Question

17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Using CAPM equation, Expected return = Risk free rate + Beta*(Expected market return - Risk free rate),

We get following expected returns for each project

Project Expected returns IRR
W 9.95% 8.9%
X 10.44% 10.8%
Y 11.63% 12.8%
Z 13.45% 13.3%

a) Projects Z and Y have higher return than firm's 11% cost of capital

b) Project W and Z have more expected return than IRR and hence accepted

c) Project W have been incorrectly rejected (because its 9.95% expected return is below 11% cost of capital but above 8.9% IRR and project Y has been incorrectly accepted (because its 11.63% expected return is higher than 11% cost of capital but lower than 12.8% IRR)

Add a comment
Know the answer?
Add Answer to:
17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • SML and WACC. An all-equity firm is considering the following projects: The T-bill rate is 4...

    SML and WACC. An all-equity firm is considering the following projects: The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm’s 12 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted or rejected if the firm’s overall cost of capital were used as a hurdle rate?

  • An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X .75     10.6 Y 1.31     14.1 Z 1.42     17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...

  • An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3%...

    An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...

  • n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90...

    n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90 11.4 Y 1.10 12.1 Z 1.35 15.1 he T-bill rate is 4 percent, and the expected return on the market is 12 percent. . Which projects have a higher expected return than the firm's 12 percent cost of capital? expected return, Project X has a Project W has a expected return, Project Y has a expected return expected return, and Project Z has a...

  • An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87...

    An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87 9.7% Y 1.13 12.1% Z 1.47 15.2% The T-bill rate is 4.2 percent, and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a _____(answer 1) (lower or Higher)____ expected return, Project X has a _____(answer 2) (lower or Higher)____ expected return, Project Y has a _____(answer 3) (lower or Higher)____ expected...

  • An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108...

    An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108 143 173 1.52 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm's 12.3 percent cost of capital? expected return, Project X has a expected return, Project Y has a Project W has a expected return, and Project Z has a expected return b. Which projects should...

  • An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .89 10.3 % X .76 10.8 Y 1.41 14.3 Z 1.52 17.3 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm’s 12.3 percent cost of capital?    Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)higherlower expected return, Project Y has a (Click...

  • An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 %...

    An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 % X .90       10.5 Y 1.20       14.0 Z 1.80       17.0 The T-bill rate is 5 percent, and the expected return on the market is 12 percent. Required: (a) Which projects have a higher expected return than the firm’s 12 percent cost of capital? Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project...

  • (5 points) An all equity firm is considering the following projects: 2. Project Beta 0.8 1.2...

    (5 points) An all equity firm is considering the following projects: 2. Project Beta 0.8 1.2 IRR 10% 12% The risk-free rate is 3% and the expected market rate premium is 8%. The firm has a beta equal to 1 (1 point) What is the firm's cost of capital? a. b. (2 points) Which projects should be accepted? Explain (2 point) Which projects will be incorrectly accepted or rejected if the firm's overall cost of capital were used to as...

  • An all-equity firm is considering the following projects: Project Beta IRR W 0.80 9.4% X .95...

    An all-equity firm is considering the following projects: Project Beta IRR W 0.80 9.4% X .95 10.9% Y 1.15 13.0% Z 1.45 14.2% The firm’s overall cost of capital is 11%. Assume T -bill rate is 3.5 percent, and the expected return on the market is 11 percent. a. Which projects should be accepted? And Why?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT