One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with each alternative are available. Use B/C analysis at a discount rate of 7% per year over a 20-year study period to determine which alternative should be selected. For analysis purposes only, assume the flood damage would be prevented in years 3, 13, and 18 of the study period.
Retention Pond | Channel | |
Initial Cost, $ | 960,000 | 2,900,000 |
Annual Maintenance , $/Year | 92,000 | 30,000 |
Reduced Flood Damage, $ | 200,000 | 550,000 |
The ΔB/C ratio is .
The alternative that should be selected is the
One of two alternatives will be selected to reduce flood damage in a rural community in...
One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with each alternative are available. Use B/C analysis at a discount rate of 7% per year over a 20 year study period to determine which alternative should be selected. For analysis purposes only, assume that the benefits of reduced flood damage are available in years 3, 8, and 18 of the study period. 33 Retention Pond Channel Initial Cost,...
Problem 09.029 Two Alternative Comparison One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with each alternative are available. Use B/C analysis at a discount rate of 9% per year over a 20-year study period to determine which alternative should be selected. For analysis purposes only, assume that the benefits of reduced flood damage are available in years 4, 8, and 18 of the study period. Retention Pond...
htrmi Help Save &Exit Submt 3 One of two alternatives will be each alternative are avalilable. Use B/C analysis at a discount rate of alternative should be selected. For analysis purposes only, assume that the benefts of reduced flood 12, and 18 of the study period to reduce flood n a rural community in central Arizona. The estimates associated with of reduced flood damage are available in years7 Pond 10 Initial Cost,$ 92.000 550000 The AB/C ratio ism The alternative...
The two ME alternatives shown are under consideration for facility improvements in a company in Abu Dhabi. Determine which one should be selected based on a B/C analysis. Assume an interest rate of 10% per year and a 5-year study period. Alternative X Alternative Y First costs, AED 40,000 90,000 Annual M&O costs, AED per year 50,000 20,000 Benefits, AED per year 120,000 150,000 Disbenefits, AED per year 30,000 10,000 Match the closest correct answers for the below questions: - ...
The cash flow for two alternatives is shown in the table below. a) Determine which alternative should be selected based on present worth comparison (use i=10%). b) If your analysis period (study period) is just 3 years, what should be the salvage value of alternative A2 at the end of year 3 to make the two alternatives economically indifferent? A1 Year 0 -900 -400 A2 -1800 -300 -300 1 2 -400 3 -400+200 -300 4 5 6 -300 -300 -300...
An area on the Colorado River is subject to periodic flood damage that occurs, on the average, every two years (i.e., probability of flooding in any year is 0.5) and results in a $2,200,000 loss. It has been proposed that the river channel be improved by straightening and deepening it at a cost of$2,400,000, to reduce the annual probability of flooding to 0.364 during a period of 18 years before it would have to be deepened again. This procedure would...
Question 13 15 points Save Answer The two ME alternatives shown are under consideration for facility improvements in a company in Abu Dhabi. Determine which one should be selected based on a B/C analysis. Assume an interest rate of 10% per year and a 5-year study period. Alternative X Alternative Y First costs, AED 40,000 90,000 20,000 Annual M&O costs, AED per year 50,000 150,000 Benefits, AED per year 120,000 Disbenefits, AED per year 30,000 10,000 Match the closest correct...
Question 13 15 points Save Answer The two ME alternatives shown are under consideration for facility improvements in a company in Abu Dhabi. Determine which one should be selected based on a B/C analysis. Assume an interest rate of 10% per year and a 5 year study period Alternative X Alternative Y 90,000 First costs, AED 40.000 50,000 20,000 Annual M&O costs, AED per year Benefits, AED per year 120,000 150,000 Disbenefits, AED per year 30,000 10,000 Match the closest...
Question 13 15 points Save Answer The two ME alternatives shown are under consideration for facility improvements in a company in Abu Dhabi. Determine which one should be selected based on a B/C analysis. Assume an interest rate of 10% per year and a 5 year study period Alternative X Alternative Y 90,000 First costs, AED 40.000 50,000 20,000 Annual M&O costs, AED per year Benefits, AED per year 120,000 150,000 Disbenefits, AED per year 30,000 10,000 Match the closest...
Question 13 15 points Save An The two ME alternatives shown are under consideration for facility improvements in a company in Abu Dhabl. Determine which one should be selected based on a B/c analysis. Assume an interest rate of 10% per year and a 5-year study period. Altereative X Alternative Y 90,000 40,000 First costs, AED 50,000 20,000 Annual M&0 costs, AED per year 150,000 Benefits, AED per year Disbenefits, AED per year 10,000 Match the closest comect answers for...