Question

On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...

On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019.

Expenditures on the project were as follows: January 1, 2018 $ 316,000 September 1, 2018 $ 462,000 December 31, 2018 $ 462,000 March 31, 2019 $ 462,000 September 30, 2019 $ 316,000

Dreamworld had $5,400,000 in 14% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Date Amount Period Weighted average expenditure
January 1,2018          3,16,000 12/12                                   3,16,000
September 1,2018          4,62,000 4/12                                   1,54,000
December 31,2018          4,62,000 0                                              -  
       12,40,000                                   4,70,000
Average accumulated expenditures for 2018 was $470,000
Interest Exp for 2018 = $470,000 *14% = $65,800
Date Amount Period Weighted average expenditure
January 1,2019(12,40,000+65,800)        13,05,800 9/ 9                                 13,05,800
mar31,2019          4,62,000 6/9                                   6,93,000
Sept 30. 2019          3,16,000 0                                              -  
       20,83,800                                 19,98,800
Average accumulated expenditures for 2019 was $19,98,800
Add a comment
Know the answer?
Add Answer to:
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...

    On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 311,000 September 1, 2018 $ 453,000 December 31, 2018 $ 453,000 March 31, 2019 $ 453,000 September 30, 2019 $ 311,000 Dreamworld had $5,100,000 in 10% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2018 was: Multiple Choice $622,000. $539,750. $462,000. $311,000.

  • On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...

    On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows:      January 1, 2016 $316,000   September 1, 2016 $462,000   December 31, 2016 $462,000   March 31, 2017 $462,000   September 30, 2017 $316,000    Dreamworld had $5,400,000 in 14% bonds outstanding through both years.    Dreamworld's capitalized interest in 2016 was: 2) -------------------------------------------------------------------------------------------- Data related to the inventories of Alpine Ski...

  • Question 10 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse....

    Question 10 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2018 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2018 was: $300.000 $450,000 $525,000. $600,000

  • On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...

    On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $300,000 September 1, 2016 $450,000 December 31, 2016 $450,000 March 31, 2017 $450,000 September 30, 2017 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's average accumulated expenditures for 2016 was: a. $300,000 b. $450,000 c. $525,000 d. $600,000

  • On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...

    On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows:      January 1, 2016 $320,000   September 1, 2016 $480,000   December 31, 2016 $480,000   March 31, 2017 $480,000   September 30, 2017 $320,000    Dreamworld had $6,000,000 in 14% bonds outstanding through both years.    Dreamworld's capitalized interest in 2016 was:    Multiple Choice $44,800. $67,200. $78,400. $89,600.

  • Question 11 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse....

    Question 11 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2018 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was: $1,950,000...

  • 5 points Save Ang On January 1, 2021, Dreamworld Co began construction of a new warehouse....

    5 points Save Ang On January 1, 2021, Dreamworld Co began construction of a new warehouse. The building was finished and ready for use on September 30, 2022 Expenditures on the project were as follows January 1, 2021 $ 308 000 September 1, 2021 $ 456.000 December 31, 2021 $ 456 000 March 31, 2022 $ 456.000 September 30, 2022 $ 308,000 Dreamworld had 55 200,000 in 12% bonds outstanding through both years What was the final cost of Dreamworld's...

  • Question 9 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse....

    Question 9 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2013 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was: $1,950,000....

  • Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 15 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1. 2018. This loan was outstanding throughout the construction period. The...

  • Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle...

    Question 8 (1 point) On January 1, 2018, Kendall Inc, began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $200,000 September 1, 2018 $300,000 December 31, 2018 $300,000 March 31, 2019 $300,000 September 30, 2019 $200,000 Kendall borrowed $750,000 on a construction loan at 12% interest on January 1 2018. This loan was outstanding throughout the construction period. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT