Question

An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87...

An all-equity firm is considering the following projects:

Project Beta IRR

W .58 9%

X .87 9.7%

Y 1.13 12.1%

Z 1.47 15.2%

The T-bill rate is 4.2 percent, and the expected return on the market is 11.2 percent.

Compared with the firm's 11.2 percent cost of capital, Project W has a _____(answer 1) (lower or Higher)____ expected return, Project X has a _____(answer 2) (lower or Higher)____ expected return, Project Y has a _____(answer 3) (lower or Higher)____ expected return, and Project z has a _____(answer 4) (lower or Higher)____ expected return.

Project W should be ___(answer 5) (accepted or rejected)____, Project X should be ___(answer 6) (accepted or rejected)____, Project Y should be ___(answer 7) (accepted or rejected)____, and Project z should be ___(answer 8) (accepted or rejected)____.

If the firm's overall cost of capital were used as a hurdle rate, Project W would be ___(answer 9) (Correctly accepted, Correctly rejected, incorrectly accepted or incorrectly rejected)____, Project X would be ___(answer 10) (Correctly accepted, Correctly rejected, incorrectly accepted or incorrectly rejected)____, Project Y would be ___(answer 11) (Correctly accepted, Correctly rejected, incorrectly accepted or incorrectly rejected)____ and Project Z would be ___(answer 12) (Correctly accepted, Correctly rejected, incorrectly accepted or incorrectly rejected)____

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Expected Return of W =Risk free rate+Beta*(Market Return-Risk free Rate)=4.2%+0.58*(11.2%-4.2%) =8.26%
Expected Return of X =Risk free rate+Beta*(Market Return-Risk free Rate)=4.2%+0.87*(11.2%-4.2%) =10.29%
Expected Return of Y =Risk free rate+Beta*(Market Return-Risk free Rate)=4.2%+1.13*(11.2%-4.2%) =12.11%
Expected Return of Z =Risk free rate+Beta*(Market Return-Risk free Rate)=4.2%+1.47*(11.2%-4.2%) =14.49%

If cost of capital is 11.2%
Project W has lower expected return , ​​​​​​​​​​​​​​Project X has lower expected return .​​​​​​​​​​​​​​Project Y has higher expected return .
​​​​​​​​​​​​​​Project Z has higher expected return .

​​​​​​​Project W would be  rejected , ​​​​​​​​​​​​​​​​​​​​​Project X would be  rejected .​​​​​​​​​​​​​​Project Y would be accepted. .
​​​​​​​​​​​​​​Project Z would be accepted.

If IRR would be used as hurdle rate
Project W Correctly rejected.
Project X incorrectly accepted​​​​​​​
Project Y correctly accepted ​​​​​​​
Project Z incorrectly rejected.

Add a comment
Know the answer?
Add Answer to:
An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • An all-equity firm is considering the following projects: Project Beta W 58 IRR 9.0 % X 87 9.7 Y 1.13 12.1 Z 1.47 15.2...

    An all-equity firm is considering the following projects: Project Beta W 58 IRR 9.0 % X 87 9.7 Y 1.13 12.1 Z 1.47 15.2 The T-bill rate is 4.2 percent and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a expected return, Project Y has a expected return expected return, Project X has a. expected return, and Project Z has a b. Project W should be Project...

  • An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X .76 10.8 Y 1.41 14.3 Z 1.52 17.3 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm’s 12.3 percent cost of capital?    Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)higherlower expected return, Project Y has a (Click...

  • An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 %...

    An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 % X .90       10.5 Y 1.20       14.0 Z 1.80       17.0 The T-bill rate is 5 percent, and the expected return on the market is 12 percent. Required: (a) Which projects have a higher expected return than the firm’s 12 percent cost of capital? Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project...

  • n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90...

    n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90 11.4 Y 1.10 12.1 Z 1.35 15.1 he T-bill rate is 4 percent, and the expected return on the market is 12 percent. . Which projects have a higher expected return than the firm's 12 percent cost of capital? expected return, Project X has a Project W has a expected return, Project Y has a expected return expected return, and Project Z has a...

  • An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X .75     10.6 Y 1.31     14.1 Z 1.42     17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...

  • An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108...

    An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108 143 173 1.52 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm's 12.3 percent cost of capital? expected return, Project X has a expected return, Project Y has a Project W has a expected return, and Project Z has a expected return b. Which projects should...

  • An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3%...

    An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...

  • 17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR...

    17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35 10.8 12.8 < 13.3 N The T-bill rate is 4 percent, and the expected return on the market is 11 percent. a. Which projects have a higher expected return than the firm's 11 percent cost of capital? b. Which projects should be accepted? c. Which projects would be incorrectly accepted or rejected if the firm's overall cost...

  • In section (a) the options for each drop down are higher or lower In section (b)...

    In section (a) the options for each drop down are higher or lower In section (b) the options for each drop down section are accepted or rejected In section (c) the options for each drop down section are correctly accepted, incorrectly accepted, correctly rejected or incorrectly rejected Thank you! An all-equity firm is considering the following projects: Project W Х Beta .80 .90 1.10 1.35 IRR 10.2% 11.4 12.6 15.1 Ž The T-bill rate is 4 percent, and the expected...

  • An all-equity firm is considering the following projects: Project Beta IRR W .56 9.2 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .56 9.2 % X .89 9.9 Y 1.11 12.3 Z 1.49 15.4 The T-bill rate is 4.4 percent, and the expected return on the market is 11.4 percent. Compared with the firm's 11.4 percent cost of capital, Project W has a expected return, Project X has a expected return, Project Y has a expected return, and Project Z has a expected return.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT