TASK |
SECONDS |
TASKS THAT |
A |
25 |
— |
B |
15 |
A |
C |
20 |
B |
D |
29 |
B |
E |
16 |
C |
F |
8 |
D |
G |
35 |
E, F |
H |
32 |
G |
The workday is 10.5 hours long. Demand for completed product is 900
per day.
a. Find the cycle time required to meet the
desired output rate. (Round your answer to 1 decimal
place.)
b. What is the theoretical number of
workstations required to meet the desired output rate?
(Round up your answer to the next whole
number.)
d. Balance the line using sequential restrictions and the longest-operating-time rule. (Leave no cells blank - be certain to enter "0" wherever required. Round your answers to 1 decimal place.)
e. What is the efficiency of the line balanced as in part (d) assuming it is running at the cycle time determined in part (a)? (Round your answer to 1 decimal place.)
f. Suppose that demand rose from 900 to 950 units per day. What would you do? (Round your answer for cycle time down to the nearest whole number.)
g. Suppose that demand rose from 900 to 1,150
units per day. What would you do? (Round your answer for
cycle time down to the nearest whole number.)
Answer a: desired output = 900 units per 10.5 hours= 10.5*60*60/240= 42 secs per unit
Hence the workstation cycle time required is 42 secs per unit
Total task time =25+15+20+29+16+18+35+32= 190 secs
Minimum no. of work station = total task time/ cycle time = 190/42 =4.5 ~5
Answer b: Theoretical minimum no. of workstation is 5
Answer c: Line balancing, required cycle time is 42 secs per workstation. Sum of task times in a workstation cannot be more than cycle time.
Workstation |
Tasks |
Idle time= Cycle time- sum of task time |
Reason |
1 |
A, B |
42-25-15= 2 |
Based on precedence |
2 |
D, F |
42-29-8= 5 |
D is the longer task than C |
3 |
C, E |
42-16-20= 6 |
There was no space for C after D |
4 |
G |
42-35= 7 |
|
5 |
H |
42-32= 10 |
Answer d: Total idle time= 2+5+6+7+10= 30 secs
Balanced delay = total idle time/ no. of workstation* cycle time = 30/(5*32)= 0.1923 ie 19.23%
Efficiency= 1-balanced delay= 80.77%
Note: Chegg's guidelines mandate to solve one question or 1st four subparts of a question at a time. Please post again for remaining questions.
The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 18 — B 10 A C 25 B D 15 B E 14 C F 17 D G 12 E, F H 20 G The workday is 6.25 hours long. Demand for completed product is 750 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) The minimum cycle...
OPERATIONS AND SUPPLY CHAIN MANAGEMENT L06-4 SOLVED PROBLEM 2 TASKS THAT MUST PRECEDE TASK TIME (SECONDS) 50 TASK A B С D E F G H 40 20 45 20 25 10 35 A С С D E B, F, G a. Draw the schematic diagram. b. What is the theoretical minimum number of stations required to meet a forecast demand ei 400 units per eight-hour day? c. Use the longest-task-time rule and balance the line in the minimum number...
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.) Minimum cycle time minutes Maximum cycle time minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the...
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.) Minimum cycle time minutes Maximum cycle time minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter...
An assembly line with 17 tasks is to be balanced. The longest task is 2.3 minutes, and the total time for all tasks is 18 minutes. The line will operate for 490 minutes per day. a. What is the minimum number of workstations needed if the output rate is to be 170 units per day? (Round the final answer to the next whole number.) Number of workstation b. What cycle time will provide an output rate of 126 units per...
Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...
Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...
A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible. Task Length (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.3 - d 1.3 b, c e 0.1 - f 0.8 e g 0.3 d, f h 1.2 g a. Do each of the following: (2) Assign...
J Packing 2.0 a-b) One of the possible assignment of tasks to workstations is shown correctly in Fig. 2. The efficiency of the assembly line with 3 workstations = 98.28 % (enter your response rounded to two decimal places). c) The goal is to have 100% efficiency. Is this possible? No d) The theoretical minimum number of workstations = 3 (round your response up to the next whole number). Teen The following table details the tasks required for Indiana-based Frank...