Question

Consider a process with a unit cost of $50 for the first unit and a learning...

Consider a process with a unit cost of $50 for the first unit and a learning rate of 0.9. What will be the unit cost for the 64th unit?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The cumulative average for the learning rate is given by the following formula

Y = ax^b

Y = cumulative average time/cost

a = time/cost for the first unit

x = the number of units

b = log LR/log 2

LR = learning rate in decimals

At 0.9 learning rate the value of b = log 0.9/log 2 = -0.152

This means the cumulative cost to produce 63rd unit will be

Y1 = 50*63^(-0.152) = 26.63 s

Total cost = 63*26.63 = 1677.69

The cumulative cost to produce 64th unit will be

Y2 = 50*64^(-0.152) = 26.57

Total cost = 64*26.57 = 1700.48

The cost of producing the 64th unit will be 1700.48 – 1677.69 = 22.79

Add a comment
Answer #2

To determine the unit cost for the 64th unit using a learning rate of 0.9, we can apply the learning curve formula:

Unit Cost = Initial Unit Cost * (Number of Units)^Learning Rate

Given: Initial Unit Cost = $50 Number of Units = 64 Learning Rate = 0.9

Unit Cost for the 64th unit = $50 * (64^0.9)

Using a calculator or computational tool, we can evaluate this expression:

Unit Cost for the 64th unit = $50 * (64^0.9) ≈ $50 * 19.641 ≈ $982.05

Therefore, the unit cost for the 64th unit, with a learning rate of 0.9, is approximately $982.05.


answered by: Mayre Yıldırım
Add a comment
Know the answer?
Add Answer to:
Consider a process with a unit cost of $50 for the first unit and a learning...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 5. Consider a process restringing tennis rackets. The process starts with a unit cost of $10...

    5. Consider a process restringing tennis rackets. The process starts with a unit cost of $10 for the first unit—that is, c(1) = 10—and a learning rate of LR = 0.9. What will be the unit cost for the 35th unit?

  • Assume that a certain process has an 95% learning curve effect and the first unit took...

    Assume that a certain process has an 95% learning curve effect and the first unit took 4000hrs to produce. Required: Compute the number of hours required to produce the first 34 units                                                                                                                                                               (3 Marks) Compute the number of hours required to produce 34th unit.                                                                                                                                                            (2 Marks) iii) Assume that the wage rate is Kshs.100 per hour, compute the Labor cost of producing the last 16 units                              

  • b) Assume that a certain process has an 95% learning curve effect and the first unit...

    b) Assume that a certain process has an 95% learning curve effect and the first unit took 4000hrs to produce. Required: i) Compute the number of hours required to produce the first 34 units                                                   (3 Marks) ii) Compute the number of hours required to produce 34th unit.                                                (2 Marks) iii) Assume that the wage rate is Kshs.100 per hour, compute the Labor cost of producing the last 16 units

  • The first unit of a product took 80 days for production. The learning rate for the...

    The first unit of a product took 80 days for production. The learning rate for the production process is 75%. How long will it take to make the 17th unit? (You can use Table E.3 in Module E (Learning Curves) of the textbook.) from 22 to 23 days from 24 to 25 days from 21 to 22 days from 25 to 26 days from 23 to 24 days The first unit of a product took 80 days for production. The...

  • The first unit of a product took 500 hours to build, and the learning rate for...

    The first unit of a product took 500 hours to build, and the learning rate for the production process is 78%. How long will it take to make the 256th unit? (Use at least five decimals in the exponent if you use the logarithmic approaches.) from 75 to 85 hours from 85 to 95 hours from 65 to 75 hours from 95 to 105 hours from 55 to 65 hours

  • Explain the learning curve of an employee must be taken into account in any unit cost...

    Explain the learning curve of an employee must be taken into account in any unit cost estimation process.

  • (1) Let us suppose it costs $70 to produce the 80th unit, assuming a learning rate...

    (1) Let us suppose it costs $70 to produce the 80th unit, assuming a learning rate of 95%, determine the cost of the 160th unit. (2) If the 4th unit took 24 hours to produce, and the 20th unit took 19 hours to produce, what would the learning rate be? Note: Express your answer in decimal places, i.e., if your answer is 40.56%, enter in 0.4056. (3) Let us suppose it costs $500 to produce the 120th unit, assuming a...

  • If the learning rate is 0.90, and the first 5 units had an average cost of...

    If the learning rate is 0.90, and the first 5 units had an average cost of $40, what is the cumulative average cost for the first 100 units? Enter your answer to two decimal places, with no dollar sign.

  • Learning Curve percentage 0.80 Exponent for an 80% learning curve -0.321900 Direct Material Cost, per unit...

    Learning Curve percentage 0.80 Exponent for an 80% learning curve -0.321900 Direct Material Cost, per unit $74,400.00 DMLH, for first unit 2,790.00 DML$, per hour $23.25 VMOH, per DMLH $13.95 (6) Calculate the total variable cost of producing 2, 4, 8, and 16 units, using the Cumulative average-time model. (7) Calculate the total variable cost of producing 2, 3, 4, and 5 units, using the Incremental unit-time model.

  • Find the time per unit (in minutes) required to produce the first unit, if the slope parameter of the learning rate is 8...

    Find the time per unit (in minutes) required to produce the first unit, if the slope parameter of the learning rate is 86 % and the time to complete unit 65 takes 9 minutes. (Enter your answer as a number without the units.)

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT