Question

3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- workiin & Ttelve tasks, with times and precedence requirements as shown in the following table, are to be assigned to work- statio

0 0
Add a comment Improve this question Transcribed image text
Answer #1

cycle time = 56/4 = 14 minutes

Number of workstations = task time / cycle time = 45/14 =4

Position weight

task PW
a 23
b 20
c 18
d 25
e 18
f 29
g 24
h 14

task assignment

WS Task Time Idle time
I d,f 12 2
II g,a,b 11 3
III e,c 8 6
IV h,i 14 0

2.

2.0 0 10 to {.0 Lo 2.0 0.2 0.9

Number of workstations needed = task time / cycle time = 4/1.5 =3

assignment

WS Task Time Idle time
I a,b,c 1.2 0.3
II e,d,f,g,h 1.4 0.1
III I,j,k,l 1.4 0.1

fraction idle time = 0.5 /4.5 = 0.1111

or 11.11%

Add a comment
Know the answer?
Add Answer to:
3. A manager wants to assign tasks to workstations in order to achieve an hourly output...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4. A large manufacturer of pencil sharpeners is planning to add a new sharpener, and you...

    4. A large manufacturer of pencil sharpeners is planning to add a new sharpener, and you have been asked to bal- ance the assembly line, given the following task times and precedence relationships. Assume that cycle time is 1.3 minutes per unit. Task Duration (minutes) 0.2 Immediate Follower 0.4 0.3 1.3 oooo s T 0.1 0.8 0.3 1.2 a. Do each of the following: i. Draw the precedence network. ii. Assign the tasks to workstations using the heuristic rule "Assign...

  • As part of a major plant renovation project, the industrial engineering department has been asked to...

    As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:     Task Duration (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f d. Assign tasks to workstations on the basis of greatest number of following...

  • 2. Show all the steps for the question to be worth any marks. The following table...

    2. Show all the steps for the question to be worth any marks. The following table presentss the tasks, durations, and immediate predecessors necessary to produce a particular Rroduct The required daily output is 320 units, and the working day is 8.0 hours on an assembly line. Immediate Predecessor Duration (in minutes) Activity A 0.9 B 0.7 C 0.8 Г E 0.4 В, с А, D E 0.5 0.4 G E 0.6 Н F, G 0.5 T 1.1 a. Draw...

  • EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt....

    EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt. Five hundred wagons are required per day. Production time per day is 420 minutes, and the assembly steps and times for the wagon are given in Exhibit 8.9A. Assignment: Find the balance that minimizes the number of workstations, subject to cycle time and precedence constraints SOLUTION I. Draw a precedence diagram. Exhibit 8.9B illustrates the sequential relationships identi- fied in Exhibit 8.9A. (The length...

  • Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...

    Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below: Task Time (seconds) Predecessor A 13 - B 4 A C 10 B D 10 - E 6 D F 12 E G 5 E H 6 F, G I 7 H J 5 H...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points) b) Assign tasks to workstations using...

  • Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and...

    Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the "most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points). b) Assign tasks to workstations using...

  • You have been asked to balance a flow shop assembly operation to achieve an output rate...

    You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16 hours. Task times and precedence relationships are shown in the table below: Task Predecessor Time (minutes) A -- 2 B A 4 C 7 D A, B 11 E C 9 F D 10 G E, F 7 H D, G 4 What is the cycle time in minutes? What is the theoretical number of...

  • For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A...

    For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.)    The minimum cycle...

  • A pipe bending machine used to produce ship system components was operated as follows: The perio...

    A pipe bending machine used to produce ship system components was operated as follows: The period of operation was 25 days @ 10 hrs per day. It produced 800 total pipe details, of which 40 were rejected by quality inspectors. The total setup time for the machine during the 25 days was 22 hours. The machine had 3 unplanned breakdown events 1.5 hours for a power failure 0.5 hours for computer network failure 2.2 hours for lubricant pump failure The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT