For the set of tasks given below, do the following:

Task Task
Time(seconds)
Immediate
Predecessor
A 45 -
B 11 A
C 9 B
D 50 -
E 26 D
F 11 E
G 12 C
H 10 C
I 9 F, G, H
J 10 I
193


b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.)
  

The minimum cycle time seconds
The maximum cycle time seconds


c. Determine the minimum number of workstations for output of 500 units per day. (Round up your answer to the next whole number.)
  
Minimum number of workstations             

d. Balance the line using the greatest positional weight heuristic. Break ties with the most following tasks heuristic. Use a cycle time of 50 seconds.

Work stations Following Tasks
I   (Click to select)   C   E   D   A   B
II   (Click to select)   C   A   B   F   D
III   (Click to select)   B   A, E, C   B, E, C   A   C
IV   (Click to select)   G, H   G   F, A, G   C   G, F, H, I
V   (Click to select)   A   J   D   C   B


e. Calculate the percentage idle time for the line using the 50 second cycle time. (Round your answer to 1 decimal place. Omit the "%" sign in your response.)
  
Percentage of idle time             %

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3. A manager wants to assign tasks to workstations in order to achieve an hourly output...

    3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points) b) Assign tasks to workstations using...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the "most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points). b) Assign tasks to workstations using...

  • The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST...

    The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 18 — B 10 A C 25 B D 15 B E 14 C F 17 D G 12 E, F H 20 G The workday is 6.25 hours long. Demand for completed product is 750 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical...

  • I need help with the total idle time per cycle question, please include steps with explanations...

    I need help with the total idle time per cycle question, please include steps with explanations & Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. T Question Help he demand for the train is 4,800 units p 40-hour workweek Performance Time Task Predecessors 20 27 B, C D.E 12 This exeroise only contains parts b, c, d, e, and f b) Given the demand, the...

  • OPERATIONS AND SUPPLY CHAIN MANAGEMENT L06-4 SOLVED PROBLEM 2 TASKS THAT MUST PRECEDE TASK TIME (SECONDS)...

    OPERATIONS AND SUPPLY CHAIN MANAGEMENT L06-4 SOLVED PROBLEM 2 TASKS THAT MUST PRECEDE TASK TIME (SECONDS) 50 TASK A B С D E F G H 40 20 45 20 25 10 35 A С С D E B, F, G a. Draw the schematic diagram. b. What is the theoretical minimum number of stations required to meet a forecast demand ei 400 units per eight-hour day? c. Use the longest-task-time rule and balance the line in the minimum number...

  • TASK SECONDS TASKS THAT MUST PRECEDE A 25 — B 15 A C 20 B D...

    TASK SECONDS TASKS THAT MUST PRECEDE A 25 — B 15 A C 20 B D 29 B E 16 C F 8 D G 35 E, F H 32 G The workday is 10.5 hours long. Demand for completed product is 900 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical number of workstations required to meet the desired output rate? (Round...

  • An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 1...

    An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)    Minimum cycle time minutes Maximum cycle time minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the...

  • Hello, I need to see the solution, how they got these numbers? Will appreciate help. The...

    Hello, I need to see the solution, how they got these numbers? Will appreciate help. The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Predecessors Task A B С D E F Performance Time (seconds) 22 27 14 15 10 28 А A А B, C DE This exercise only contains parts b, c, d, e, and...

  • Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach...

    Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT