On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: |
January 1, 2016 | $320,000 |
September 1, 2016 | $480,000 |
December 31, 2016 | $480,000 |
March 31, 2017 | $480,000 |
September 30, 2017 | $320,000 |
Dreamworld had $6,000,000 in 14% bonds outstanding through both years. |
Dreamworld's capitalized interest in 2016 was: |
Multiple Choice
$44,800.
$67,200.
$78,400.
$89,600.
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $300,000 September 1, 2016 $450,000 December 31, 2016 $450,000 March 31, 2017 $450,000 September 30, 2017 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2016 was: a. $300,000 b. $450,000 c. $525,000 d. $600,000
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $316,000 September 1, 2016 $462,000 December 31, 2016 $462,000 March 31, 2017 $462,000 September 30, 2017 $316,000 Dreamworld had $5,400,000 in 14% bonds outstanding through both years. Dreamworld's capitalized interest in 2016 was: 2) -------------------------------------------------------------------------------------------- Data related to the inventories of Alpine Ski...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 311,000 September 1, 2018 $ 453,000 December 31, 2018 $ 453,000 March 31, 2019 $ 453,000 September 30, 2019 $ 311,000 Dreamworld had $5,100,000 in 10% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2018 was: Multiple Choice $622,000. $539,750. $462,000. $311,000.
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 316,000 September 1, 2018 $ 462,000 December 31, 2018 $ 462,000 March 31, 2019 $ 462,000 September 30, 2019 $ 316,000 Dreamworld had $5,400,000 in 14% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
Question 10 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2018 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2018 was: $300.000 $450,000 $525,000. $600,000
5 points Save Ang On January 1, 2021, Dreamworld Co began construction of a new warehouse. The building was finished and ready for use on September 30, 2022 Expenditures on the project were as follows January 1, 2021 $ 308 000 September 1, 2021 $ 456.000 December 31, 2021 $ 456 000 March 31, 2022 $ 456.000 September 30, 2022 $ 308,000 Dreamworld had 55 200,000 in 12% bonds outstanding through both years What was the final cost of Dreamworld's...
Question 11 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2018 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was: $1,950,000...
Question 9 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2013 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was: $1,950,000....
8. Horton Stores exchanged land and cash of $5,000 for similar land. The book value and the fair value of the land were $90,000 and $100,000, respectively. Assuming that the exchange has commercial substance, record the transaction: 9. On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 September 1, 2018 December 31, 2018 March 31,...
On January 2, 2017, Sunland Company began construction of a new
citrus processing plant. The automated plant was finished and ready
for use on September 30, 2018. Expenditures for the construction
were as follows:
January 2, 2017
$ 597000
September 1, 2017
1812000
December 31, 2017
1812000
March 31, 2018
1812000
September 30, 2018
1215000
Sunland Company borrowed $3370000 on a construction loan at 10%
interest on January 2, 2017. This loan was outstanding during the
construction period. The company...