Question

At the beginning of the period, the Cutting Department budgeted direct labor of $39,330 and supervisor...

At the beginning of the period, the Cutting Department budgeted direct labor of $39,330 and supervisor salaries of $49,850 for 4,370 hours of production. The department actually completed 4,800 hours of production. Determine the budget for the department assuming that it uses flexible budgeting.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Variable costs:
Direct labour (4,800 hours *$9) $43,200
fixed cost:
supervisor salaries 49,850
total departmental cost $93,050

direct labour rate = $39,330 supervisor salaries / 4370 hours of production

=>$9.

Add a comment
Know the answer?
Add Answer to:
At the beginning of the period, the Cutting Department budgeted direct labor of $39,330 and supervisor...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT