Vath Corporation, which makes landing gears, has provided the following data for a recent month: Budgeted...

Vath Corporation, which makes landing gears, has provided the following data for a recent month:

Budgeted production 9,300 gears
Standard machine-hours per gear 4.0 machine-hours
Budgeted supplies cost $3.00 per machine-hour
Actual production 9,870 gears
Actual machine-hours 39,542 machine-hours
Actual supplies cost (total) $111,045


Required:

Determine the rate and efficiency variances for the variable overhead item supplies and indicate whether those variables are favorable or unfavorable.

Variable overhead rate variance
Variable overhead efficiency variance
0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Vath Corporation, which makes landing gears, has provided the following data for a recent month: Budgeted...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Buis Corporation, which makes landing gears, has provided the following data for a recent month:...

    1. Buis Corporation, which makes landing gears, has provided the following data for a recent month: Budgeted production. Standard machine-hours per gear.. Budgeted supplies cost. Actual production. Actual machine-hours.. Actual supplies cost (total). 1,200 gears 5.9 machine-hours $6.50 per machine-hour 1,300 gears 7,950 machine-hours $49,742 Required: Determine the rate and efficiency variances for the variable overhead item supplies and indicate whether those variables are favorable or unfavorable. Show your work!

  • 2. Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2,700 engines....

    2. Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2,700 engines. The standard power cost is $1.80 per machine-hour. The company's standards indicate that each engine requires 10.5 machine-hours. Actual production was 3,000 engines. Actual machine-hours were 29,750 machine-hours. Actual power cost totaled $58,537. Required: Determine the rate and efficiency variances for the variable overhead item power cost and indicate whether those variances are unfavorable or favorable. (Indicate the effect of each variance by selecting...

  • Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2,800 engines. The...

    Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2,800 engines. The standard power cost is $1.90 per machine-hour. The company's standards indicate that each engine requires 10.6 machine-hours. Actual production was 3,100 engines. Actual machine-hours were 31380 machine-hours. Actual power cost totaled $62.280. Required: Determine the rate and efficiency variances for the variable overhead item power cost and indicate whether those variances are unfavorable or favorable. (Indicate the effect of each variance by selecting "F"...

  • Bondi Corporation makes automotive engines. For the most recent month,, budgeted production was 2,500 engines. The...

    Bondi Corporation makes automotive engines. For the most recent month,, budgeted production was 2,500 engines. The standard power cost is $1.60 per machine-hour. The company's standards indicate that each engine requires 10.3 machine-hours. Actual production was 2,800 engines. Actual machine-hours were 27,750 machine-hours. Actual power cost totaled $48,058. Required: Determine the rate and efficiency variances for the variable overhead item power cost. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...

  • Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 3,400 engines. The...

    Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 3,400 engines. The standard power cost is $2.20 per machine-hour. The company's standards indicate that each engine requires 112 machine-hours. Actual production was 3,700 engines. Actual machine-hours were 39,740 machine-hours. Actual power cost totaled $89,780. Required: Determine the rate and efficiency variances for the variable overhead item power cost. (Indicate the effect of each variance by selecting "F" for favorable. "U" for unfavorable, and "None" for no...

  • Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2.500 engines. The...

    Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2.500 engines. The standard power cost is $160 per machine-hour. The company's standards indicate that each engine requires 10.3 machine-hours. Actual production was 2.800 engines. Actual machine-hours were 27750 machine-hours. Actual power cost totaled $48,058 Required: Determine the rate and efficiency variances for the variable overhead item power cost. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...

  • Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 3,500 engines. The...

    Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 3,500 engines. The standard power cost is $1.50 per machine-hour. The company's standards indicate that each engine requires 11.3 machine-hours. Actual production was 3,800 engines. Actual machine-hours were 41,340 machine-hours. Actual power cost totaled $66,642. Required: Determine the rate and efficiency variances for the variable overhead item power cost. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...

  • Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 3,500 engines. The...

    Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 3,500 engines. The standard power cost is $1.50 per machine-hour. The company's standards indicate that each engine requires 11.3 machine-hours. Actual production was 3,800 engines. Actual machine-hours were 41,340 machine-hours. Actual power cost totaled $66,642. Required: Determine the rate and efficiency variances for the variable overhead item power cost. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...

  • Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2,100 engines. The...

    Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2,100 engines. The standard power cost is $3.10 per machine-hour. The company's standards indicate that each engine requires 9.9 machine-hours. Actual production was 2,400 engines. Actual machine-hours were 22,670 machine-hours. Actual power cost totaled $74,909. Required: Determine the rate and efficiency variances for the variable overhead item power cost. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...

  • Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2,600 engines. The...

    Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 2,600 engines. The standard power cost is $1.70 per machine-hour. The company's standards indicate that each engine requires 10.4 machine-hours. Actual production was 2,900 engines. Actual machine-hours were 28,890 machine-hours. Actual power cost totaled $53,702. Required: Determine the rate and efficiency variances for the variable overhead item power cost. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT