The IT department's cost data is as follows:

Estimated Costs

Fixed Costs $ 500,000

Variable, ($300 per hour) $600,000

Total $1,100,000

IT Departmental Usage:   

Hours Department A Department B

Budgeted 1,100 900

Actual 1,300 1,200

The fixed costs are allocated based on relative budgeted hours with variable costs applied based on actual hours. Department A will be allocated total overhead of:

A. $715,000

B. $390,000

C. $605,000

D. $665,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1

If it is helpful, please rate the answer and if any doubt arises let me know

Correct option is: D. $6,65,000
Workings:
Hours Department A Department B Total
Budgeted                   1,100                        900          2,000
Actual                   1,300                    1,200          2,500
Variable cost per hour = $                   300
Fixed cost per hour = $500000 / 2000 hours
= $                   250
Overhead Cost Department A Department B
(Actual hours X $300) Variable cost $         3,90,000 $          3,60,000
(Budgeted hours X $250) Fixed Cost $         2,75,000 $          2,25,000
Total $         6,65,000 $          5,85,000
Add a comment
Know the answer?
Add Answer to:
The IT department's cost data is as follows: Estimated Costs Fixed Costs $ 500,000 Variable, ($300...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT