DIRECT LABOR VARIANCE ANALYSIS ON PRODUCTION OF SHIRTS:

Information
Standard Actual
Direct material price per yard $5.00 $5.20
Direct material quantity (yards) 1,000 990
Direct labor rate per hour $10.00 $9.75
Direct labor hours 1,750 1,700
Units produced 2000 1990

Calculate the Direct Labor Time Variance (select from each drop down box):

Direct Labor TIME VARIANCE Calculation
(Fav)/Unfav
Actual DL hours Choose...9901,7002,0001,9901,0001,750
- Standard DL hours -Choose...9901,7002,0001,9901,0001,750
DL hours difference 10(50)50(10) Choose...UnfavorableFavorable
x Standard DL rate per hour x$Choose...5.2010.009.755.00
   ——
Total Direct Labor TIME VARIANCE $Choose...500198(425)(500)425(200)200(198) Choose...UnfavorableFavorable
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Fav / Unfav
Standard DL hours 1,750
- Actual DL hours 1,700
DL hours difference 50 Favourable
× Standard DL rate per hour 10
Total Direct Labor Time Variance 500 Favourable
Add a comment
Know the answer?
Add Answer to:
Question text DIRECT LABOR VARIANCE ANALYSIS ON PRODUCTION OF SHIRTS: Information Standard Actual Direct material price...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • REQUIRED: Determine the missing values DIRECT-LABOR PRICE AND QUANTITY VARIANCES ACTUAL LABOR COST Actual Actual Hours...

    REQUIRED: Determine the missing values DIRECT-LABOR PRICE AND QUANTITY VARIANCES ACTUAL LABOR COST Actual Actual Hours Price $8.30 Actual Hours X Standard Price $6.90 STANDARD LABOR COST Standard Standard Hours Price 1,500X $6.90 Direct-labor rate variance $197 Unfav. Direct-labor efficiency variance Direct-labor variance DIRECT-MATERIAL PRICE AND QUANTITY VARIANCES ACTUAL MATERIAL COST STANDARD MATERIAL COST Actual Actual Actual Standard Standard Standard Quantity X Price Quantity Price Quantity X Price 420 420 $345.00 435 x $345.00 $2,950 Fav. Direct-material price variance $8.125...

  • Find the Total Spending Variance, Direct Material variance, Direct Labor Variances, and Variable O/H Variance Analysis...

    Find the Total Spending Variance, Direct Material variance, Direct Labor Variances, and Variable O/H Variance Analysis Insert a formula into each cell containing a ?. Chatham Company produces a beach towel and incurs the following variable manufacturing costs: Std Qty Std Price/Rate Direct material (cloth) Direct labor Variable O/H (based on direct labor hours) 3 yds 0.75 hours 0.75 hours $ $ $ 1.80 per yd 12.00 per hour 4.00 per hour Standard Cost per Unit: Std Cost per towel...

  • 28. A weekly factory production report shows the following data: Product units produced Standard Direct Labor...

    28. A weekly factory production report shows the following data: Product units produced Standard Direct Labor (DL) time for 18,000 units 20,000 hours Standard DL rate per hour Actual DL time used in production: 20,800 hours Actual DL rate per hour Standard Direct Materials (DM) cost per unit Standard Factory Overhead (FO) rate: 40% of DL cost 18.00 Instructions (a, b, c): Calculate the following variances: please indicate (unfavorable) with your answer: 521.00 520.00 a) DL rate variance averable) er...

  • Given the following information regarding direct labor: Actual direct labor hours = 24,000 hours; Actual rate...

    Given the following information regarding direct labor: Actual direct labor hours = 24,000 hours; Actual rate per direct labor hour = $14 per hour; Standard direct labor hours per unit = 3 hours per unit; Standard rate per direct labor hour = $11 per hour; Units produced = 9,000 units : -What is the direct labor rate variance? (AR - SR) x AH ? -What is the direct labor efficiency variance? (AH - SH allowed) x SR ?

  • A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual...

    A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...

  • The direct material price variance during June is ___?

    Heavy Products, Inc. developed standard costs for direct material and direct labor. In 2017, AII estimated the following standard costs for one of their major products, the 10−gallon plastic container.Budgeted quantity Budgeted priceDirect materials0.7 pounds$50 per poundDirect labor0.05 hours$25 per hourDuring June, Heavy Products produced and sold 23,000 containers using 20,000 pounds of direct materials at an average cost per pound of $53 and 16,100 direct manufacturing labor-hours at an average wage of $25.50 per hour.The direct material price variance...

  • Given the following information for The Pelican Inn, what is the direct labor time variance? Actual...

    Given the following information for The Pelican Inn, what is the direct labor time variance? Actual housekeeping staff hours worked 760 Standard staff hours for rooms cleaned 800 Standard staff pay rate per hour $12.50 Actual staff pay rate per hour $13.00 a.$500 unfavorable b.$400 unfavorable c.$(20) favorable d.$(500) favorable

  • Black and Decker Corporation has the following information is for their standard and actual costs: Standard...

    Black and Decker Corporation has the following information is for their standard and actual costs: Standard Costs: Budgeted units of production - 9,000 (100% of capacity) Standard material per unit - 12 lbs. Standard material cost - $14.00 per pound Standard labor hours per unit - 12 Standard labor rate - $29.00 per hour Standard variable overhead rate - $7.50 per labor hour Budgeted fixed overhead - $729,000 Fixed overhead rate is based on budgeted labor hours at 100% capacity...

  • Direct Materials and Direct Labor Variance Analysis Shasta Fixture Company manufactures faucets in a small manufacturing...

    Direct Materials and Direct Labor Variance Analysis Shasta Fixture Company manufactures faucets in a small manufacturing facility. The faucets are made from brass. Manufacturing has 30 employees. Each employee presently provides 35 hours of labor per week. Information about a production week is as follows: Standard wage per hour $13.20 Standard labor time per unit 20 min. Standard number of lbs. of brass 1.3 lbs. Standard price per Ib. of brass $12.25 Actual price per lb. of brass $12.50 12,051...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $140 per ton Standard labor rate $14.50 per hour Standard materials price $142 per ton Quantities Actual hours incurred and used 3,800 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 3,850 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT