b) Assume that a certain process has an 95% learning curve effect and the first unit took 4000hrs to produce.
Required:
i) Compute the number of hours required to produce the first 34 units                                                   (3 Marks)
ii) Compute the number of hours required to produce 34th unit.                                                (2 Marks)
iii) Assume that the wage rate is Kshs.100 per hour, compute the Labor cost of producing the last 16 units

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Time taken to produce est unit (a) = 4000 houry learning rate = 95%. . Learning cofficient (6) = logo = – 0.074 logo.05 (1) hin hours required to produce 34th unit step: hours reanived 33 unit 9. Ob -0.074 4000x33 y = logy: 1094000 -0.074 (tog33) - 3laste producing 16 unik. of (1) Labour cost last 16unit to produce Total time reauired reanived ime Total time - Total time f

Add a comment
Know the answer?
Add Answer to:
b) Assume that a certain process has an 95% learning curve effect and the first unit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Assume that a certain process has an 95% learning curve effect and the first unit took...

    Assume that a certain process has an 95% learning curve effect and the first unit took 4000hrs to produce. Required: Compute the number of hours required to produce the first 34 units                                                                                                                                                               (3 Marks) Compute the number of hours required to produce 34th unit.                                                                                                                                                            (2 Marks) iii) Assume that the wage rate is Kshs.100 per hour, compute the Labor cost of producing the last 16 units                              

  • UNIT CODE: BAF2202 UNIT TITLE: MANAGEMENT ACCOUNTING I                            Assume that a certain process has an

    UNIT CODE: BAF2202 UNIT TITLE: MANAGEMENT ACCOUNTING I                            Assume that a certain process has an 95% learning curve effect and the first unit took 4000hrs to produce. Required: Compute the number of hours required to produce the first 34 units Compute the number of hours required to produce 34th unit. iii) Assume that the wage rate is Kshs.100 per hour, compute the Labor cost of producing the last 16 units Differentiate between management accounting and financial accounting Highlight the assumptions...

  • UNIT CODE: BAF2202          UNIT TITLE: MANAGEMENT ACCOUNTING I                        &nb

    UNIT CODE: BAF2202          UNIT TITLE: MANAGEMENT ACCOUNTING I                                                                                            Assume that a certain process has an 95% learning curve effect and the first unit took 4000hrs to produce. Required: Compute the number of hours required to produce the first 34 units Compute the number of hours required to produce 34th unit. iii) Assume that the wage rate is Kshs.100 per hour, compute the Labor cost of producing the last 16 units Differentiate between management accounting and financial accounting Highlight the...

  • a) Outline the objectives of management accounting (3 Marks) b) Assume that a certain process has...

    a) Outline the objectives of management accounting (3 Marks) b) Assume that a certain process has an 95% learning curve effect and the first unit took 4000hrs to produce. Required: i) Compute the number of hours required to produce the first 34 units                                                   (3 Marks) ii) Compute the number of hours required to produce 34th unit.                                                (2 Marks) iii) Assume that the wage rate is Kshs.100 per hour, compute the Labor cost of producing the last 16 units...

  • A job with a 95% learning curve required 19 hours for the second unit. The first...

    A job with a 95% learning curve required 19 hours for the second unit. The first unit should require approximately how many hours?

  • Harper Ltd is a manufacturer of rowing boats. It has designed a new boat called the...

    Harper Ltd is a manufacturer of rowing boats. It has designed a new boat called the Seafarer and expects to produce the Seafarer in a continuous operation over an 18 month period During this period, it is expected that a total of sixteen Seafarer's will be produced and sold. The production of the Seafarer is a labour intensive operation and units are produced one after another The costs of producing the first Seafarer are as follows Skilled Labour 1,000 hours...

  • 10 Points What is the labor-hour estimate for a 95% learning curve unit #16, if the...

    10 Points What is the labor-hour estimate for a 95% learning curve unit #16, if the first unit is 100 man- hours? a. 95 labor-hours b. 80.45 labor-hours 90.25 labor-hours d. None of the above c.

  • 3) Assume that the first unit of production required 3 hours time for assembly. The learning...

    3) Assume that the first unit of production required 3 hours time for assembly. The learning curve rate is 75%. Find the time needed to assemble the first 6 units?

  • Learning Curve percentage 0.80 Exponent for an 80% learning curve -0.321900 Direct Material Cost, per unit...

    Learning Curve percentage 0.80 Exponent for an 80% learning curve -0.321900 Direct Material Cost, per unit $74,400.00 DMLH, for first unit 2,790.00 DML$, per hour $23.25 VMOH, per DMLH $13.95 (6) Calculate the total variable cost of producing 2, 4, 8, and 16 units, using the Cumulative average-time model. (7) Calculate the total variable cost of producing 2, 3, 4, and 5 units, using the Incremental unit-time model.

  • LEARNING CURVE TABLE 1.0000 0.8000 1.0000 0.8500 0.7021 0.6400 0.7729 0.5957 0.5618 0.5345 0.5120 0.7225 0.6856...

    LEARNING CURVE TABLE 1.0000 0.8000 1.0000 0.8500 0.7021 0.6400 0.7729 0.5957 0.5618 0.5345 0.5120 0.7225 0.6856 0.6569 0.6336 0.6141 1.0000 0.9000 0.8462 0.8100 0.7830 0.7616 0.7440 0.7290 1.0000 0.9500 0.9219 0.9025 0.8877 0.8758 0.8659 0.8574 Question 1 (13 marks) ABC produces equipment. It has just completed the manufacture of its first newly designed AB-XY Data is as follows: Direct Materials $ 5,000 Direct labor-first unit 180 hrs Learning curve - Incremental 90% Direct labor cost $45/DM labour hour Variable Manufacuring...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT