Question

Question 11 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and

Question 13 (1 point) The cost of constructing a new parking lot at the companys office building would be recorded as: Land.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1)correct option is "B"- 1554000

For 2018

Date Amount * Period of outstanding = Accumulated expenditure for 2018
1/1/2018 300000 12/12 300000
1/9/2018 450000 4/12    [1Sep -31Dec] 150000
31/12/2018 450000 0/12 0
Total 1200000 450000
Capitalized interest for 2018 450000*12%= 54000
Total balance at end 1254000

For 2019::Project is completed in September (so total 9months)

Date Amount * Period of outstanding = Accumulated expenditure for 2018
1/1/2019 1254000 9/9 1254000
31/3/2019 450000 6/9 [1Apr -30Sep ] 300000
30/9/2019 300000 0/9 0
Total 2004000 1554000

12)

Correct option is "c"

As per the definition ,Interest should be capitalized only in respect of qualifying asset which means asset constructed for sale or lease or for company's own use is to be capitalized .

Interest is not to be capitalized on inventory or other routinely produced asset

13)Correct option is "B"-Land improvement

cost of construction of a new parking lot on a land on which office building is already constructed is an improvement to land .

14)Correct option is "A"

Average accumulated expenditure = Average Amount of debt outstanding for a period * interest rate

Add a comment
Know the answer?
Add Answer to:
Question 11 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 9 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse....

    Question 9 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2013 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was: $1,950,000....

  • Question 10 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse....

    Question 10 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2018 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2018 was: $300.000 $450,000 $525,000. $600,000

  • On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...

    On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 316,000 September 1, 2018 $ 462,000 December 31, 2018 $ 462,000 March 31, 2019 $ 462,000 September 30, 2019 $ 316,000 Dreamworld had $5,400,000 in 14% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:

  • On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...

    On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $300,000 September 1, 2016 $450,000 December 31, 2016 $450,000 March 31, 2017 $450,000 September 30, 2017 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2016 was: a. $300,000 b. $450,000 c. $525,000 d. $600,000

  • On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...

    On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 311,000 September 1, 2018 $ 453,000 December 31, 2018 $ 453,000 March 31, 2019 $ 453,000 September 30, 2019 $ 311,000 Dreamworld had $5,100,000 in 10% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2018 was: Multiple Choice $622,000. $539,750. $462,000. $311,000.

  • On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...

    On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows:      January 1, 2016 $320,000   September 1, 2016 $480,000   December 31, 2016 $480,000   March 31, 2017 $480,000   September 30, 2017 $320,000    Dreamworld had $6,000,000 in 14% bonds outstanding through both years.    Dreamworld's capitalized interest in 2016 was:    Multiple Choice $44,800. $67,200. $78,400. $89,600.

  • On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...

    On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows:      January 1, 2016 $316,000   September 1, 2016 $462,000   December 31, 2016 $462,000   March 31, 2017 $462,000   September 30, 2017 $316,000    Dreamworld had $5,400,000 in 14% bonds outstanding through both years.    Dreamworld's capitalized interest in 2016 was: 2) -------------------------------------------------------------------------------------------- Data related to the inventories of Alpine Ski...

  • On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $10,100,000 and an effective interest rate of 9%. Construction expenditures incurred during 2018 were as follows: January 1 March 1 July 31 September 30 December 31 $ 510,000 606, 000 486,000 610,000 310,000 Required: Calculate the amount of...

  • Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1. 2018. This loan was outstanding throughout the construction period. The...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $9,000, 800, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 48e, eae 720,899 720.99 660,800 120,00€ The company's fiscal year-end is December...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT