The Charming City Construction Company is considering five projects. The projects, the number of supervisors and the number of workers required for each project, and the expected NPV for each project are given below.
Project
1 2 3 4 5
__________________________________________________________
Supervisors Required 4 3 5 3 4
Workers Required 15 24 35 20 24
NPV (in thousands of dollars) 200 280 320 220 280
The objective is to maximize the company's total expected NPV subject to the following constraints:
- Use no more than 15 supervisors
- Use no more than 80 workers
- At least three projects are to be done.
(a) Formulate a capital budgeting problem by defining the decision variables, the objective function, and all the constraints. Briefly describe what the objective function and each constraint represent.
(b) The optimal solution for the above problem is given below.
Variable values are X1 = 0, X2 = 1, X3 = 1, X4 = 1, X5 = 0
Objective function value is 820
Interpret the optimal solution to make a recommendation to the company.
a. The capital budgeting problem can be formulated by taking the decision variables as X1, X2, X3, X4, X5 where each variable represents if the project will be chosen or not.
The constraints are as follows,
Objective Function = Z ( max NPV) = 200X1 +280X2 + 320X3+220 X4 + 280X5
Constraints :-
0<=X1, X2, X3, X4, X5<=1 ( This means that if a variable is 1 then that project is chosen if it is 0 it is excluded)
S = 4X1 +3X2 + 5X3+3 X4 + 4X5 <= 15 -- ( No. of supervisors constraint)
W = 15X1 +24 X2 + 35 X3+ 20 X4 + 24 X5 <= 80 -- ( No. of workers constraint)
Also , X1 +X2 + X3+ X4 + X5 >= 3 -- ( Min no. of project constraints)
b.
Given:-
The optimal solution for the above problem is X1 = 0, X2 = 1, X3 = 1, X4 = 1, X5 = 0 , This means that the project 2,3 and 4 are chosen.
So, for those three choices the value of the objective function will be :-
Z ( NPV) = 200X1 +280X2 + 320X3+220 X4 + 280X5
= 200 * 0 +280*1 + 320 * 1+220 * 1 + 280* 0
= 280 + 320 +220
= 820
The Charming City Construction Company is considering five projects. The projects, the number of supervisors and...
5. Charming City Foods manufactures a snack bar by blending two ingredients: a nut mix and a granola mix. Information about the two ingredients (per ounce) is shown below Ingredient Nut Mi:x Granola Mix Cost In Dollars 0.90 0.50 Fat Grams 24 4 Calories 650 60 Protein Grams The company needs to develop a linear programming model whose solution would tell them how many ounces of each mix to put into the snack bar. The blend should contain no more...
Question 5 An investor wants to invest $5 million in different projects. After preliminary assessment, he is focusing on 8 promising projects. Each project is characterized by a budget and an associated net present value (NPV). These budgets and NPVs are displayed in the following table. Project Budget (in $100,000 NPV (in $100,000) 31 22 17 31 28 17 15 33 16 9 10 13 15 8 622 The investor wants to find a portfolio of projects that will maximize...
[Business Analytics/Operational Management] (Excel) Capital budgeting: A firm has 6 projects that it would like to undertake over the next 5 years but because of budget limitations not all can be selected. The total budget that the firm has considered to invest in the projects is $12,400,000. The following table displays the expected revenue (NPV) of each project after 5 years and the required yearly capital for each investment. Table 1: Investment Details Capital (in $000) required per year Investment/...
The Valley Research Inc. is contemplating a research and development (R&D) program encompassing five potential research projects named 1, 2, 3, 4, and 5. All the projects are expected to go on simultaneously. The company is constrained from embarking on all projects by the number of scientists it has and the budget available for R&D projects. The company has 23 scientists and $300,000 (three hundred thousand dollars) budgeted for R&D projects. Furthermore, since projects 2 and 5 require the involvement...
1. A company manufactures two products: large fans and medium fans. Each large fan requires 3 hours of wiring and 2 hours of drilling. Each medium fan requires 2 hours of wiring and 1 hour of drilling. There are 480 hours of wiring time available and 280 hours of drilling time available. Each large fan yields a profit of $25. Each medium fan yields a profit of $18. The company wants to manufacture at least 20 large fans. The objective...
The Valley Research Inc. is contemplating a research and development (R&D) program encompassing five potential research projects named 1, 2, 3, 4, and 5. All the projects are expected to go on simultaneously. The company is constrained from embarking on all projects by the number of scientists it has and the budget available for R&D projects. The company has 23 scientists and $300,000 (three hundred thousand dollars) budgeted for R&D projects. Furthermore, since projects 2 and 5 require the involvement...
3a, b and c please help 3. (30pt) A company considers the following 4 projects: Project Capital Investment in year 0$10,000$6,000 A В С D $4,000 $8,000 -$2,000 $5,000 $1,600 $1,300$1,500 $4,000 $5,000 $8,000 $1,200 Net Cash Flow in 1 year Net Cash Flow in year 2 $4,000 $8,000 $10,200 Net Cash Flow in year The MARR is 10% per year. The company has a $20,000 budget for the capital investment in year 0. a) (10pt) Find NPV8 of 4...
40. You are given a group of possible investment projects for your company’s capital. For each project, you are given the NPV the project would add to the firm, as well as the cash outflow required by each project during each year. Determine the investments that maximize the firm’s NPV. The firm has $25 million available during each of the next five years. All numbers are in millions of dollars. I intend to leave a thumbs up no matter what!...
Use the information below answer questions 1-3: • Management is considering five different projects (Alpha, Beta, Delta, Gamma, Theta) • There are no cash flows to consider besides the initial cash outlay and the payoff • All payoffs are expected in two years Project Alpha Beta Delta Gamma Theta Probabilty [Failure] 80% 60% 50% 40% 20% Payoff [Success] $ 320 $ 280 $ 400 $ 150 $ 150 Payoff [Failure] $ 280$ $ 200 $ $ 190 $ $ 140...
Formulate the followings into optimization problems. While you could use the integer constraints, the linear structure should be maintained. However, you shouldn’t use the integer constraints if you can formulate the problem without them. Describe the decision variables, objective function and constraints carefully. You don’t need to solve this problem. (b) (10 pts) Three workers are available to perform two jobs. The timei takes each worker to perform each job is given in the following table. Formulate the problem to...