35 | 12% | 14.80% |
Projects Y and Z have higher expected return than cost of capital | ||||
b.The projects whose IRR is higher than expected return should be accepted | ||||
I.e. Projects X and Z | ||||
Project Y will be wrongly accepted and Project X would be wrongly rejected |
n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90...
An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...
An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87 9.7% Y 1.13 12.1% Z 1.47 15.2% The T-bill rate is 4.2 percent, and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a _____(answer 1) (lower or Higher)____ expected return, Project X has a _____(answer 2) (lower or Higher)____ expected return, Project Y has a _____(answer 3) (lower or Higher)____ expected...
An all-equity firm is considering the following projects: Project Beta IRR W .65 10.0 % X .90 10.5 Y 1.20 14.0 Z 1.80 17.0 The T-bill rate is 5 percent, and the expected return on the market is 12 percent. Required: (a) Which projects have a higher expected return than the firm’s 12 percent cost of capital? Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project...
An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108 143 173 1.52 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm's 12.3 percent cost of capital? expected return, Project X has a expected return, Project Y has a Project W has a expected return, and Project Z has a expected return b. Which projects should...
An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X .76 10.8 Y 1.41 14.3 Z 1.52 17.3 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm’s 12.3 percent cost of capital? Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)higherlower expected return, Project Y has a (Click...
An all-equity firm is considering the following projects: Project Beta IRR W .64 9.5 % X .75 10.6 Y 1.31 14.1 Z 1.42 17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...
17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35 10.8 12.8 < 13.3 N The T-bill rate is 4 percent, and the expected return on the market is 11 percent. a. Which projects have a higher expected return than the firm's 11 percent cost of capital? b. Which projects should be accepted? c. Which projects would be incorrectly accepted or rejected if the firm's overall cost...
An all-equity firm is considering the following projects: Project Beta W 58 IRR 9.0 % X 87 9.7 Y 1.13 12.1 Z 1.47 15.2 The T-bill rate is 4.2 percent and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a expected return, Project Y has a expected return expected return, Project X has a. expected return, and Project Z has a b. Project W should be Project...
In section (a) the options for each drop down are higher or lower In section (b) the options for each drop down section are accepted or rejected In section (c) the options for each drop down section are correctly accepted, incorrectly accepted, correctly rejected or incorrectly rejected Thank you! An all-equity firm is considering the following projects: Project W Х Beta .80 .90 1.10 1.35 IRR 10.2% 11.4 12.6 15.1 Ž The T-bill rate is 4 percent, and the expected...
An all-equity firm is considering the following projects: Project Beta IRR W .56 9.2 % X .89 9.9 Y 1.11 12.3 Z 1.49 15.4 The T-bill rate is 4.4 percent, and the expected return on the market is 11.4 percent. Compared with the firm's 11.4 percent cost of capital, Project W has a expected return, Project X has a expected return, Project Y has a expected return, and Project Z has a expected return.